JOB HAZARD ANALYSIS

Location of Work: PMFTC – Batangas Plant Project in charge : Ikeuchi Kenchiro, Danilo
Contractor: Miura Singapore CO Pte Ltd – PH (Boiler Room) Marcorde and Ardy Dioso
Branch Contact No : +63 2 528 3134
Project : Parts Assembly For Miura Boiler PREPARED BY: Mr. Danilo Marcorde
Safety Officer: Engr. Perk Oasan
APPROVED BY: Engr. Reynaldo Gutierrez
Contact No: 09205072075

JOB ACTIVITY HAZARD EFFECT CONTROL MEASURES

• Conduct toolbox meeting


1. Work Evaluation Un-authorize work ; Invalid • Discuss step by step procedure & potential
Permit hazard to workers
• Get the permit Validated in specific date.

• Proper body positioning & handling of tools ;


2. Preparation and Slips and trips hazard Fracture bones , cuts and bruises (work instruction)
mobilization of tools and
• Body System, use of PPE (hard hat, safety
materials
shoes , reflectorized vest)

3. Turning off mechanical Physical and electrocution • Assistance and Proper coordination to
Plant shut-down, Burns and bone
valves and electrical hazard the person in charge in plant operation or
fractures
switches team
• Well trained personnel allowed in the
working area
• Verify electrical lines for cuts and fracture
• Use of PPE ( hard hat, goggles,
reflectorized vest, safety shoes and
electrical gloves
4. Assembly and Installing Physical and electrocution Fracture bones, burns, cuts • Proper coordination with the operating
mechanical parts( valves, hazard and plant shutdown and personnel in the plant.
pipes and metal malfunction • Well trained person allowed in the working
components), Electrical area
parts (wires, • Use the right tools for the specific activities
electromagnetic switches JOB HAZARD • Use of PPE (hard hat, safety shoes,
and electronic devices reflectorized vest and working gloves)
ANALYSIS
1
JOB HAZARD ANALYSIS
Location of Work: PMFTC – Batangas Plant Project in charge : Ikeuchi Kenchiro, Danilo
Contractor: Miura Singapore CO Pte Ltd – PH Marcorde and Ardy Dioso
Branch (Boiler Room)
Contact No : +63 2 528 3134
Project : Parts Assembly For Miura Boiler Safety Officer: Engr. Perk Oasan
PREPARED BY: Mr. Danilo S. Marcorde
APPROVED BY: Engr. Reynaldo Gutierrez Contact No: 09205072075

JOB ACTIVITY HAZARD EFFECT CONTROL MEASURES

5. Applying chemicals to the Skin and eye irritation Blindness , and skin • Safety data sheet or certificate of analysis for
chemical feed tank irritation the chemical product must be provided.
• Well trained personnel must do the pouring or
applying the chemicals
• Use of PPE (hard hat, safety shoes, chemical
gloves and goggles)

6. Turning on mechanical Physical and electrocution Burn and cut skin, damage • Proper coordination and turn over with the
valves and electrical hazard and plant malfunction of property personnel in the operation
switches for testing and or shutdown • Well trained personnel allowed in the working
turn over area
• Ensure that machine is operated according to
the operating instruction.
• Use of PPE (hard hat, safety shoes, working
gloves , goggles and reflectorized vest)

7. House keeping and Depletion of resources and land Fracture bones, bruises • Proper 5’s implementation (sort, set,
demobilization of tools pollution, physical hazard and cut skin, pollution to shine, standardized, sustain)
the environment • Wash hands after the activity
• Proper segregation and disposal
• Use of PPE (hard hat, safety shoes,
reflectorized vest)

JOB HAZARD
ANALYSIS
2