Documente Academic
Documente Profesional
Documente Cultură
Presentation
Learning Experience from 720MW Mangdechhu Project
-Construction of Adit-II and Associated works of HRT
By Chenga Penjor
1
Overview
2
Objective
• Basic concept of Hydropower
• Classes of Rock and its support system
• Get rid of Tunnel Phobia
• Accustomed with the Tunnel and appreciate the Nature
3
Understanding Hydropower
Mangdechhu
Intake Tunnel
DC
Surge
Shaft
4
Construction of Adit-II
• Background:
• Five Construction Adits for 13.541 Km of HRT
• Longest Adit with 652m in length (7m X 6.5m Ø)
• Collapse of old portal in August-2012
• Relocation of Portal (40m downstream) – September-2012
• Actual start of Portal Excavation: 28th October 2012
• Completion Date: 27th July 2013
5
Old Portal Collapse
BEFORE
6
Old Portal Collapse
AFTER
7
Relocation of Adit-II
Portal Excavation
8
Relocation of Adit-II
New Portal
Old
40 m
9
Excavation Cycle
1. Surveying &
Profile
Marking
13
Fixing welded wiremesh
14
Face Shotcreting
15
Highest Achievement from Single Face
Nos. of Blast Vs. Pull (m)
16
14 13.5
12 11.2
Nos. of Blast & Pull (m)
10 9.5
8.6 8.6 8.6
7.8
7.4
8 7.4 Nos. of
6.4 7.4 7.1 Blast
7.5
6.4 Pull (m)
6 5.3
6 5 4.8
4.2 5 4.5 4.8 5
4 4.5 4
4 4 4 4 4
3 3
3 3 3 3 3
3 3
2 2 2 2
2 2
1 1
0
16
Head Race Tunnel
• Total Length of HRT: 13.541 km
• 6.5m Ø Horse shoe shaped
• Slope: 1 in 198.86 (0.503 %)
• Upstream: Face-III 1135 m
• Lowest cover => 68 m
ADIT-II
• Downstream: Face-IV 2318 m
• Highest Cover => 1008 m
17
Rib Twisting
18
Rib Rectification
-Squeezing Zone
• Wherever the desired dimension of 3.4 m from the centerline to rib
flange is less than 3.4 m on both sides, remining was done on both sides
to achieve the desired section.
• Wherever the desired dimension of 3.4 m from the centerline to rib
flange is less than 3.4 m on one side and more than 3.4 m on the
opposite side, remining was avoided and centerline was adjusted to
achieve the desired section.
• Wherever the desired dimension of 3.4 m from the centerline to rib
flange is less on one side and exactly 3.4 m on the opposite side,
remining will be done on one side only.
19
Remining
20
Change in Slope
INVERT
SL. No Original New Original
RD (m) New Slope Remarks
Elevation Elevation Slope
Overt Reinforcement
22
Concrete Lining in HRT
6. Curing 1. Surveying
2. Kerb
5. Concreting
Concreting
4. Bulkhead 3. Shifting of
Fixing Gantry
23
Grouting in the Tunnel
- Between concrete lining and Rock surface
• Contact Grouting - 45mm Ø, 300mm into the Rock @ 3m c/c
• Throughout the Tunnel - 1-3 kg/cm2
25
Team HRT
26
Security Team 27
Plugging of Adit-II and Charging of HRT
• Plugging of Adit-II completed on 11th
February 2019.
• Charging of HRT on 23rd April 2019.
• Rectification of Seepage:
• Consolidation grouting beyond concrete
plug up to 10 m was carried out.
• Pressure: 3-5 kg/cm2
• Application of Penetron layers (dampness)
Plugged Adit-II
28
Cost of the Tunnel
SL. No Description Unit Amount/Qtty
1. Adit Construction
1 Total length of Adit-II m 652
2 Total expenditure Nu. 99,351,088.26
Cost of tunnel/m (7 m width X 6.5 m Ø, D-
3 Nu./m 152,378.97
Shaped)
1. HRT Construction
1 Total length of Face-IV m 2318
2 Total expenditure Nu. 571,941,145.68
30
31