NIA STANDARDS

AND
SPECIFICATIONS
1.2400 PSI, The mixing is 1:2:4
-2400 psi compressive strength of
concrete through testing sample -6x12
conc, cylinder-28 days old keep at
water at 100% humidity.
2 .3000 PSI, The mixing is 1:2:3

- Dam & canal structure required


compressive strength of 3000 psi
3 .Use Pongke(1x1x1) for
aggregates measurement..
4.Use Mixing Board
5.Bar dia., Splicing, hooks & spacing should
be followed..
- Used grade 40
- grade 40 means 40,000 psi.
6. Area should be clean/free from dirt
before pouring..
- such as canal slab/ flooring
- Bar flooring should be at the center.
- Used Fulcrum(calso)
7. FORMS/OR FORMWORKS SHOULD BE
SEALED W/ LUBRICANT AGENT..
- the form will not stick to concrete.
- Produced quality concrete.
- Economical
-Minimized Labor cost
8. Backfilling/Embankment properly
compacted.
- 90% compaction
- Gradual compaction( at .20,.. at
.40,..at 60 cm.)
9. Use Line(linsa) for canal alignment
and observed the canal slope & canal
curvature.
10. Used clean water for mixing of
concrete..
- Turbidity of water reduced the fc’ of
concrete.
- it will poison the concrete.
- Excessive water will result to
shrinkage of concrete.
- cracks exposed the bars to corrosion.
-Lack of water resulted to honeycomb.
CONTRACTOR’S MONTHLY
STATISTICAL REPORTS
(MSR)
Note: Compliance of MC 69 S.2017
1. Location & Key Map
2. Project Outline
3. Daily Inspector’s Report
4.Monthly Equipment Utilization
Report
5. Monthly Manpower Utilization
Report
6. Bar Chart & S-curve
7. SWA
8. Weather Chart Report
1.Location & Key Map
2. PROJECT OUTLINE
PROJECT OUTLINE/ NARRATIVE SUMMARY
Project Title :

Contract No. :

Implementing Agency

Location :

Contractor :

Date of Bidding :

Contract Effectivity :

Contract Duration :

Revised Contract Duration :

Contract Expiry Date :

Revised Contract Expiry Date :

Contract Amount :

Physical Accomplishment

Program To Date (%) :

Actual to Date (%) :

(%) Ahead of Schedule :

Time Elapsed (C.D.) :

Percent Time Elapsed (%) :

Issues and Concerns :

Action Taken :
3. Daily Inspector’s Reports
4. Monthly Equipment Utilization Schedule
PROJECT NAME :
CONTRACT NO. :
CONTRACT DESCRIPTION :
LOCATION :

MONTHLY EQUIPMENT UTILIZATION SCHEDULE


(For the period of January 1, 2016 to January 31, 2016)
Minimum EQUIPMENT UTILIZED
Mobilized at
EQUIPMENT Equipment JANUARY, 2016
Site
Required 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 Backhoe 4 4 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2 2
2 Grader 3 3 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 3 3 3 3 2 2 2 2 2
3 Dump Truck 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
4
5
6
7
8
9
10
11
12
13

CONTRACTOR NATIONAL IRRIGATION ADMINISTRATION


SUBMITTED BY: VERIFIED BY:

Proeject Manager/ Project In-charge (RIS)/


Authorized Managing Officer Residing Engineer (SRIP)
Manager, Const. Div. (PMO)
5.Monthly Manpower Utilization Report
PROJECT NAME :
CONTRACT NO. :
CONTRACT DESCRIPTION :
LOCATION :

MONTHLY MANPOWER UTILIZATION SCHEDULE


(For the period of January 1, 2016 to January 31, 2016)
ITE Minimum MANPOWER UTILIZED
Mobilized at
M DESIGNATION Manpower JANUARY, 2016
Site
NO. Required 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 Project Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 Project Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Materials Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
4 Office Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
5 Laborer 35 35 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25
6
7
8
9
10
11
12
13

CONTRACTOR NATIONAL IRRIGATION ADMINISTRATION


SUBMITTED BY: VERIFIED BY:

Project Manager/ Project In-charge (RIS)/


Authorized Managing Officer Residing Engineer (SRIP)
Manager, Const. Div. (PMO)
6. Bar Chart & S-curve
CONSTRUCTION SCHEDULE AND S-CURVE
NAME OF PROJECT :
CONTRACT NO. :
LOCATI ON :
RELATIVE CALENDAR DAYS
UNIT ORIGINAL CONTRACT
DESCRIPTION UNIT WEIGHT MARCH 2014 APRIL 2014 MAY 2014 JUNE 2014
COST (%)
QUANTITY AMOUNT 21 51 82 8
CONTRACT WORKS Plan S-Curve
100%

CANALIZATION - PHILRICE AREA


Common Exav ation cu.m. 191.07 1,061.25 202,773.04 1.77% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25%
0.27% 0.27% 0.27% 0.27% 0.27%

Earthfill w ith Compaction cu.m. 203.87 1,592.95 324,754.72 2.83% Actual S-Curve, 53.71% as of 0.80% 0.80% 0.80% 0.13% 0.10% 0.10% 0.10% 75%
4/21/14
0.28% 0.28%
2,400 psi Concrete cu.m. 5,171.81 434.52 2,247,254.88 19.60% 1.78% 1.78% 1.78% 2.00% 3.00% 3.50% 4.00% 0.50% 0.50% 0.38% 0.37%
1.96% 1.96% 1.96% 1.96% 1.96%

CHB Lining sq.m. 901.56 4,043.20 3,645,187.39 31.78% 3.18% 3.18% 3.18% 3.18% 3.18% 3.60% 4.20% 3.18% 3.18% 1.73% 50%

3.18% 3.18% 3.18% 3.20% 3.20%


Furnishing, Bending & I nst. Of RSB kg. 77.87 34,676.34 2,700,246.60 23.55% 2.14% 2.14% 2.14% 2.14% 2.14% 3.00% 3.50% 1.80% 1.55% 1.50% 1.50%
2.35% 2.35% 3.00% 3.00% 3.00%

Grouted Riprap cu.m. 4,238.53 554.00 2,348,145.62 20.47% 2.05% 2.05% 2.05% 2.05% 3.00% 3.20% 2.05% 2.05% 1.00% 0.99% 25%

2.66% 3.00% 3.00% 3.71%

TOTAL 11,468,362.24 100.00%


Periodic Acc. (%) 0.25% 7.35% 9.40% 9.40% 9.62% 11.42% 14.15% 15.70% 7.66% 7.38% 4.71% 2.96%
PLANNED
Commulative Acc. (%) 0.25% 7.61% 17.01% 26.41% 36.03% 47.44% 61.60% 77.30% 84.95% 92.33% 97.04% 100.00%
Periodic Acc. (%) 0.27% 7.76% 10.42% 11.40% 11.71% 12.15% -
ACTUAL
Commulative Acc. (%) 0.27% 8.02% 18.44% 29.85% 41.55% 53.71%

Submitted by: Inspected by: Verified by: Approved by:

Contractor PIC Division Manager Regional Manager


7. Statement of Work Accomplished
Monthly Statistical Report NO. 1
Period Covered: December 1-30,2017

NATIONAL IRRIGATION ADMINISTRATION

Nam e of Contract Diversion Works,Canalization & Protection Works Date of Effectivity Nov. 27,2017
Contract No CABTRIS-01-ASDI-ADN-IMO-2017-R Original Contract Duration 240 cd
Contractor Roim Builders & Construction Supply Revised Contract Duration
Original Contract Expiry Date July 25, 2017
Revised Contract Expiry Date
Contract Amount P 32,345,661.97

STATEMENT OF WORK ACCOMPLISHED

ORIGINAL POW WORK ACCOMPLISHMENT Weighted % Accomplishment % accomplishment

ITEM OF WORKS ACCOMPLISHMENT unit cost( Previous This Period To Date


UNIT QTY. UNIT COST 25% AMOUNT WT.% Previous This Period To Date Per Item
QTY Amount QTY Amount QTY Amount
discount)
CONTRACT WORKS
DIVERSION WORKS
3000 ps i concrete cu.m 71.09 9,364.04 7,023.03 499,267.20 1.54 - - - - - - -
Reinforcing Steel Bar kg 5,205.99 91.96 68.97 359,057.13 1.11 - - - - - - -
Boulder Riprap cu.m 14.40 5,904.49 4,428.37 63,768.49 0.20 - - - - - - -
Gravel Blanket cu.m 8.00 890.66 668.00 5,343.96 0.02 - - - - - - -
Filter Drain cu.m 3.20 1,094.13 820.60 2,625.91 0.01 - - - - - - -
2"dia. GI Pipe x 6m pc 10.00 933.66 700.25 7,002.45 0.02 - - - - - - -
18" dia. RCP pc 12.00 1,503.89 1,127.92 13,535.01 0.04 - - - - - - -
Structure Excavation cu.m 192.00 235.03 176.27 33,844.32 0.10 - - - - - - -
Structure Backfill w/ com paction cu.m 242.88 388.44 291.33 70,758.23 0.22 - - - - - - -
Steel Gate Sluice unit 1.00 416,461.50 312,346.13 312,346.13 0.97 - - - - - - -
SteEL Gate intake unit 2.00 269,655.75 202,241.81 404,483.63 1.25 - - - - - - -
CANALIZATION - - - - -
2400 PSI cu.m 4,334.18 5,605.10 4,203.83 18,220,134.24 56.33 31.65 177,401.42 31.65 177,401.42 - 0.55 0.55 0.55
Com m on Excavation Mech. cu.m 1,635.90 119.57 89.68 146,703.42 0.45 33.60 4,017.55 33.60 4,017.55 - 0.01 0.01 0.01
Backfill w/ com paction cu.m 6,125.06 718.90 539.18 3,302,479.23 10.21 - - - - - - -
Furnis hing bending & Ins t. Of RSB kg 72,099.45 86.45 64.84 4,674,748.09 14.45 1,431.05 123,714.27 1,431.05 123,714.27 - 0.38 0.38 0.38
Gravel Blanket cu.m 671.32 713.07 534.80 359,023.61 1.11 12.00 8,556.84 12.00 8,556.84 - 0.03 0.03 0.03
PROTECTION WORKS - - - - -
3000 PSI cu.m 516.00 6,498.48 4,873.86 2,514,911.76 7.78 - - - - - - -
Reinforcing Steel Bars kg 200.00 171.83 128.87 25,774.50 0.08 - - - - - - -
Gravel Blanket cu.m 206.40 709.48 532.11 109,827.50 0.34 - - - - - - -
Proc. & Ins t. Of Matres s es s et 16.00 2,357.18 1,767.89 28,286.16 0.09 - - - - - - -
Com m on Structure Excavation(Mech.) cu.m 900.00 169.18 126.89 114,196.50 0.35 - - - - - - -
Structure Backfill (Mech.) cu.m 6,800.00 196.33 147.25 1,001,283.00 3.10 - - - - - - -
Cofferdam cu.m 700.00 145.26 108.95 76,261.50 0.24 - - - - - - -
- - - - - -

TOTAL 32,345,661.97 100.00 - 313,690.08 313,690.08 - 0.97 0.97 0.97

CONTRACTOR NATIONAL IRRIGATION ADMINSTRATION

Subm itted by: Ins pected by: Verified by: Approved by: Noted by:

GERWIN G. CALO ADELINE H. MANLUNAS FERDINAND D. AMON MADANTE P. GANOTISI


Resident Engineer Project Incharge Assistant Division Manager Division Manager Regional Manager
Roim Builders &Construction Supply
8.Weather Chart Report