Sunteți pe pagina 1din 53

consorcio

supervisor
del centro

“MEJORAMIENTO Y AMPLIACION DE LA CAPACIDAD RESOLUTIVA


DE LOS SERVICIOS DE SALUD DEL HOSPITAL REGIONAL DANIEL A.
CARRION DEL DISTRITO DE YANACANCHA PROVINCIA DE PASCO-
PASCO"
Informe de Avance de Obra N°17
Contratista: Consorcio
de la Salud Pasco

Supervisión: Consorcio
Supervisor del Centro
VISTA PANORAMICA BLOCK 02,03,04 y 06 Av. D. A. C.

Pasco, 30 de Abril - 2017

VISTA PANORAMICA BLOCK 1 y 9 Av. Los Incas.


Ficha Técnica
DEL PROYECTO:

OBJETO DEL CONTRATO :


ELABORACION DE EXPEDIENTE TECNICO Y EJECUCION DE OBRA
DEL PIP "MEJORAMIENTO Y AMPLIACION DE LA CAPACIDAD
RESOLUTIVA DE LOS SERVICIOS DE SALUD DEL HOSPITAL
REGIONAL DANIEL A. CARRIÓN DEL DISTRITO DE YANACANCHA
PROVINCIA Y DPTO. DE PASCO"

CODIGO SNIP N° : 173538

UBICACIÓN : DISTRITO: YANACANCHA

PROVINCIA Y DPTO. DE PASCO

REGION: PASCO

ENTIDAD : GOBIERNO REGIONAL DE PASCO

FUENTE DE FINANCIAMIENTO : RECURSOS ORDINARIOS


Ficha Técnica
DEL CONTRATISTA:
PROCESO : L.P. N°011-2012-G.R.PASCO
CONTRATISTA : CONSORCIO DE LA SALUD PASCO
CONTRATO Nº : 122-2013-G.R.PASCO/PRES
FECHA DE FIRMA DEL CONTRATO : 08/03/2013
(S/. 3,228,000.00 Elb. Exp. Tec. S/. 117,030,607.36 Infraes. - S/.
MONTO DEL CONTRATO DE OBRA (ADENDA N°08) : S/. 190,973,553.52 Inc. IGV 70,714,946.16 Equip.)

PLAZO DE EJECUCION REFORMULADO : 660 Días Calendario


PLAZO DE EJECUCION INCLUIDO LA AMPLIACION DE PLAZO
: 719 Días Calendario
No. 01 (59 d.c.)
SISTEMA DE CONTRATACION-MODALIDAD : A SUMA ALZADA - LLAVE EN MANO
RESIDENTE : ING. JUAN MENDOZA TICONA
MONTO DEL ADELANTO DIRECTO : S/. 28,834,133.01 INC IGV 15.1%

FECHA DE PAGO DEL ADELANTO DIRECTO : 17-nov.-2015


MONTO DEL ADELANTO DE MATERIALES Nº 1 : S/. 16,480,000.00 INC IGV 8.78% (08 – Ene - 2016)
MONTO DEL ADELANTO DE MATERIALES Nº 2 : S/. 5,006,815.43 INC IGV 2.62% (25 – Ago - 2016)
MONTO DEL ADELANTO DE MATERIALES Nº 3 : S/. 3,945,000.00 INC IGV 2.07% (12 – Oct - 2016)
MONTO DEL ADELANTO DE MATERIALES Nº 4 : S/. 3,055,000.00 INC IGV 1.60% (12 – Oct - 2016)
MONTO DEL ADELANTO DE MATERIALES Nº 5 : S/. 14,000,000.00 INC IGV 7.46% (04 – Nov - 2016)
MONTO DEL ADELANTO DE MATERIALES Nº 6 : S/. 1,800,000.00 INC IGV 0.96% (26 – Dic - 2016)
MONTO DEL ADELANTO DE MATERIALES Nº 7 : S/. 3,562,790.00 INC IGV 1.90% -----------------------
31/08/16 (PRESENTADO
AMPLIACION DE PLAZO Nº 1 (POR 89 D. C.) : 23/08/16 (CONTRATISTA) A LA ENTIDAD)
(DENEGADO)
RER Nº 0871-
2016-GRP/GOB

AMPLIACION DE PLAZO Nº 1 (POR 59 D. C.) : Aprobado mediante Acta de Conciliación No. 014-2017,de fecha 08.03.2017
AMPLIACIÓN DE PLAZO Nº 2 (POR 10 D.C.) : Denegado mediante Resolución Ejecutiva Regional Nº 0315, de fecha 20.04.2017
FECHA DE PAGO DEL ADELANTO DE MATERIALES 1,2,3,4,5 y 6 : 08.01.2016, 25.08.2016, 12.10.2016, 12.10.2016 , 04.11.2016 y 26.12.16

FECHA DE ENTREGA DE TERRENO : 5-nov.-2015

FECHA DE INICIO DE LA OBRA : 5-dic.-2015

TERMINO DEL PLAZO CONTRACTUAL : 24-Sep.-2017


NUEVO TERMINO DE PLAZO CONTRACTUNAL INCLUIDO LA
: 22-Nov.-2017
AMPLIACION DE PLAZO No. 01 (59 d.c.)
Ficha Técnica
DEL SUPERVISOR:
PROCESO : CP.N°007-2012-G.R.PASCO

SUPERVISION : CONSORCIO SUPERVISOR DEL CENTRO

CONTRATO Nº : N°0423-2012-G.R.PASCO/PRES

FECHA DE FIRMA DE CONTRATO : 19-dic.-2012

MONTO DEL CONTRATO DE SUPERVISION : S/. 8,843,554.00 Inc. IGV

MONTO DEL ADELANTO


S/. 2,653,066.20 Inc. IGV
DIRECTO

FECHA DE ENTREGA Marzo 2013

JEFE DE SUPERVISION : ING. JESUS LECCA REYES

PLAZO DE EJECUCION : 660 Dias Calendario

SISTEMA DE
: A SUMA ALZADA
CONTRATACION
Descripción del Proyecto

La obra en referencia consta de lo siguiente:


En un área de 10,351.40m2, se construirá el Hospital Daniel Alcides Carrión,
dicha edificación consta de 01 semi-sótano y 05 niveles.
El área ocupada abarca el 56% del área del terreno y el 44% área libre, con
un área total construida de 23,822.61m2.
El área construida consta de: 12 bloques (11 bloques por construir y 01 block
por rehabilitar y construir, block 12).
Descripción del Proyecto
DISTRIBUCION DE AMBIENTES POR BLOCK
Descripción del Proyecto al 30.04.17
BLOCK 7 (Nv. +16.13)
BLOCK 9 (Nv. +25.21) BLOCK 11 (Nv. +16.13) BLOCK 12 (Nv. +16.13) ESTRUCTURAS: ESTRUCTURAS AL 100%.
OBRAS EXTERIORES
ESTRUCTURAS: AL 100%; CISTERNA AL 100%; EN EL 6° PISO COLOCACION ESTRUTURAS METALICAS PARA TECHO AL 80%. ESTRUCTURAS: AL 100% ESTRUCTURAS: AL 100% ARQUITECTURA: ASENTADO DE LADRILLO DE ARCILLA EN EL 1° Y 2° NIVEL AL 100% Y EN 3° NIVEL 95%;
ARQUITECTURA: SOLAQUEO Y PINTURA IMPRIMANTE EN CIELORRASOS EN TODOS SU NIVELES AL 100%; ASENTADO DE ARQUITECTURA: ARQUITECTURA: SOLAQUEO DE SOLAQUEADO Y PINTURA IMPRIMANTE EN CIELORRASOS 1° Y 2° NIVEL AL 100%; TARRAJEO DE MURO
INST. SANITARIAS: EXCAVACION DE
MUROS DE LADRILLO DE ARCILLA EN 1° PISO AL 40%; 2°, 3°, 4°, 5°, 6° PISO AL 100%, TARRAJEO DE MUROS EN 6° PISO AL 100%; SOLAQUEO Y PINTURA CIELORRASOS 2° PISO AL 100%; PARAPETO DE TERRAZA AL 100%; TARRAJEO DE MUROS EN EL 1° PISO AL 30%, 2° PISO AL 75%; ASENTADO
ZANJAS, COLOCACION DE TUBERIAS
VACIADO DE CONTRAPISOS INTERIORES DEL 3°, 4° Y 5° PISO AL 100%; CONTRAPISO DE AISLACION TERMICA DE TECHO DEL 6° IMPRIMANTE EN EL 1° Y 2° PSO ASENTADO DE LADRILLO DE DE LADRILLOS PARA MURO DE FACHADA 1° Y 2° AL 95%, 3° AL 90%; VACIADO DE CONTRAPISO
PVC DE DESAGUE, VACIADO DE
PISO AL 100% (1RA CAPA); IMPERMEABILIZADO DE TECHO CON GEOMENBRANA BICAPA 6° (TECHO) AL 100%; VACIADO DE AL 100%, 3° PISO AL 70%; K.K. DE ARCILLA EN EL 1° PISO IMPERMEABILIZANTE 1RA CAPA 3° PISO (AZOTEA) AL 100%; IMPERMEABILIZACION DE TECHO CON
CAJAS Y BUZONES PARA REDES
PISO TERMINADO 2DA CAPA EN 6° NIVEL (AREA DE MAQUINAS) AL 100%; TABIQUERIA INTERIOR DRYWALL RH, RF Y ST: 5° Y 4° ASENTADO DE LADRILLO DE AL 90%; 3° PISO AL 90%, 2° PISO GEOMEMBRANA BICAPA EN EL 3° NIVEL AL 80%; COLOCACION DE ESTRUTURAS METALICAS PARA ENTRE
COLECTORAS DEL SISTEMA DE
PISO AL 80%, 3° PISO AL 70%. K.K. AL 100% EN EL 1° PISO, 2° AL 20%; CONTRAPISO 3° PISO PISO PARA EQUIPOS DE AIRE ACONDICIONADO AL 100%; VACIADO DE CONTRAPISOS EN EL 2° Y 3° AL 100%;
ALCANTARILLADO ENTRE CAJAS DE
INST. SANITARIAS: COLOCACIÓN DE TUBERIAS PVC PARA MONTANTES DE DESAGUE PLUVIAL Y REDES DE DESAGUE AL 80% Y 3° AL 90%; VACIADO AL 100%; COLOCACION DE IMPERMEABILIZADO DE TECHO INCLINADO CON GEOMEMBRANA AL 90%.
REGISTRO Y BUZONES UBICADOS
PLUVIAL COLGADAS EN TECHO DEL 1°, 2°. 3°, 4° Y 5° PISO AL 100%; COLOCACIÓN DE COLGADORES (RIELES) Y TUBERIAS DE DE CONTRAPISOS 3° AL 100%. PLATAFORMA DE EXTERIORMENTE AL BLOCK 10, INST. SANITARIAS: COLOCACION DE TUBERIAS PVC PARA REDES DE DESAGUE PLUVIAL Y AIRE
COBRE DE REDES DE AGUA FRIA Y CALIENTE AL 100% EN EL 4° Y 5°, 3° AL 90%; COLOCACION DE TUBERIAS PVC Y INST. ELÉCTRICAS Y ESTRUCTURAS METALICAS AL ACONDICIONADO DE LA TERRAZA EN EL 3° PISO (COLGADOS EN EL TECHO DEL 2° PISO); MONTANTES DE
BLOCK 12, BLOCK 11 Y BLOCK 8.
ACCESORIOS PARA DESAGUE DE AIRE ACONDICIONADO DEL 6° PISO (COLGADOS EN EL TECHO DEL 5° PISO) AL 100%; COMUNICACIONES:COLOCACIO 100%. DESAGUE PLUVIAL EN EL 2° Y 3° NIVEL AL 100%; COLOCACION DE MONTANTE Y TUBERIAS PARA RED DE
INST. ELECTRICAS: TRABAJOS
COLOCACIÓN DE TUBERIAS Y ACCESORIOS DE COBRE PARA DISTRIBUCIÓN DE AGUA AL 100% EN EL 4° Y 5° PISO. N DE TUBERIAS CONDUIT Y INST. SANITARIAS: CULMINADOS CON PRUEBAS DE DESAGUE PLUVIAL COLGADAS EN TECHO DE SOTANO TECNICO AL 100%.
INST. ELÉCTRICAS: COLOCACIÓN DE BANDEJAS METÁLICAS PORTA CABLES EN EL 3°, 4° Y 5° PISO AL 100%; RESPECTO A PASES PARA INSTALACIONES COLOCACION DE TUBERIAS MEDICION DE RESISTIVIDAD PARA INSTALACIONES ELÉCTRICAS Y DE COMUNICACIONES:
ALUMBRADO, TOMACORRIENTES, LUCES DE EMERGENCIAS LA COLOCACION DE CAJAS DE PASE, TUBERIAS AL 50% EN EL 1° ELECTRICAS Y MECANICAS EN PARA DESAGUE Y VENTILACION COLOCADO DE BANDEJAS METÁLICAS EN 1° Y 2° NIVEL PARA LAS INST. ELÉCTRICAS Y DE
SISTEMA DE PUESTA A TIERRA
PISO; RESPECTO A ALUMBRADO LA COLOCACION DE CAJAS DE PASE, TUBERIAS Y CABLEADO SE ENCUENTRAN EN UN 90% EL SOTANO. EN EL 1° PISO. COMUNICACIONES; EN EL SOTANO TECNICO RESPECTO A ALUMBRADO, TOMACORRIENTES E
LONGITUDINAL MEDIANTE MALLA,
EN EL 4° PISO, 100% EN EL 5°; RESPECTO A TOMACORRIENTES NORMALES LA COLOCACION DE CAJAS DE PASE, TUBERIAS Y
ENTRE EL BLOCK 5 Y BLOCK 12; Y INTERRUPTORES: COLOCACIÓN DE CAJAS DE PASE, TUBERIAS CONDUIT Y CABLEADO AL 100%;
CABLEADO SE ENCUENTRAN EN UN 90% EN EL 4° PISO Y 100% EN EL 5°; RESPECTO A TOMACORRIENTES PARA EQUIPOS
POZO Y MALLA EXTERIOR AL 7 Y 12. COLOCACION DE LUMINARIAS AL 100%.
MEDICOS SE ENCUENTRAN EN UN 90% EN EL 4° Y 100% EN EL 5°; RESPECTO A LUCES DE EMERGENCIA LA COLOCACION DE BLOCK 10 (Nv. +4.97)
CAJAS DE PASE, TUBERIAS Y CABLEADO EN EL 5° PISO AL 100%; EN EL SOTANO TECNICO SE ENCUENTRAN SALIDAS DE ESTRUCTURAS: ESTRUCTURAS AL 100%; COLOCACION DE BLOCK 6 (Nv. +15.78)
TOMACORRIENTES Y ALUMBRADO (CABLEADOS) AL 100% Y COLOCACIÓN DE LUMINARIAS AL 100%. ESTRUCTURAS METALICAS PARA TECHO METALICO AL 100%; ESTRUCTURAS: ESTRUCTURAS AL 100%; LOSA COLABORANTE AL 100%; COLOCACIÓN DE TECHO LIGERO DE
INST. COMUNICACIONES: COLOCADO DE BANDEJAS METÁLICAS PORTA CABLES EN 3°, 4° Y 5° NIVEL AL 100%; PARA SISTEMA COLOCACION DE COBERTURA PARA TECHO AL 40%. ESTRUCTURAS METÁLICAS AL 50%.
CONTRA INCENDIO SE TIENE COLOCADOS SALIDAS PARA DETECTORES DE HUMO, SALIDA PARA PARLANTE CON LUZ ARQUITECTURA: ASENTADO DE LADRILLOS DE K.K. PARA ARQUITECTURA: SOLAQUEO, PINTURA IMPRIMANTE EN CIELORRASOS Y ASENTADO DE LADRILLO DE
ESTROBOSCOPICA, SALIDA PARA ESTACION MANUAL: COLOCACION DE CAJAS DE PASE, TUBERIAS CONDUIT Y CABLEADO MUROS EN UN 60%. ARCILLA 1°, 2°, 3° NIVEL Y AZOTEA AL 100%; TARRAJEO DE MUROS EN EL 2° AL 70%, 3° PISO AL 90% Y 4°
EN EL 4° PISO AL 70%, EN EL 5° AL 100%. INST. ELECTRICAS: COLOCACION DE PASES. (AZOTEA) AL 100%; ASENTADO DE MUROS DE LADRILLO CÍLICO CALCAREO 1° NIVEL AL 85%, 2° Y 3° NIVEL AL
INST. MECANICAS: COLOCADO DE DUCTOS METALICOS PARA AIRE ACONDICIONADO EN EL 5° PISO AL 50%. INST. SANITARIAS: COLOCACION DE TUBERIAS PVC DE 3”. 100%; VACIADO DE CONTRAPISO IMPERMEABILIZANTE 1RA CAPA EN EL 3° NIVEL (TERRAZA) Y 4° NIVEL
(AZOTEA) AL 100%; IMPERMEABILIZADO DE TECHO CON GEOMENBRANA BICAPA EN EL 4° NIVEL AL 100%;
VACIADO DE PISO TERMINADO EN 4° NIVEL AL 100%; VACIADO DE ESCENARIO DEL AUDITORIO AL 100%;
BLOCK 8 (Nv. +7.82) COLOCACION DE ESTRUCTURAS METALICAS PARA EL DESARROLLO DE MUROS PARA AUDITORIO EN UN
ESTRUCTURAS: AL 100%; ESTRUCTURAS METÁLICAS PARA TECHO 100%. 95%; VACIADO DE CONTRAPISOS 2° Y 3° AL 100%; TABIQUERIA INTERIOR DRYWALL 50% EN EL 3° PISO.
ARQUITECTURA: TARRAJEO, ASENTADO DE MUROS DE LADRILLO DE ARCILLA 2° Y 3° NIVEL AL 100%, 1° INST. SANITARIAS: INSTALACION DE COLGADORES (RIELES) PARA TUBERIAS DE COBRE DEL SISTEMA DE
NIVEL AL 90%; VACIADO DE CONTRAPISO INTERIOR 2° NIVEL AL 100%, AISLAMIENTO TERMICO ACUSTICO AGUA AL 100% EN EL 1° PISO; COLOCACION DE TUBERIAS DE COBRE PARA REDES DE AGUA FRIA Y
E IMPERMEABILIZADO DE TECHO CON GEOMENBRANA AL 100%; TABIQUERIA INTERIOR DRYWALL RH, Y CALIENTE EN EL 1° NIVEL AL 100%; COLOCACION DE TUBERIAS PVC PARA REDES Y MONTANTES DE
ST: 2° PISO AL 70%. DESAGUE PLUVIAL EN EL 1°, 2° Y 3° NIVEL AL 100%; COLOCACION DE MONTANTE Y TUBERIAS PARA RED DE
INSTALACIONES SANITARIAS: COLOCACION DE COLGADORES (RIELES) Y TUBERIAS DE COBRE PARA DESAGUE PLUVIAL COLGADAS EN TECHO DE SOTANO TECNICO AL 100%; COLOCACIÓN DE TUBERIAS PARA
REDES DE AGUA FRIA Y CALIENTE EN EL 2° NIVEL AL 100%; TUBERIAS DE COBRE PARA RED DE RED INTERNA DE DESAGUE EN EL 1° PISO EMPOTRADOS EN MUROS.
DISTRIBUCION DE AGUA EN 100%; COLOCACIÓN DE TUBERIAS PARA MONTANTES Y RED DE DESAGUE INST. ELÉCTRICAS Y DE COMUNICACIONES:
PLUVIAL AL 100%; COLOCACION DE TUBERIAS PARA RED INTERNA DE DESAGUE Y VENTILACION DEL 2° COLOCADO DE BANDEJAS METÁLICAS PORTA CABLES EN 1° NIVEL AL 100% PARA LAS INST. ELÉCTRICAS;
PISO (COLGADAS EN EL TECHO DEL 1° PISO) AL 100%; TUBERIAS PARA RED DE DESAGUE GENERAL Y INICIO DE COLOCACION DE BANDEJAS EN EL 2° NIVEL; PARA INSTALACIONES ELECTRICAS DE
RED DE SISTEMA DE AGUA EN EL 1° PISO 100%. TOMACORRIENTES, E INTERRUPTORES EMPOTRADOS EN MUROS EN EL 2° Y 3° NIVEL AL 100%; EN EL
INST. ELÉCTRICAS: COLOCADO DE BANDEJAS METÁLICAS PORTA CABLES EN 2° NIVEL AL 100%; SOTANO TECNICO RESPECTO A ALUMBRADO, TOMACORRIENTES E INTERRUPTORES: COLOCACIÓN DE
RESPECTO A ALUMBRADO LA COLOCACION DE CAJAS DE PASE, TUBERIAS Y CABLEADO SE CAJAS DE PASE, TUBERIAS CONDUIT Y CABLEADO AL 100%; COLOCACION DE LUMINARIAS AL 100%.
ENCUENTRAN EN UN 95% EN EL 2° PISO; RESPECTO A TOMACORRIENTES NORMALES LA COLOCACION DE
CAJAS DE PASE, TUBERIAS Y CABLEADO SE ENCUENTRAN EN UN 95% EN EL 2° PISO; RESPECTO A LUCES BLOCK 5 (Nv. + 20.91)
DE EMERGENCIA LA COLOCACION DE CAJAS DE PASE, TUBERIAS Y CABLEADO EN EL 2° PISO AL 95%; ESTRUCTURAS: ESTRUCTURAS AL 100%.
INSTALACION DE POZOS DE PUESTA A TIERRA PARA BAJA Y MEDIA TENSION AL 100%; DUCTOS DE ARQUITECTURA: SOLAQUEO, PINTURA IMPRIMANTE EN CIELORRASOS, ASENTADO DE
CONCRETO PARA RED DE MEDIA TENSION. LADRILLOS DE MUROS INTERIOR DEL 1° AL 6° PISO AL 100%; TARRAJEO INTERIOR DE

Av. Los Incas


INST. DE COMUNICACIONES: COLOCADO DE BANDEJAS METÁLICAS EN 2° NIVEL AL 100%; PARA SISTEMA MUROS 1° PISO AL 70%, 2° PISO AL 70%, 3° PISO AL 80%, 4° PISO AL 80%, 5° PISO AL 98%, 6°
CONTRA INCENDIO SE TIENE COLOCADOS SALIDAS PARA DETECTORES DE HUMO, SALIDA PARA PISO (AZOTEA) AL 100%; ASENTADO DE LADRILLOS DE MURO DE FACHADA EN EL 2°, 3°, 4°
PARLANTE CON LUZ ESTROBOSCOPICA, SALIDA PARA ESTACION MANUAL: COLOCACION DE CAJAS DE Y 5 PISO AL 100%; VACIADO DE CONTRAPISOS IMPERMEABILIZANTES 1RA CAPA EN 6°
PASE, TUBERIAS CONDUIT Y CABLEADO EN EL 2° PISO AL 70%. NIVEL (TECHO) AL 100%, 5° NIVEL (TERRAZAS) AL 100%; VACIADO DE CONTRAPISOS
INST. MECANICAS: COLOCADO DE DUCTOS METALICOS PARA AIRE ACONDICIONADO EN EL 2° PISO AL INTERIORES DEL 2°, 3°, 4° Y 5° PISO AL 100%; IMPERMEABILIZADO DE TECHO CON
50%. GEOMENBRANA BICAPA 6° (TECHO) AL 100%; TABIQUERIA INTERIOR DRYWALL RH, RF Y
ST: 5° PISO AL 80%, 4° AL 70%, 3° AL 65% Y 2° PISO AL 20%.
INST. SANITARIAS: INSTALACION DE COLGADORES (RIELES) PARA TUBERIAS DE COBRE
BLOCK 1 (Nv. +27.18) DEL SISTEMA DE AGUA EN EL 1°, 2°, 3°, 4° Y 5° PISO AL 100%; COLOCACION DE TUBERIAS DE
ESTRUCTURAS: AL 100% ESTRUCTURAS. COBRE EN RIELES PARA REDES DE AGUA FRIA Y CALIENTE 1°, 2°, 3°, 4° Y 5° NIVEL AL 100%;
ARQUITECTURA: SOLAQUEO, PINTURA IMPRIMANTE EN CIELORRASOS, ASENTADO DE LADRILLOS DE MUROS INTERIOR DEL 1° COLOCACIÓN DE TUBERIAS Y ACCESORIOS DE COBRE PARA DISTRIBUCIÓN DE AGUA AL
AL 6° PISO AL 100%; TARRAJEO INTERIOR DE MUROS, COLUMNAS Y PLACAS 1°, 2°, 4° PISO AL 90%, 3° Y 5° PISO AL 95%, 6° PISO AL 100% EN EL 4° Y 5° PISO; COLOCACION DE TUBERIAS PVC PARA MONTANTES Y RED DE
100% Y 7° NIVEL (AZOTEA) AL 100%; ASENTADO DE LADRILLOS DE MURO DE FACHADA EN EL1° PISO AL 70% Y 2°, 3°, 4°, 5° Y 6° DESAGUE PLUVIAL COLGADAS EN EL TECHO DEL 1°, 2°, 3°, 4° Y 5° PISO AL 100%;
PISO AL 100%; VACIADO DE CONTRAPISOS INTERIORES DEL 2°, 3°, 4°, 5° Y 6° PISO AL 100%; VACIADO DE CONTRAPISOS COLOCACION DE MONTANTE Y TUBERIAS PARA RED DE DESAGUE PLUVIAL COLGADAS EN
IMPERMEABILIZANTES 1RA CAPA (CON AISLACION TÉRMICA) EN 7° NIVEL (TECHO), 6° NIVEL (AZOTEA) Y 4° NIVEL (AZOTEA) AL TECHO DE SOTANO TECNICO AL 100%; COLOCACION DE TUBERIAS SCH-40 PARA EL
100%, IMPERMEABILIZADO DE TECHO CON GEOMENBRANA BICAPA 7° (TECHO) Y 6° (AZOTEA) AL 100%, 4° PISO (AZOTEA) AL SISTEMA DE AGUA CONTRA INCENDIOS (ACI) AL 80% EN EL 5° PISO Y 60% EN EL 4°.
100%; VACIADO DE PISOS TERMINADOS 2DA CAPA EN 7° NIVEL (TECHO), 6° (AZOTEA) AL 100%; TABIQUERIA INTERIOR DRYWALL INST. ELÉCTRICAS: COLOCACIÓN DE BANDEJAS METALICAS PORTA CABLES EN EL 1° ,3°, 4°
RH, RF Y ST: 5°, 4°, 3° PISO AL 70% Y 2° AL 20%. Y 5° PISO AL 100%; RESPECTO A ALUMBRADO LA COLOCACION DE CAJAS DE PASE,
INST. SANITARIAS: COLOCACIÓN DE COLGADORES (RIELES) Y TUBERIAS DE COBRE PARA SISTEMA DE AGUA FRIA Y CALIENTE TUBERIAS Y CABLEADO SE ENCUENTRAN EN UN 95% EN EL 4° PISO, 100% EN EL 5°;
EN EL 1°, 2°, 3°, 4° Y 5° PISO AL 100%; COLOCACIÓN DE TUBERIAS Y ACCESORIOS DE COBRE PARA DISTRIBUCIÓN DE AGUA A LOS RESPECTO A TOMACORRIENTES NORMALES LA COLOCACION DE CAJAS DE PASE,
AMBIENTES AL 100% EN EL 5° PISO, AL 50% EN EL 4° PISO; COLOCACIÓN DE TUBERIAS Y ACCESORIOS PVC PARA MONTANTES Y TUBERIAS Y CABLEADO SE ENCUENTRAN EN UN 30% EN EL 3° PISO, 95% EN EL 4° PISO Y
REDES DE DESAGUE PLUVIAL Y DESAGUE DE AIRE ACONDICIONADO DEL 1°, 2°, 3°, 4°, 5° Y 6° PISO AL 100%; COLOCACION DE 100% EN EL 5°; RESPECTO A TOMACORRIENTES PARA EQUIPOS MEDICOS SE ENCUENTRAN
TUBERIAS PVC PARA DESAGUE INTERIOR Y DE VENTILACION DEL 5° PISO AL 100% Y DEL 4° AL 80%; COLOCACION DE TUBERIAS EN UN 95% EN EL 4° Y 100% EN EL 5°; RESPECTO A LUCES DE EMERGENCIA LA
SCH-40 PARA EL SISTEMA DE AGUA CONTRA INCENDIOS (ACI) AL 50% EN EL 5° PISO. COLOCACION DE CAJAS DE PASE, TUBERIAS Y CABLEADO EN EL 5° PISO AL 100%;EN EL
INST. ELÉCTRICAS: COLOCACIÓN DE BANDEJAS METÁLICAS PORTA CABLES AL 100% EN EL 1°, 2°, 3°, 4° Y 5° PISO; RESPECTO A SOTANO TECNICO RESPECTO A ALUMBRADO, TOMACORRIENTES E INTERRUPTORES:
ALUMBRADO LA COLOCACION DE CAJAS DE PASE, TUBERIAS Y CABLEADO SE ENCUENTRAN EN UN 40% EN EL 3° PISO, AL 90% COLOCACIÓN DE CAJAS DE PASE, TUBERIAS CONDUIT Y CABLEADO AL 100%;
EN EL 4° PISO, 100% EN EL 5°; RESPECTO A TOMACORRIENTES NORMALES LA COLOCACION DE CAJAS DE PASE, TUBERIAS Y COLOCACION DE LUMINARIAS AL 100%.
CABLEADO SE ENCUENTRAN EN UN 40% EN EL 3° PISO, AL 90% EN EL 4° PISO Y 100% EN EL 5°; RESPECTO A TOMACORRIENTES INST. COMUNICACIONES: COLOCACIÓN DE BANDEJAS METALICAS PORTA CABLES EN EL
PARA EQUIPOS MEDICOS SE ENCUENTRAN EN UN 90% EN EL 4° Y 100% EN EL 5°; RESPECTO A LUCES DE EMERGENCIA LA
COLOCACION DE CAJAS DE PASE, TUBERIAS Y CABLEADO EN EL 4° PISO AL 70% Y EN EL 5° PISO AL 100%. Av. Daniel A. Carrión 1°, 3°, 4° Y 5° PISO AL 100%, INICIO EN EL 2°; PARA SISTEMA CONTRA INCENDIO SE TIENE
COLOCADOS SALIDAS PARA DETECTORES DE HUMO, SALIDA PARA PARLANTE CON LUZ
INST. COMUNICACIONES: COLOCADO DE BANDEJAS METÁLICAS PORTA CABLES EN 1°, 3°, 4° Y 5° NIVEL AL 100%; PARA SISTEMA ESTROBOSCOPICA, SALIDA PARA ESTACION MANUAL: COLOCACION DE CAJAS DE PASE,
CONTRA INCENDIO SE TIENE COLOCADOS SALIDAS PARA DETECTORES DE HUMO, SALIDA PARA PARLANTE CON LUZ TUBERIAS CONDUIT Y CABLEADO EN EL 4° PISO AL 80%, EN EL 5° AL 100%.
ESTROBOSCOPICA, SALIDA PARA ESTACION MANUAL: COLOCACION DE CAJAS DE PASE, TUBERIAS CONDUIT Y CABLEADO EN
EL 4° PISO AL 60%, EN EL 5° AL 90%.
INST. MECANICAS: COLOCADO DE DUCTOS METALICOS PARA AIRE ACONDICIONADO EN EL 5° PISO AL 60%.
BLOCK 3 (Nv. +13.70) BLOCK 4 (Nv. +13.70)
ESTRUCTURAS: AL 100%; TECHO LIGERO DE ESTRUCT. METÁLICA AL 50% ESTRUCTURAS: AL 100%.
ARQUITECTURA: SOLAQUEO Y PINTURA IMPRIMANTE EN CIELORRASOS 1°, 2° Y 3° ARQUITECTURA: SOLAQUEO Y PINTURA IMPRIMANTE EN CIELORRASOS 1° y
AISLADORES SÍSMICOS BLOCK 2 (Nv. +13.70) NIVEL AL 100%; ASENTADO DE MUROS DE LADRILLO SILICO CALCAREO 3° Y 2° NIVEL 2° Y 3° NIVEL AL 100; ASENTADO DE MUROS DE LADRILLO CILICO
(instalados los 158, ESTRUCTURAS: AL 100%; TECHO LIGERO DE ESTRUCT. METÁLICA AL 50% AL 100% Y 1° AL 90%; VACIADO DE CONTRAPISOS INTERIORES DEL 2° Y 3° AL 100%; CALCAREO 1° NIVEL AL 90%, 2° , 3° AL 100%; VACIADO DE CONTRAPISOS
deslizadores 28) ARQUITECTURA:SOLAQUEO Y PINTURA IMPRIMANTE EN CIELORRASOS 1°, 2° y 3° NIVEL AL
TABIQUERIA INTERIOR DRYWALL AL 50%; IMPERMEABILIZADO DE TECHO CON INTERIORES DEL 2° Y 3° AL 100%; TABIQUERIA INTERIOR DRYWALL AL 50%; SOTANO TÉCNICO (Nv. -2.07)
*CONCLUIDO 100%; ASENTADO DE MUROS DE LADRILLO SILICO CALCAREO 1°, 2°, 3° PISO AL 100%;
GEOMEMBRANA AL 20%. IMPERMEABILIZADO DE TECHO CON GEOMEMBRANA AL 100%.
ASENTADO DE LADRILLOS DE MURO INTERIOR AL 100% EN EL 1° PISO; VACIADO DE
INST. SANITARIAS: COLOCACIÓN DE TUBERIAS PARA MONTANTES Y REDES DE INSTALACIONES SANITARIAS: COLOCACIÓN DE TUBERIAS PARA INST. SANITARIAS: TUBERÍAS PARA RED DE
CONTRAPISOS INTERIORES DEL 2° Y 3°; TABIQUERIA INTERIOR DRYWALL RH, RF Y ST AL 50%;
DESAGUE PLUVIAL EN EL 1°, 2° Y 3° PISO AL 100%; COLOCACION DE MONTANTE MONTANTES Y REDES DE DESAGUE PLUVIAL EN EL 1°, 2° Y 3° PISO AL 100%; DESAGUE PLUVIAL QUE RECOGEN DE LAS
IMPERMEABILIZADO DE TECHO CON GEOMEMBRANA AL 100%.
PRINCIPAL Y TUBERIAS PARA RED DE DESAGUE PLUVIAL COLGADAS EN TECHO DE COLOCACION DE MONTANTE Y TUBERIAS PARA RED DE DESAGUE PLUVIAL MONTANTES DE LOS PISOS SUPERIORES AL
INSTALACIONES SANITARIAS: COLOCACION DE TUBERIAS DE COBRE EN RIELES PARA SOTANO TECNICO AL 100%; COLOCACION EN EL 3° NIVEL TUBERIAS DE COBRE EN COLGADAS EN TECHO DE SOTANO TECNICO AL 100%; COLOCACION EN EL 100%; TUBERIAS DE DESAGUE PARA LINEA
SISTEMA DE AGUA EN EL 2° PISO AL 70% Y EN EL 3° AL 100%; COLOCACION DE TUBERIAS
RIELES PARA SISTEMA DE AGUA AL 100%; COLOCACIÓN DE TUBERÍAS DE COBRE 2° NIVEL TUBERIAS DE COBRE EN RIELES PARA SISTEMA DE AGUA AL 50% DE IMPULSIÓN AL 80%; COLOCACION DE
PARA DISTRIBUCION DEL SISTEMA DE AGUA EN EL 3° AL 85%; COLOCACIÓN DE TUBERIAS
PARA DISTRIBUCIÓN DE AGUA EN AMBIENTES EN EL 3° PISO AL 75%; SISTEMA DE Y EN EL 3° AL 100%; COLOCACIÓN DE TUBERÍAS DE COBRE PARA ELECTROBOMBAS DE POZOS SUMIDEROS
PARA MONTANTES Y REDES DE DESAGUE PLUVIAL EN EL 1°, 2° Y 3° PISO AL 100%;
DESAGUE Y VENTILACION EN EL 3° PISO AL 30%. DISTRIBUCIÓN DE AGUA EN EL 3° EN UN 75%; COLOCACION DE TUBERIAS EN EJECUCIÓN.
COLOCACION DE MONTANTE Y DE TUBERIAS PARA RED DE DESAGUE PLUVIAL COLGADAS EN PARA EL SISTEMA DE DESAGUE Y VENTILACION EN EL 3° AL 30%.
INST. ELÉCTRICAS: COLOCADO DE BANDEJAS METÁLICAS PORTA CABLES AL 100% INST. ELECTRICAS: SALIDAS DE
TECHO DE SOTANO TECNICO AL 100%; COLOCACION DE TUBERIAS PARA RED INTERNA DE EN EL 1°, 2° Y 3° NIVEL; RESPECTO A ALUMBRADO Y TOMACORRIENTES EN INST. ELÉCTRICAS: COLOCADO DE BANDEJAS METÁLICAS EN 1°, 2° Y 3° AL
DESAGUE DEL 2° PISO AL 100%. TOMACORRIENTES Y ALUMBRADO CON
COLOCACION DE CAJAS METALICAS Y TUBERIAS AL 60% EN EL 3° PISO; COLOCACION 100%; CAJAS DE PASE EN EL 1°; RESPECTO A ALUMBRADO Y COLOCACION DE TUBERIAS, CAJAS DE
INST. ELÉCTRICAS: COLOCADO DE BANDEJAS METÁLICAS PORTA CABLES AL 100% EN EL 1°,
DE CAJAS METALICAS AL 100% EN EL 1° PISO; EN EL SOTANO TECNICO RESPECTO A TOMACORRIENTES AL 505 EN EL 3° PISO; EN EL SOTANO TECNICO PASE, CURVAS ELECTRICAS Y RESPECTIVOS
2° Y 3° NIVEL; RESPECTO A ALUMBRADO Y TOMACORRIENTES COLOCACION DE CAJAS DE
ALUMBRADO, TOMACORRIENTES E INTERRUPTORES: COLOCACIÓN DE CAJAS DE RESPECTO A ALUMBRADO, TOMACORRIENTES E INTERRUPTORES: ACCSESORIOS Y CABLEADOS AL 100%;
PASE Y TUBERIAS AL 60% EN EL 3° PISO, CAJAS DE PASE AL 100% EN EL 1° PISO.
PASE, TUBERIAS CONDUIT Y CABLEADO AL 100%; COLOCACION DE LUMINARIAS AL COLOCACIÓN DE CAJAS DE PASE, TUBERIAS CONDUIT Y CABLEADO AL COLOCACION DE LUMINARIA AL 100%.
INST. DE COMUNICACIONES: COLOCADO DE BANDEJAS METÁLICAS PORTA CABLES AL 100%
100%. 100%; COLOCACION DE LUMINARIAS AL 100%. INST. DE COMUNICACIONES: COLOCACION
EN EL 1°, 2° Y 3° NIVEL; COLOCACION DE CAJAS DE PASE Y TUBERIAS CONDUIT PARA
INST. DE COMUNICACIONES: COLOCADO DE BANDEJAS METÁLICAS PORTA CABLES INST. DE COMUNICACIONES: COLOCACION DE CAJAS DE PASE EN NEL 2° Y DE BAMDEJAS METALICAS AL 80%.
DETECTORES DE HUMO AL 100% EN EL 1° NIVEL, 2° Y 3° PISO AL 20%.
AL 100% EN EL 1°, 2° Y 3° NIVEL. 3° PISO.
CURVA DE AVANCE DE OBRA
110%
AVANCE ACUMULADO DE ESTRUCTURAS
100%
PROGRAMADO EJECUTADO
90%
80%
70%
% AVANCE ACUMULADO

60%
50% AVANCE
40% AVANCE PROGRAMADA
30% REAL 88.83 %
20% 96.72 %
10%
0%
-10%
feb.-16

feb.-17
dic.-15

abr.-16

nov.-16

dic.-16

abr.-17
ene.-16

mar.-16

may.-16

sep.-16

mar.-17
jun.-16

ago.-16
jul.-16

oct.-16

ene.-17
ESTRUCTURAS
VALORIZACIONES DE OBRA PROGRAMADA VALORIZACIONES DE OBRA REAL
TOTALES PORCENTAJES TOTALES PORCENTAJES SITUACION DE LA OBRA
N° PERIODO
(S/.) (%) (S/.) (%)
PARCIAL ACUM. (A) PARCIAL ACUM. PARCIAL ACUM. (B) PARCIAL ACUM. OBRA %

1.00 dic-15 382,284.83 382,284.83 1.09% 1.09% 699,684.67 699,684.67 1.99% 1.99% ADELANTADA 83.03%
2.00 ene-16 911,617.05 1,293,901.88 2.59% 3.68% 970,818.78 1,670,503.45 2.76% 4.75% ADELANTADA 29.11%
3.00 feb-16 994,587.18 2,288,489.05 2.83% 6.51% 1,324,741.19 2,995,244.64 3.77% 8.52% ADELANTADA 30.88%
4.00 mar-16 1,124,613.78 3,413,102.83 3.20% 9.71% 1,612,244.73 4,607,489.37 4.58% 13.10% ADELANTADA 34.99%
5.00 abr-16 1,446,024.81 4,859,127.64 4.11% 13.82% 2,233,355.77 6,840,845.14 6.35% 19.45% ADELANTADA 40.78%
6.00 may-16 2,239,786.23 7,098,913.86 6.37% 20.19% 1,893,270.75 8,734,115.89 5.38% 24.84% ADELANTADA 23.03%
7.00 jun-16 2,494,941.29 9,593,855.15 7.09% 27.28% 2,330,701.16 11,064,817.05 6.63% 31.46% ADELANTADA 15.33%
8.00 jul-16 2,714,995.00 12,308,850.15 7.72% 35.00% 1,656,611.83 12,721,428.88 4.71% 36.17% ADELANTADA 3.35%
9.00 ago-16 2,844,567.76 15,153,417.91 8.09% 43.09% 4,403,351.12 17,124,780.00 12.52% 48.70% ADELANTADA 13.01%
10.00 sep-16 2,910,475.25 18,063,893.16 8.28% 51.37% 4,877,463.40 22,002,243.40 13.87% 62.56% ADELANTADA 21.80%
11.00 oct-16 3,155,986.03 21,219,879.19 8.97% 60.34% 3,248,331.02 25,250,574.42 9.24% 71.80% ADELANTADA 18.99%
12.00 nov-16 2,333,557.79 23,553,436.98 6.64% 66.98% 4,215,176.47 29,465,750.89 11.99% 83.79% ADELANTADA 25.10%
13.00 dic-16 2,114,286.74 25,667,723.71 6.01% 72.99% 1,666,255.40 31,132,006.29 4.74% 88.53% ADELANTADA 21.29%
14.00 ene-17 1,666,139.46 27,333,863.18 4.74% 77.73% 1,004,307.44 32,136,313.73 2.86% 91.38% ADELANTADA 17.57%
15.00 feb-17 1,265,503.30 28,599,366.48 3.60% 81.32% 676,964.43 32,813,278.16 1.92% 93.31% ADELANTADA 14.73%
16.00 mar-17 1,396,945.35 29,996,311.83 3.97% 85.30% 631,372.93 33,444,651.09 1.80% 95.10% ADELANTADA 11.50%
17.00 abr-17 1,243,477.36 31,239,789.19 3.54% 88.83% 569,394.81 34,014,045.90 1.62% 96.72% ADELANTADA 8.88%
TOTAL 35,167,240.68 34,014,045.90
CURVA DE AVANCE DE OBRA
AVANCE ACUMULADO DE ARQUITECTURA
110%
100%
PROGRAMADO EJECUTADO
90%
80%
70% AVANCE
% AVANCE ACUMULADO

60% PROGRAMADA
50% 91.04 %
AVANCE
40%
30%
REAL
20% 24.56 %
10%
0%
-10%
feb.-16

abr.-16

nov.-16

feb.-17

abr.-17
dic.-15

jun.-16

dic.-16
ene.-16

sep.-16

ene.-17
mar.-16

may.-16

oct.-16

mar.-17
jul.-16

ago.-16
ARQUITECTURA
VALORIZACIONES DE OBRA PROGRAMADA VALORIZACIONES DE OBRA REAL
TOTALES PORCENTAJES TOTALES PORCENTAJES SITUACION DE LA OBRA
N° PERIODO
(S/.) (%) (S/.) (%)
PARCIAL ACUM. (A) PARCIAL ACUM. PARCIAL ACUM. (B) PARCIAL ACUM. OBRA %

1.00 dic-15
2.00 ene-16
3.00 feb-16
4.00 mar-16
5.00 abr-16 97,978.84 97,978.84 0.41% 0.41%
6.00 may-16 540,928.64 638,907.48 2.26% 2.67%
7.00 jun-16 726,306.08 1,365,213.55 3.04% 5.71% 94,985.02 94,985.02 0.40% 0.40% ATRASADA 93.04%
8.00 jul-16 1,264,217.41 2,629,430.96 5.28% 10.99% 30,430.63 125,415.65 0.13% 0.52% ATRASADA 95.23%
9.00 ago-16 2,291,116.63 4,920,547.59 9.58% 20.57% 53,682.75 179,098.40 0.22% 0.75% ATRASADA 96.36%
10.00 sep-16 3,972,923.46 8,893,471.05 16.61% 37.17% 64,742.71 243,841.11 0.27% 1.02% ATRASADA 97.26%
11.00 oct-16 4,475,684.88 13,369,155.93 18.71% 55.88% 109,231.23 353,072.34 0.46% 1.48% ATRASADA 97.36%
12.00 nov-16 2,808,819.70 16,177,975.64 11.74% 67.62% 360,366.45 713,438.79 1.51% 2.98% ATRASADA 95.59%
13.00 dic-16 1,997,519.76 18,175,495.39 8.35% 75.97% 344,230.78 1,057,669.57 1.44% 4.42% ATRASADA 94.18%
14.00 ene-17 881,877.87 19,057,373.26 3.69% 79.66% 1,177,710.58 2,235,380.15 4.92% 9.34% ATRASADA 88.27%
15.00 feb-17 647,982.13 19,705,355.39 2.71% 82.37% 599,633.05 2,835,013.20 2.51% 11.85% ATRASADA 85.61%
16.00 mar-17 775,569.59 20,480,924.99 3.24% 85.61% 1,886,860.49 4,721,873.69 7.89% 19.74% ATRASADA 76.95%
17.00 abr-17 1,299,788.93 21,780,713.91 5.43% 91.04% 1,153,263.21 5,875,136.90 4.82% 24.56% ATRASADA 73.03%
TOTAL 23,923,401.59 5,875,136.90
CURVA DE AVANCE DE OBRA
AVANCE ACUMULADO DE INSTALACIONES SANITARIAS
110%
100%
90% AVANCE
80% PROGRAMADA
70% AVANCE 37.44 %
% AVANCE ACUMULADO

PROGRAMADO EJECUTADO
60% REAL
50%
20.37 %
40%
30%
20%
10%
0%
-10%
feb.-16

feb.-17
dic.-15

abr.-16

nov.-16

dic.-16

abr.-17
ene.-16

mar.-16

may.-16

jun.-16

ago.-16

sep.-16

oct.-16

ene.-17

mar.-17
jul.-16
INSTALACIONES SANITARIAS
VALORIZACIONES DE OBRA PROGRAMADA VALORIZACIONES DE OBRA REAL
TOTALES PORCENTAJES TOTALES PORCENTAJES SITUACION DE LA OBRA
N° PERIODO
(S/.) (%) (S/.) (%)
PARCIAL ACUM. (A) PARCIAL ACUM. PARCIAL ACUM. (B) PARCIAL ACUM. OBRA %

1.00 dic-15
2.00 ene-16
3.00 feb-16
4.00 mar-16
5.00 abr-16
6.00 may-16 71,030.73 71,030.73 1.19% 1.19%
7.00 jun-16 123,769.16 194,799.89 2.07% 3.26% 16,053.95 16,053.95 0.27% 0.27% ATRASADA 91.76%
8.00 jul-16 151,314.90 346,114.79 2.53% 5.79% 21,133.43 37,187.38 0.35% 0.62% ATRASADA 89.26%
9.00 ago-16 164,063.96 510,178.75 2.74% 8.53% 4,455.43 41,642.81 0.07% 0.70% ATRASADA 91.84%
10.00 sep-16 127,248.48 637,427.23 2.13% 10.66% 2,608.15 44,250.96 0.04% 0.74% ATRASADA 93.06%
11.00 oct-16 96,374.42 733,801.64 1.61% 12.27% 10,151.10 54,402.06 0.17% 0.91% ATRASADA 92.59%
12.00 nov-16 128,560.28 862,361.92 2.15% 14.42% 13,810.34 68,212.40 0.23% 1.14% ATRASADA 92.09%
13.00 dic-16 194,384.76 1,056,746.68 3.25% 17.67% 0.00 68,212.40 0.00% 1.14% ATRASADA 93.55%
14.00 ene-17 259,687.29 1,316,433.97 4.34% 22.01% 46,087.13 114,299.53 0.77% 1.91% ATRASADA 91.32%
15.00 feb-17 355,198.31 1,671,632.27 5.94% 27.95% 341,339.50 455,639.03 5.71% 7.62% ATRASADA 72.74%
16.00 mar-17 338,689.41 2,010,321.68 5.66% 33.61% 333,270.20 788,909.23 5.57% 13.19% ATRASADA 60.76%
17.00 abr-17 229,157.83 2,239,479.51 3.83% 37.44% 429,868.25 1,218,777.48 7.19% 20.37% ATRASADA 45.58%
TOTAL 5,981,776.93 1,218,777.48
CURVA DE AVANCE DE OBRA
AVANCE ACUMULADO DE INSTALACIONES ELÉCTRICAS
110%
100%
90% AVANCE
PROGRAMADO EJECUTADO PROGRAMADA
80%
AVANCE 49.48 %
70%
% AVANCE ACUMULADO

60%
REAL
50% 24.35 %
40%
30%
20%
10%
0%
-10%
dic.-15

feb.-16

sep.-16

nov.-16

dic.-16

feb.-17
mar.-16

abr.-16

mar.-17

abr.-17
ene.-16

jun.-16

ago.-16

ene.-17
may.-16

jul.-16

oct.-16
INSTALACIONES ELECTRICAS
VALORIZACIONES DE OBRA PROGRAMADA VALORIZACIONES DE OBRA REAL
TOTALES PORCENTAJES TOTALES PORCENTAJES SITUACION DE LA OBRA
N° PERIODO
(S/.) (%) (S/.) (%)
PARCIAL ACUM. (A) PARCIAL ACUM. PARCIAL ACUM. (B) PARCIAL ACUM. OBRA %

1.00 dic-15
2.00 ene-16
3.00 feb-16
4.00 mar-16
5.00 abr-16
6.00 may-16
7.00 jun-16
8.00 jul-16
9.00 ago-16
10.00 sep-16 13,397.29 13,397.29 0.15% 0.15% ADELANTADA
11.00 oct-16 34,256.39 34,256.39 0.39% 0.39% 0.00 13,397.29 0.00% 0.15% ATRASADA 60.89%
12.00 nov-16 688,351.58 722,607.96 7.88% 8.27% 0.00 13,397.29 0.00% 0.15% ATRASADA 98.15%
13.00 dic-16 1,053,969.24 1,776,577.20 12.06% 20.33% 0.00 13,397.29 0.00% 0.15% ATRASADA 99.25%
14.00 ene-17 778,709.89 2,555,287.09 8.91% 29.24% 92,656.37 106,053.66 1.06% 1.21% ATRASADA 95.85%
15.00 feb-17 522,471.35 3,077,758.44 5.98% 35.22% 480,382.14 586,435.80 5.50% 6.71% ATRASADA 80.95%
16.00 mar-17 389,668.80 3,467,427.24 4.46% 39.68% 652,627.61 1,239,063.41 7.47% 14.18% ATRASADA 64.27%
17.00 abr-17 856,370.51 4,323,797.75 9.80% 49.48% 888,733.02 2,127,796.43 10.17% 24.35% ATRASADA 50.79%
TOTAL 8,737,900.94 2,127,796.43
CURVA DE AVANCE DE OBRA
AVANCE ACUMULADO DE INSTALACIONES MECÁNICAS
110%
100%
90%
PROGRAMADO EJECUTADO
80%
70%
% AVANCE ACUMULADO

60% AVANCE
50% PROGRAMADA
40% AVANCE 21.64 %
30% REAL
20% 1.86 %
10%
0%
-10%
dic.-15

feb.-16

feb.-17
abr.-16

nov.-16

dic.-16

abr.-17
ene.-16

mar.-16

may.-16

ago.-16

sep.-16

mar.-17
jun.-16

jul.-16

oct.-16

ene.-17
INSTALACIONES MECANICAS
VALORIZACIONES DE OBRA PROGRAMADA VALORIZACIONES DE OBRA REAL
TOTALES PORCENTAJES TOTALES PORCENTAJES SITUACION DE LA OBRA
N° PERIODO
(S/.) (%) (S/.) (%)
PARCIAL ACUM. (A) PARCIAL ACUM. PARCIAL ACUM. (B) PARCIAL ACUM. OBRA %

1.00 dic-15
2.00 ene-16
3.00 feb-16
4.00 mar-16
5.00 abr-16
6.00 may-16
7.00 jun-16
8.00 jul-16
9.00 ago-16
10.00 sep-16
11.00 oct-16
12.00 nov-16
13.00 dic-16 59,999.94 59,999.94 0.42% 0.42% 0.00 0.00 0.00% 0.00% ATRASADA 100.00%
14.00 ene-17 273,448.19 333,448.13 1.92% 2.35% 0.00 0.00 0.00% 0.00% ATRASADA 100.00%
15.00 feb-17 528,478.79 861,926.93 3.72% 6.06% 0.00 0.00 0.00% 0.00% ATRASADA 100.00%
16.00 mar-17 915,802.42 1,777,729.35 6.44% 12.51% 0.00 0.00 0.00% 0.00% ATRASADA 100.00%
17.00 abr-17 1,298,510.99 3,076,240.34 9.14% 21.64% 264,053.25 264,053.25 1.86% 1.86% ATRASADA 91.42%
TOTAL 14,213,019.11 264,053.25
CURVA DE AVANCE DE OBRA
AVANCE ACUMULADO DE INSTALACIONES DE COMUNICACIONES
110%
100%
90%
80%
PROGRAMADO EJECUTADO
70%
% AVANCE ACUMULADO

60% AVANCE
50% REAL
40% AVANCE 13.6 %
30% PROGRAMADA
20% 6.28 %
10%
0%
-10% abr.-16

abr.-17
sep.-16

nov.-16
feb.-16

feb.-17
dic.-15

dic.-16
ene.-16

ago.-16

ene.-17
mar.-16

may.-16

oct.-16

mar.-17
jun.-16

jul.-16
INSTALACIONES DE COMUNICACIONES
VALORIZACIONES DE OBRA PROGRAMADA VALORIZACIONES DE OBRA REAL
TOTALES PORCENTAJES TOTALES PORCENTAJES SITUACION DE LA OBRA
N° PERIODO
(S/.) (%) (S/.) (%)
PARCIAL ACUM. (A) PARCIAL ACUM. PARCIAL ACUM. (B) PARCIAL ACUM. OBRA %

1.00 dic-15
2.00 ene-16
3.00 feb-16
4.00 mar-16
5.00 abr-16
6.00 may-16
7.00 jun-16
8.00 jul-16
9.00 ago-16
10.00 sep-16
11.00 oct-16
12.00 nov-16
13.00 dic-16
14.00 ene-17 112,171.37 112,171.37 1.01% 1.01% ADELANTADA
15.00 feb-17 610,046.19 722,217.56 5.47% 6.47% ADELANTADA
16.00 mar-17 262,215.95 262,215.95 2.35% 2.35% 557,672.97 1,279,890.53 5.00% 11.47% ADELANTADA 388.11%
17.00 abr-17 437,897.93 700,113.88 3.93% 6.28% 237,572.43 1,517,462.96 2.13% 13.60% ADELANTADA 116.75%
TOTAL 11,155,141.58 1,517,462.96
CURVA DE AVANCE DE OBRA
AVANCE ACUMULADO DE EQUIPAMIENTO BIOMEDICO
110%
100%
90%
80%
PROGRAMADO EJECUTADO AVANCE
70% REAL
AVANCE
% AVANCE ACUMULADO

60% 53.03 %
PROGRAMADA
50% 9.30 %
40%
30%
20%
10%
0%
-10%
feb.-16

feb.-17
dic.-15

abr.-16

nov.-16

dic.-16

abr.-17
ene.-16

ago.-16

oct.-16

ene.-17
mar.-16

sep.-16

mar.-17
jun.-16

jul.-16
may.-
16
EQUIPAMIENTO BIOMEDICO
VALORIZACIONES DE OBRA PROGRAMADA VALORIZACIONES DE OBRA REAL
TOTALES PORCENTAJES TOTALES PORCENTAJES SITUACION DE LA OBRA
N° PERIODO
(S/.) (%) (S/.) (%)
PARCIAL ACUM. (A) PARCIAL ACUM. PARCIAL ACUM. (B) PARCIAL ACUM. OBRA %

1.00 dic-15
2.00 ene-16
3.00 feb-16
4.00 mar-16
5.00 abr-16
6.00 may-16
7.00 jun-16
8.00 jul-16 7,058,041.70 7,058,041.70 11.78% 11.78% ADELANTADA 100.00%
9.00 ago-16 0.00 7,058,041.70 0.00% 11.78% NO PROG. 100.00%
10.00 sep-16 0.00 7,058,041.70 0.00% 11.78% NO PROG. 100.00%
11.00 oct-16 4,162,783.45 11,220,825.15 6.95% 18.72% ADELANTADA 100.00%
12.00 nov-16 1,783,650.40 13,004,475.55 2.98% 21.70% ADELANTADA 100.00%
13.00 dic-16 6,578,773.03 19,583,248.58 10.98% 32.68% ADELANTADA 100.00%
14.00 ene-17 599,279.20 599,279.20 1.00% 1.00% 788,778.17 20,372,026.75 1.32% 33.99% ADELANTADA 3299.42%
15.00 feb-17 1,498,198.01 2,097,477.22 2.50% 3.50% 2,777,864.91 23,149,891.66 4.64% 38.63% ADELANTADA 1003.70%
16.00 mar-17 1,677,981.77 3,775,458.99 2.80% 6.30% 2,052,179.30 25,202,070.96 3.42% 42.05% ADELANTADA 567.52%
17.00 abr-17 1,797,837.61 5,573,296.61 3.00% 9.30% 6,574,825.77 31,776,896.73 10.97% 53.03% ADELANTADA 470.16%
TOTAL 59,927,920.48 31,776,896.73
CURVA DE AVANCE DE OBRA
AVANCE ACUMULADO DE OBRAS CIVILES + EQUIPAMIENTO
110%
100%
90%
80% PROGRAMADO EJECUTADO AVANCE
70% REAL
% AVANCE ACUMULADO

60% 48.27 %
50%
40%
30%
20% AVANCE
10% PROGRAMADA
0% 43.33 %
-10%
dic.-15

dic.-16
feb.-16

abr.-16

nov.-16

feb.-17

abr.-17
ene.-16

ago.-16

sep.-16

ene.-17
mar.-16

may.-16

jun.-16

oct.-16

mar.-17
jul.-16
VALORIZACIONES DE OBRA PROGRAMADA VALORIZACIONES DE OBRA REAL
TOTALES PORCENTAJES TOTALES PORCENTAJES SITUACION DE LA OBRA
N° PERIODO
(S/.) (%) (S/.) (%)
PARCIAL ACUM. (A) PARCIAL ACUM. PARCIAL ACUM. (B) PARCIAL ACUM. OBRA %

1.00 dic-15 382,284.83 382,284.83 0.24% 0.24% 699,684.67 699,684.67 0.44% 0.44% ADELANTADA 83.03%
2.00 ene-16 911,617.05 1,293,901.88 0.57% 0.81% 970,818.78 1,670,503.45 0.61% 1.05% ADELANTADA 29.11%
3.00 feb-16 994,587.18 2,288,489.05 0.63% 1.44% 1,324,741.19 2,995,244.64 0.83% 1.88% ADELANTADA 30.88%
4.00 mar-16 1,124,613.78 3,413,102.83 0.71% 2.15% 1,612,244.73 4,607,489.37 1.01% 2.90% ADELANTADA 34.99%
5.00 abr-16 1,544,003.65 4,957,106.48 0.97% 3.12% 2,233,355.77 6,840,845.14 1.40% 4.30% ADELANTADA 38.00%
6.00 may-16 2,851,745.59 7,808,852.06 1.79% 4.91% 1,893,270.75 8,734,115.89 1.19% 5.49% ADELANTADA 11.85%
7.00 jun-16 3,345,016.53 11,153,868.59 2.10% 7.01% 2,441,740.13 11,175,856.02 1.53% 7.02% ADELANTADA 0.20%
8.00 jul-16 4,130,527.31 15,284,395.90 2.60% 9.61% 8,766,217.59 19,942,073.61 5.51% 12.53% ADELANTADA 30.47%
9.00 ago-16 5,299,748.35 20,584,144.25 3.33% 12.94% 4,461,489.30 24,403,562.91 2.80% 15.34% ADELANTADA 18.56%
10.00 sep-16 7,010,647.19 27,594,791.44 4.41% 17.34% 4,958,211.55 29,361,774.46 3.12% 18.45% ADELANTADA 6.40%
11.00 oct-16 7,762,301.71 35,357,093.15 4.88% 22.22% 7,530,496.80 36,892,271.26 4.73% 23.19% ADELANTADA 4.34%
12.00 nov-16 5,959,289.34 41,316,382.49 3.75% 25.97% 6,373,003.66 43,265,274.92 4.01% 27.19% ADELANTADA 4.72%
13.00 dic-16 5,420,160.44 46,736,542.93 3.41% 29.37% 8,589,259.21 51,854,534.13 5.40% 32.59% ADELANTADA 10.95%
14.00 ene-17 4,459,141.90 51,195,684.83 2.80% 32.18% 3,221,711.06 55,076,245.19 2.02% 34.62% ADELANTADA 7.58%
15.00 feb-17 4,817,831.89 56,013,516.72 3.03% 35.21% 5,486,230.22 60,562,475.41 3.45% 38.06% ADELANTADA 8.12%
16.00 mar-17 5,756,873.30 61,770,390.02 3.62% 38.8233% 6,113,983.50 66,676,458.91 3.84% 41.91% ADELANTADA 7.94%
17.00 abr-17 7,163,041.17 68,933,431.19 4.5020% 43.33% 10,117,710.74 76,794,169.65 6.36% 48.27% ADELANTADA 11.40%
TOTAL 159,106,401.29 76,794,169.65
PRESENTACION
PANEL FOTOGRAFICO
Avance de Obra al 30/04/17

Vista aérea del Drone de la Obra D.A.C (Se aprecia los Sgts
blocks 2, 3, 4, 5, 6, 7 y 1)
Avance de Obra al 30/04/17

En la figura se aprecia los avances del presente mes referente


marzo: blocks :1(Nivel + 27.18) y 9(Nivel + 25.21).
Avance de Obra al 30/04/17

20170104_111218_resized

En la figura se aprecia los avances del presente mes


referente marzo block 6 (Nivel + 15.78) encimado de
ladrillos.
Avance de Obra al 30/04/17

20170104_111218_resized

Vista panorámica: se observa blocks: 9(Nivel + 25.21). y 1(Nivel


+ 27.18)
Avance de Obra al 30/04/17

20170104_111218_resized

En la figura se aprecia los avances del presente mes en lo que


se refiere albañilería en los block 12 y 11 en el 1er, 2do y 3er
nivel
Avance de Obra al 30/04/17

20170104_111218_resized

En la figura se aprecia los avances del presente mes en lo que


se refiere albañilería en los block 5 y 1 en el 1er nivel
Avance de Obra al 30/04/17

Vista en la que se observa las tuberías SCH 40 colocadas para el sistema de agua contra
incendio, así como las tuberías de cobre para la instalaciones de agua, así como también
bandejas, tuberías y cableado para las instalaciones eléctricas, que se vienen realizando en
el bloque 1 y 5 del 4º y 5º nivel .
Avance de Obra al 30/04/17

En la vista se aprecia los ductos de aire acondicionado pertenecientes a las


instalaciones mecánicas, así como las tuberías de cobre para las instalaciones de
agua y cableado para las instalaciones eléctricas que se vienen colocando en el
bloque 9, 1 y 5 en el 4to y 5to nivel.
Avance de Obra al 30/03/17

En la vista se aprecia el colocado de imprimante y cubierta de


manto asfáltico, en el techo inclinado del bloque 7.
Avance de Obra al 30/04/17

En la figura se aprecia el vaciado de concreto f’c= 140 kg/cm2


para contrapiso en el 3er nivel del bloque 1
Avance de Obra al 30/03/17

Vista en la que se observa el vaciado de concreto


f’c=140 kg/cm2 para contrapiso del 3er nivel del
block 11 y 12.
Avance de Obra al 30/04/17

En la que se observa el vaciado de concreto f’c=210 Kg/cm2


para la exterior escalera del block 12, la que se encuentra
ubicada entre el bloque 12 y 5
Avance de Obra al 30/04/17

En la vista se aprecia el vaciado del piso terminado capa final


de la azotea de block 6, así como el corte de las juntas de
dilatación.
Avance de Obra al 30/04/17

En la vista se aprecia el colocado de imprimante y cubierta de


manto asfáltico, en la azotea del block 7.
Avance de Obra al 30/04/17

Vista en la que se puede apreciar el vaciado de concreto


f’c=210kg/cm2 en buzones para sistema de desagüe exterior,
cerca al bloque 10.
Avance de Obra al 30/04/17

En la vista se observa el vaciado de concreto f’c=140 kg/cm2


para contra piso en el 3er nivel del bloque 6
Avance de Obra al 30/04/17

En la foto se observa la prueba de resistencia eléctrica del


sistema malla a tierra ubicado entre los bloques 5 y 12,
realizado el día 11/04/2017
Avance de Obra al 30/04/17

Vista en la que se observa la colocación de acero, encofrado y


vaciado de concreto f’c=210 kg/cm2 para la losa armada del
bloque 10.
Avance de Obra al 30/04/17

En la vista se observa el vaciado de concreto f’c=140 kg/cm2


para contra piso del 2do nivel en los bloques 1, 2 y 5
Avance de Obra al 30/04/17

En la vista se observa el vaciado de concreto f’c=140 kg/cm2


para contra piso del 2do nivel en los bloques 6 y 7.
Avance de Obra al 30/04/17

En la vista se aprecia la estructura metálica colocada y pintada, así como


la tabiquería de acero galvanizada para drywall colocada en el 3er nivel
del bloque 6, en donde se tiene proyectado la construcción de un
auditorio.
Avance de Obra al 30/04/17

En la vista se aprecia el colocado de tabiquería de acero


galvanizado junto a las placas (Drywall) del 2do nivel del
block 5 y 1 (Nivel + ………).
Avance de Obra al 30/04/17

Vista en la que se observan las placas de la tabiquería de


drywall colocadas en las dos caras en los muros del 5º nivel
de los bloques 1, 5 y 9 (Nivel +……).
Avance de Obra al 30/04/17

En la vista se observa la estructura metálica colocada y


pintada en el 3º nivel del block 7.
Avance de Obra al 30/04/17

En la vista se observa la colocación de estructura metálica en


el 3º nivel del block 7,en donde se tiene proyectado la
construcción de una residencia médica
Avance de Obra al 30/04/17

En la vista se observa el asentado de muros de ladrillo King


Kong y colocación de acero para columnetas que se viene
realizando en el bloque 10 .
Avance de Obra al 30/04/17

En la vista se aprecia el colocado de imprimante y cubierta


de manto asfáltico, en el techo inclinado del bloque 12.
Avance de Obra al 30/04/17

En la vista se observa el encofrado, acero colocado y vaciado de


concreto f’c=210 kg/cm2 para la cimentación del cerco perimétrico exterior
y la caseta de guardianía número 2, que se encuentra cerca al bloque 1 y
colinda con la avenida Los Incas.
Avance de Obra al 30/04/17

En la vista se observa la estructura metálica colocada que servirá como


soporte para la cobertura de la escalera exterior que va del piso 3 al 4 en
el bloque 1.
Avance de Obra al 30/04/17

En la vista se puede observar la visita a obra de los


representantes de los equipos técnicos de las regiones de
Lima, Pasco, Huánuco, Junín, Huancavelica y Ucayali por
motivo de la VIII Cumbre de la Mancomunidad Regional
Pacífico Centro Amazónica, realizada el día 24/04/2017
Avance de Obra al 30/04/17
R E S U M E N AL 3 0 S E TI E M B R E 2 0 1 6
PEDESTALES AISLADORES DESLIZADORES
BLOCKS TOTAL TERMINADOS % COLOCADOS POR COLOCAR % COLOCADOS POR COLOCAR %
BLOCK 01 47 47 100 36 0 100.0 11 0 100.0
BLOCK 02 12 12 100 12 0 100.0 0 0 100.0
BLOCK 03 10 10 100 10 0 100.0 0 0 100.0
BLOCK 04 9 9 100 9 0 100.0 0 0 100.0
BLOCK 05 44 44 100 35 0 100.0 9 0 100.0
BLOCK 06 29 29 100 23 0 100.0 6 0 100.0
BLOCK 07 17 17 100 15 0 100.0 2 0 100.0
BLOCK 08 - - - - - - - - -
BLOCK 09 12 12 100 12 0 100.0 - - -
BLOCK 10 - - - - - - - - -
BLOCK 11 6 6 100 6 0 100.0 - - -
BLOCK 12 - - - - - - - - -
TOTAL 186 186 100.0 158 0 100.0 28 0 100
*AISLADORES TOTALES 158
*DESLIZADORES TOTALES 28
STOCK AIS. 0 STOCK DESL. 0
Observaciones
1.- El personal designado en la especialidad de arquitectura para los trabajos de muros y tabiques,
revoques y revestimiento en los distintos bloques y pisos son insuficientes; esto ha generado un ritmo lento
de trabajo.
2.- Aperturar nuevos frentes de trabajos en paralelo, incrementando personal obrero para los trabajos de
encimados de ladrillos, tarrajeos de muros, encofrados de columnetas, vigas, etc. en los diferentes blocks y
niveles.
3.- Falta de planificación del contratista para dar inicio a los trabajos de las especialidades de
Instalaciones Eléctricas, Instalaciones Mecánicas, Instalaciones sanitarias e Instalaciones Electromecánicas,
ya que estos trabajos deberían de haberse iniciado el mes de Octubre, pese a que se disponía de frentes de
trabajo.
4.- El contratista no ha incorporado en obra a los profesionales de su propuesta tanto el de Instalaciones
Sanitarias, Eléctricas, Mecánicas y el Ing. De oficina técnica y planificación propuesto en la oferta del
Contratista y en los gastos generales que a la fecha no se cuentan con su presencia en obra, este
incumplimiento genera directa e indirectamente que se tenga un ritmo lento de trabajo.
5.- Debido a las condiciones climáticas en la zona y como consecuencia de ello en la carretera central (
huaycos y derrumbes en la vía) se recomienda al contratista planificar y hacer un cronograma real de la
adquisición de sus materiales para evitar retrasos en obra.
6.- Se recomienda al contratista realizar los vaciados de contra piso en los diferentes block y pisos, así
como también poner mas énfasis en Arquitectura, Instalaciones eléctricas, sanitarias, electromecánicas y
comunicaciones .
Conclusiones
CONCLUSIONES
 Mediante Acta de Conciliación No. 014-2017,de fecha 08.03.2017, entre el Gobierno Regional Pasco y el Consorcio de la
Salud Pasco; convienen en aprobar la Ampliación de Plazo No. 01 por 59 días calendarios, y el Contratista renuncia a todos
los mayores gastos generales que pueda producir la Ampliación de Plazo No. 01.
 Se debe de precisar que mediante Resolución Ejecutiva Regional No. 250-2017-G.R.P/GOB, del 24.03.2017 se Aprobó el
Calendario de Obra Valorizado Actualizado y Programa de Ejecución de Obra GANTT y PERT-CPM
 Del componente de estructuras se tiene un avance acumulado de 95.10% quedando un saldo por valorizar de 4.90%
 Del componente de Arquitectura se tiene un retraso acumulado del orden de 76.95% debido a que el Contratista no habilito
los frentes de trabajo en el momento adecuado, esto ha generando retraso en la ejecución de la obra.
El porcentaje de avance acumulado de obra a la fecha es el siguiente:

AVANCE FISICO AL 30.04.2017


AVANCE PARTE
AVANCE X ESPECIALIDAD AVANCE TOTAL
DESCRIPCION INFRAESTRUCTURA
EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO PROGRAMADO
ESTRUCTURAS 96.72% 88.83%
ARQUITECTURA 24.56% 91.04%
INSTALACIONES SANITARIAS 20.37% 37.44%
45.39% 63.88%
INSTALACIONES ELECTRICAS 24.35% 49.48% 48.27% 43.33%
INSTALACIONES MECANICAS 1.86% 21.64%
INSTALACIONES DE COMUNICACIONES 13.60% 6.28%
EQUIPAMIENTO 53.03% 9.30%
Conclusiones

RESUMEN DE VALORIZACIONES Nº 17 CORRESPONDIENTE AL MES DE ABRIL


(Inc. IGV)
CONTRATISTA : S/. 7,203,444.33 (Se presentara el 04.04.2017)
SUPERVISION : S/. 301,406.93 (Se presentara el 05.04.2017)
Conclusiones
AVANCE FINANCIERO DEL CONTRATISTA
A la fecha se le a pagado un total de S/. 127’013,798.57, que representan el 67.65% del monto del contrato. Dichos pagos están
comprendidos en: Adelanto directo (15.36%), adelanto de materiales (Nº 1, 2, 3, 4 , 5, 6 y 7) (25.48%), Valorizaciones del 01 al
16, (Dic-2015 hasta Mar-2017), pendientes de pago valorización Nº 17 del Contratista (Abr-2017).
Amortizaciones a la fecha (S/. 28’348,161.78)
Valorizaciones del 01 – 16, los cuales representan S/. 78’678,221.51 (se debe de precisar que en este monto no se están
considerados los reajustes ni las deducciones de los reajustes que no corresponden)
AVANCE FISICO
AVANDE DE ESTRUCTURAS 96.72 %
AVANCE INFRAESTRUCTURA 45.39 %
AVANCE TOTAL 48.27%
AVANCE FINANCIERO DE LA SUPERVISION
ADELANTO DIRECTO (S/. 2’653 066.20)
AMORTIZACIONES (S/. 2’329,545.62)
VALORIZACION ETAPA SUP. ELB. EXP. TEC. (S/. 2’308,446.41)
VALORIZACIONES DEL 01 – 15, los cuales representa (S/. 5’456,705.57)
EL MONTO TOTAL VALORIZADO DE LA SUPERVISION ES DE S/. 8’088,672.56 QUE REPRESENTAN EL 87.12% DEL
MONTO TOTAL, pendientes de pago valorización No. 16 y 17 de la Supervisión (Mar y Abr - 2017)
Se esta presentando el avance físico de obra al 30/03/2017.
“MEJORAMIENTO Y AMPLIACION DE LA CAPACIDAD RESOLUTIVA
DE LOS SERVICIOS DE SALUD DEL HOSPITAL REGIONAL DANIEL A.
CARRION DEL DISTRITO DE YANACANCHA PROVINCIA DE PASCO-
PASCO"

¡Muchas gracias!