Documente Academic
Documente Profesional
Documente Cultură
Resource Allocation
Table 9-1
Activity Slopes—Cost per Period for
Crashing
Table 9-2
Crashing the Project
Figure 9-1a
Seven Day Schedule
Figure 9-1b
Six Day Schedule
Figure 9-1c
Five Day Schedule
Figure 9-1d
Four Day Schedule
Figure 9-1e
Cost-Crash Curve
Figure 9-2
The Resource Allocation Problem
Figure 9-6a
Resource B
Figure 9-6b
Resource Leveling
As soon as possible
As late as possible
Shortest task first
Most resources first
Minimum slack first
Most critical followers
Most successors
Arbitrary
Heuristic Methods Continued
1. Schedule slippage
2. Resource utilization
3. In-process inventory
Schedule Slippage
1. Optimism
2. Capacity should be equal to demand
3. The “Student Syndrome”
4. Multitasking to reduce idle time
5. Assuming network complexity makes no difference
6. Management cutting time to “motivate” workers
7. Game playing
8. Early finishes not canceling out late finishes