Documente Academic
Documente Profesional
Documente Cultură
1 OF 26
ENABLING WORKS
Site leveling including terracing :
Basic objective
• to set up the plant in a leveled ground for
smooth transportation, construction and
operation.
• To balance cutting & filling at site.
Planning of work :
The work should be planned according to the
priority and site condition.
Sequence of work :
Taking of spot levels of the existing ground.
Stripping of vegetation at the areas where filling
is to be done.
Relocation or cutting of trees (cutting to be avoided
as far as possible) 3 OF 26
ENABLING WORKS
Site leveling including terracing - Sequence of work (cont’d):
5 OF 26
ENABLING WORKS
Site leveling including terracing (cont’d):
8 OF 26
ENABLING WORKS
Site leveling including terracing (cont’d):
4) Filling of earth :
Roots, sods, wood or other organic matters shall not
be placed in the fill.
The fill material shall be laid in continuous horizontal
layers not exceeding 300 mm thickness.
Dozers and graders shall be used for spreading and
leveling the material to uniform thickness.
The fill material shall be kept slightly sloping from the
centre to the edges to avoid formation of pools during
the rains.
All large clods shall be broken up by manual laborers.
9 OF 26
ENABLING WORKS
Site leveling including terracing (cont’d):
5) Compaction of earth :
Compaction of each layer shall be carried out by
sheep foot roller capable of giving bearing
pressure of 25 kg/sq cm of foot area.
The layer of earth fill shall be compacted till the
sheep foot of the roller rises out of the ground.
Compaction of each layer may also be carried out
by a vibratory roller, 10 T power roller.
10 OF 26
ENABLING WORKS
Site leveling including terracing – Compaction of earth (cont’d):
11 OF 26
ENABLING WORKS
Site leveling including terracing – Compaction of earth (cont’d):
12 OF 26
ENABLING WORKS
Site leveling including terracing – Compaction of earth (cont’d):
6) Checking of compaction :
For filling minimum field compaction to be
achieved shall be 95% of laboratory maximum
dry density at optimum moisture content as
obtained from proctor density test.
The tolerance limit for variation of +1% and –2%
from the moisture content shall be allowed for
the fill material during compaction.
14 OF 26
ENABLING WORKS
Construction roads:
Purpose :
1) Bringing construction materials &
equipment from outside.
15 OF 26
ENABLING WORKS
Construction roads (Cont’d)
3) Transportation of excavated earth from
site to dump yard.
16 OF 26
ENABLING WORKS
Construction roads (Cont’d)
6) In plant movement of crawler/ tyre
fitted equipment from one place to
another.
17 OF 26
ENABLING WORKS
Construction roads (Cont’d)
Other features :
19 OF 26
ENABLING WORKS
Construction railways:
Purpose :
Bringing construction materials in bulk and over
dimensioned equipment from outside to project site.
20 OF 26
ENABLING WORKS
Construction railways (Cont’d)
21 OF 26
ENABLING WORKS
Construction railways (Cont’d)
Other features :
1) The standards for laying of tracks shall be same as
that for the plant permanent railway network.
storm water.
Other features :
1) The drains are planned in such a way so that
the distance between excavated pits and drain
always remain reasonable.
23 OF 26
ENABLING WORKS
Construction drains (Cont’d)
2) Construction drains are generally planned by
the side of the construction roads and railway
tracks also maximum extent in alignment of
permanent drain.
24 OF 26
ENABLING WORKS
Sewerage system during construction :
The temporary sewerage network are made for
discharging sewage generated from the laborer’s
colony, site offices etc.
The sewerage lines are generally made of uPVC
pipes, buried under the ground in a designed
slope. The sewage is transported to nearby soak
pit by gravity.
Sewerage pipes are encased while crossing the
roads, railway track etc.
25 OF 26
THANK YOU
26 OF 26