Documente Academic
Documente Profesional
Documente Cultură
Governing Principle
Firm Price A price which is not variable for any reason(other than change
in specification, quantity or time for performance)
Fixed Price A price the final value of which is fixed by reverence to some
variable parameter such as an inflation index or currency
exchange rate
Cost Incentive A price based on contractors actual cost but with prime
contractor and subcontractor sharing overspends or
underspends against a pre-agreed target cost
Cost Re- A price based on the subcontractor actual cost plus a pre-
determined amount or percentage by way of profit.
imbursement
In effect they represent a spectrum of cost-risk allocation between
client and prime contractor as shown in figure
The Cost
In a incentive
conventional contract
arms-length The fixed provides the
relationship
the prime price compromise
contractor will approach solution for
prefer a firm deals with high risk
price where he one or two work where
perceives the risks only neither side
risk to be such as is willing or
small and the
opportunity inflation and able to carry
for profit foreign the entire
great currencies cost risk
NON COMPETITIVE
COMPETITIVE (SOLE SOURCE)
ARMS-LENGTH
Buyer Risk
CONTRACT STRATEGY
MAKE SERVICE ONLY
BUYER CONTROL
TURNKEY
BUYER RISK
PRICING REGIME
COST RE-
COST INCENTIVE IMBURSHMENT
BUYER CONTROL
BUYER RISK
Contract types based on
scope of the project
Design-Build : A single business entity that performs
both the design and construction of a project. The team
can be one company or a partnership of firms.
Turnkey: One business entity that performs the design,
construction, and construction financing of the project.
Payment is made at the completion (when the
contractor turns over the "key").
Build-Operate-Transfer: One business entity that
performs the design, construction, construction and
long-term financing, and temporary operation of the
project. At the end of the operation period, which can
be many years, operation of the project is transferred
to the owner.
Poor Contract Management
Poor Contract Management Costs Companies 9% — Bottom Line
Advantages of scheme
The first main advantage of such schemes is that they are
flexible and can be tailor-made to individual circumstances.
The second advantage of cost incentive schemes is that they
promote co-operation, openness and sensible decision-making
between client and prime contractor.
Much the better than in a firm price arrangement where the
client is motivated to squeeze the last ounce of performance
from the prime contractor (regardless of cost to the prime
contractor) & the prime contractor is motivated to deliver
the bare minimum performance (regardless of client's
situation).
Payment Types
Arrangement Objective Principle
Advance payment A proportion of prime
contract price placed with
order
Stage payments Discrete sums of money paid
as and when proportions of
the work are completed
Milestone payments Discrete sums of money paid
as and when specific, key
tasks are completed
Progress payment Regular re-imbursement of
costs incurred by the prime
contractor
Project Contract and Procurement
Management
Project Procurement Management
Processes and Key Outputs
Engineering , Procurement
and Construction
Engineering , Procurement and
Construction with long lead time
items
EPC Contract structure
PMC contract structure
EPCM contract structure
Progressive Lump Sum
The timeframe obligation
If the contract does not specify a completion date then the Sale of
Goods Act comes into operation and obliges the prime contractor to
complete within a reasonable period.
Client wants that he has not accepted any part of work until whole is
completed before specified date, on the other hand milestone for
which contractor mention the date are critical to him in deciding to
release interim payments.
Failure to completion on time normally allows the client the remedy of
termination, in that case prime contractor must try to avoid milestone
dates carrying the penalty and careful drafting the contract.
Time is the essence
Essence meaning the intrinsic nature or indispensable quality of something, especially
something abstract, which determines its character.
‘Time is of the essence of the contract’- clients recommended to include it in contract
but prime contractor urged to avoid…!!!
In business contracts time is usually to be considered to be of the essence, provided
dates are specified, whether or not this expression is included.
The meaning of time is essence is that the parties have agreed to perform at a given
time agreed in a contract and shall not extend the specified time in a contract. In case
a contract does not expressly provide this phrase then in that case time is not the
essence of a contract.
Time is the essence is specified in Section 55 of The Indian Contract Act, 1872, “When
a party to a contract promises to do a certain thing at or before a specified time, or
certain things at or before specified times, and fails to do any such thing at or before
the specified time, the contract, or so much of it as has not been performed, becomes
voidable at the option of the promisee, if the intention of the parties was that time
should be of the essence of the contract.”
When time is the essence in construction contracts the standard rule is that the parties
have agreed to perform their obligation as per the time specified in a contract and
there shall not be any extension of time. Whereas, if time is not the essence of the
contract, the court allows the parties to a contract perform at some other time than
agreed upon.
Consequences of delay
Unplanned delay is bad news for the contractor in terms of additional
costs, delayed payments, negative cash flows and other such effects.
In the event of default the client is entitled to recover damages from
the prime contractor to the extent necessary to compensate him for
any financial loss suffered.
There is no good definition of direct and consequential damages since
the distinction is not absolute, it depends upon the particular
circumstances.
Liquidated damages
The ‘liquidated damages’ is a reasonable
pre-estimate of the likely level of damage potentially
to be suffered by client in the event of delay and
having agreed the sum, fixed it within the contract
the damages then payable in the event of delay.
Liquidate damages clauses generally provide for
certain amount to be paid per week to a max. period/
max. amount/ max. percentage.
Client takes the risk that amount so fixed would indeed cover his actual
loss but gains in return a much more ready means of securing payment
for damage.
Force majeure
Vop/cpa:
Given some control
How to control cost:
Material: seek long term prices
Wages: make agreement
Foreign Currency Fluctuations
Fluctuations in Currency also affect a firm's balance sheet by changing the value of the firm's assets and liabilities,
payable account’s, receivable account’s, inventory, loans in foreign currency, investments (CDs) in foreign banks
Foreign Currency
Fluctuations
If a UK prime contractor is selling abroad to a client who will pay in his
own currency, the currency should be sold forward or the prime contract
should include a formula for adjusting the price for variations in exchange
rate:
Pa = Po x (A * Er0 + B) Er1
Where Pa = Price as adjusted for exchange rate variation
Po = Price at date of prime contract
A = Variable element
B = Fixed element
Er0 = Exchange rate at base date
Er1 = Exchange rate at date of variation
Foreign Currency Fluctuations
ERV Formula:
Adjust prime contract price currency fluctuations
client pays in the prime contractor's national currency but
where the prime contractor has significant expenditure in a
different currency. Change in formula: A<1, i.e. proportion
of the prime contract price which is attributable to the
overseas expenditure
THANK YOU