New Elevator Installation at Hospital Building

 Facing difficulties in installation,


operation, maintenance from the
beginning.

 Installation completed in January,2015


without completing some key safety
tasks though Elevator received on May
26,2010.

www.icddrb.org
 Unsafe installation

www.icddrb.org
 The accident of sudden trap of 14
people for more than 18 minutes
inside the elevator # 2 was a serious
indication of risk following which
management has stopped operating
the elevators.
 A number of world reputed brand
elevator companies with strong
local experience had been engaged
to modify (if required) the elevators
(for ensuring full safety) and to
operate them as their own brand.
Creative was awarded for
refurbish two Elevators since long
term solution cannot possible with
these Elevators

www.icddrb.org
 Creative Engineers awarded
for supply, Installation of
Schindler Elevator following
strict tendering process.

 Management decided to
purchase 5 nos instead of 7
Elevators.

www.icddrb.org
Ongoing Safety Projects Under Facilities Management
Project Background Start Projected
End
1. Fire Hydrant System • Pillar Hydrant System for all icddr,b premises 95 % done January Dead line is July
Installation for the • Fire hydrant box (external) will be installed all suitable 23, 23, 2016,
Hospital building and location 2016
the premise • Installation of all fire hydrant box in the Hospital building (More than 90%
completed. work done)
• Pumps installation in the Pump house for Fire Hydrant
System completed
2. Two Emergency Stairs • Emergency Stair (R C C Stair) of hospital building 95% March July 2016
construction for Hospital completed only painting and roof top works remaining 2016
Building East Side • Emergency Stair (Steel Structure ) 85% completed (More than 85%
• Covering of Steel Stair made by MS sheet instead of MS net/ work done)
Fencing
• Painting and roof top works will be done by this month
3. Fire Detection System • FADS Panel tested and found ok for Ground floor, level-5 & 8 January July 2016
Installation • Conduit cabling for other floor are done except remaining 25,
construction parts of level 4 & 7. 2016 (More than 70%
• PO awarded to NOHMI , Japan, for additional devices and work done)
expecting to get the materials by July , 2016,
• This additional materials will be installed at remaining floors
and it may take another two weeks to complete.

www.icddrb.org
Ongoing Safety Projects Under Facilities Management

Project Background Start Projected End


4. Elevator project • Top Global brand elevator companies engaged for January 2016 December 2016
supply of new elevators
• Schindler brand awarded for – supply of 5 new
elevators ensuring international safe installation
procedure (saved cost along with higher capacity and
faster in speed),- 2 existing elevator refurbishment for
interim support
5. Waste Water Treatment • Engaged specialized consultant IWM for designing January 2016 December 2016
for Matlab Health Research the waste water treatment plant
Centre • Contractor will be engaged to complete the work
after the design completion
• on June 27,2016 we have received 3 (Three) Bid
• We cal them for presentation their proposal by end of
this week . We hope we can select Vendor within the
next week and the start work.
6. A/C installation Patent • 21 A/C Installed at Matlab Hospital before Eid
care area at Matlab Vacation ,Cable installation and improvement of
Hospital electrical wiring is in progress. We also work for
Increasing power from 250 KW to 450 KW.
7. Reparing and • For 4 Sub Centre and Matlab Hospital Repairing
renovation work at Matlab works Tender in Progress we hope By the end of Next
and Chakaria week we Can Start all work .

www.icddrb.org
Installation of Fire Suppression (Hydrant) System (Background)

Diesel Engine Pump Fire Hose Reel Fire hydrant accessories


 Equipment was purchased in Year 2007 but not yet installed
 Re-initiated the installation through modified RFP process
• DNB project: design and build (final payment based on
commissioning of system)
 Key scope of works: Design the Fire Hydrant System, Prepare a
Pump House and finally install the Fire Hydrant System
 Construction of Underground Pump house
 The entire process will be completed within July 2016

www.icddrb.org
Fire Hydrant System

Construction of Pump House completed Fire Hydrant Pump Installation

Installation of Fire Pump and Fittings Installation of Zone control valve

www.icddrb.org
Fire Hydrant System

Pump Installation Completed Double Fire Hose Box Installed

Installation of Pillar Hydrant Single Fire Hose Box installed

www.icddrb.org
Two Emergency Stairs for the Hospital Building

• Two emergency stairs of the Hospital


Building (South-east and North-east sides)
85 % completed
• Different approach: Go with steel
manufacturers
• going w/ RCC will take too long
• will be 1/3 cost and better able to
withstand earthquakes
Emergency Stair (South-East)
• Contract Document is in progress
• active engagement of suppliers
Remaining 2 floor

• looking for “solutions” not “who can


best guess what we need” or “lowest
price”

• Handover the two projects by July 2016 if


change any items or modification of any
item may extend the time

Emergency Stair (North-East)

www.icddrb.org
Emergency Stair

Emergency Stair Casting at Level 9 (RCC) 95 % done Erection of Emergency Stair ( Steel)

www.icddrb.org
Installation of Fire Detection System

Control Card & Panel NOHMI Heat Detector

• Equipment purchased in Year 2007 (BTCL/NOHMI BOSAI) and 2009


(ICEL/Ziton)……but yet to be installed!
• Added to this, BTCL became barred by CPTU/icddrb in 2009
• Contacted directly with NOHMI Japan; direct agreement with Nohmi
• This saved 121 K USD materials purchased earlier and also about
another 100 K USD by avoiding purchasing of “additional” Fire Detection
System
• The entire process will be completed within 1st quarter of 2016

www.icddrb.org
Fire Detection System

Alarm
Bell

Pull
Station

Fire Detection Panel Fitting Alarm Bell & Pull Station Fitting

www.icddrb.org
Rectification of Elevators

• Extensive Market engagement:


• Who are key players/capabilities
• Learning from experts “what do we need?” (as we are NOT elevator experts)
• Only top 06 global brands: Otis, Thyssen-Krupp, Mitsibushi, Kone, Schneider,
Schindler
• RFP conclusion: Refurbishment cannot ensure full safety and long term support
services
• RFQ for new elevators: exact specifications (based on market engagement); only 5 vs.
7
• Creative Engineers (Schindler) awarded for:
• Supply of 5 NEW elevators: 1/3 of cost; 40% larger; 30% faster…1000% SAFER
• 2 SODIMAS elevators refurbishment (main hospital building entrance) interim
solution

www.icddrb.org
Temporary Solution for running 2 Elevators maintaining safety

Load distributed
Load distributed in wide area
for safety

Directly bolted on the floor in


small area

Oil pot installed on the counter


Bracket installed on brick wall after
cemented & anchored with special glue weight guide rail .

www.icddrb.org
Temporary Solution for running 2 Elevators maintaining safety (cont.)

Previous over speed governor & Newly installed suspension rod & speed governor (with
suspension rod extended support)

www.icddrb.org
Elevator for the Chiller and OPD Building

• A common elevator can serve both


requirement
• Creative/Schindler awarded this project
• Just went through extensive RFP/RFQ
• Last month year-end budget allocation
• The elevator core will be of Steel Structure
• working closely with steel company for
emergency stairs
• Creative/Schindler will have key
accountability for integrating design
• The elevator will be “machine room-less”

www.icddrb.org
Detail Engineering Assessment by BUET (Sasakawa
Part – Hospital Building)

• Special 80 ft long I-beam designed


space

• Design Review by BUET in


progress

• Strengthening might
required to protect against
earth quake

www.icddrb.org
Waste Water Treatment Plant Requirement at Matlab
Present Scenario Proposed Treatment Process

• Pre-treatment with Bar Screen


and Grease Trap & Lime Dosing

• Biological Treatment Unit

• Tertiary Treatment with


Hypochlorite Dosing
Sewerage Stabilizing Pond

Current Status
• Budget captured
• Scope define by consultant in
progress
• Target to complete by Dec 2016

Discharge to natural canal


without ensured treatment
www.icddrb.org
Planned Maintenance for Facility Improvement at Matlab &
Sub Centre and Other Areas

Matlab Hospital

• Main Hospital Patient Care Area – Repairing


• Security Boundary Protection – Earth filling below the fence

Sub centre Repairing

• 4 Sub centre – Bordia, Khadergaon, Naergaon & Turkey

Other Areas
• Teknaf and Chokoria repair and maintenance

www.icddrb.org
Completed Maintenance of Facility at Matlab MHRC

Children Ward renovated with fresh look

Secured waiting area for the attendants of Building Designated Dustbin


patients

www.icddrb.org
If you have any ?