INDONESIA 1 PROJECT

PROPOSED METHOD EXCAVATION AT MRT AREA GRID


C8-C9
CONTENTS

1. LOCATION
2. PROJECT INTRODUCTION
3. EXCAVATION SEQUENCE
4. TOOLS AND MATERIAL
5. SCHEDULE
1. LOCATION

Delete Strut

10000 mm

Excavator enter via void


with length 9m

3700 mm 7838 mm 8000 mm 3550 mm


2. PROJECT INTRODUCTION
2.1 Geographical Condition

Length 𝛾𝑠𝑎𝑡 𝛾𝑢𝑛𝑠𝑎𝑡 c E K


No Kind of soil kN/m3 kN/m3 kN/m2 ∅ kN/m2 m/sec
(m)

Clay silt with trace 15.60 9.19 25 10 7200 0.001


1 6
of sand
Clay silt with trace 14.21 7.25 23 22 46325 0.001
2 15
to little of sand
Clay silt with a 15.47 9.20 48 9 33000 0.001
3 9
trace of sand 2
17.25 11.90 48 9 33000 0.001
4 Silty clay 6
2. PROJECT INTRODUCTION
2.2 Summary of earthwork
The existing ground level is -1.8m. The earthwork is mainly composed of fill material,
silty clay, clayey silt. The thickness of the slab and earthwork is as below:

Floor LEVEL (M) SLAB THICK (mm) AREA (m2) EXCAVATION (m) EARTH QTY (M3)

Existing Ground -1.8

Casting B1 and Strut 1 -4.3 250 230.88

Excavation 1 -6.9 230.88 5.1 1177.48

Excavation 2 -10.5 230.88 3.6 831.16

Install strut 2 -9.8

Excavation 3 and raft -14.7 230.88 4.2 969.696

Casting B2 -13.2 250 230.88


3. Excavation Sequence
3.1 Construction Sequences 1

STEP 1
- Construct capping beam
- Perform dewatering to decrease ground water level down
to 1M below targeted excavation level
- Excavate down to EL. -6.900
- Construct slab B1 EL. -4.300
- Install strut 1 EL. -4.300
3. Excavation Sequence
3.2 Construction Sequences 2

STEP 2
- Perform dewatering to decrease ground water level down
to 1M below targeted excavation level
- Excavate down to EL. -10.500
- Install strut 2 EL. -9.800
3. Excavation Sequence
3.3 Construction Sequences 3

STEP 3
- Perform dewatering to decrease ground water level down
to 1M below targeted excavation level
- Excavate down to EL. -13.200 (bottom of slab B2) and until
raft EL. -14.700
- Construct slab B2 EL.-13.200
- Casting lean concrete
4. Tools and Material

USING PC 200 9425 mm


2710 mm

2970 mm

3275 mm
4070 mm
4815 mm
5. Schedule

LEVEL AREA BUCKET CAPACITY Efficiency


Area EXCAVATION (m) EARTH QTY (m3) Machinery Time (day) Target Date
(M) (m2) (m3) (m3/day)

Excavation 1 -6.9 230.88 5.1 1177.48 0.8 230.4 2 pc 200 3 -

Excavation 2 -10.5 230.88 3.6 831.16 0.8 230.4 2 pc 200 2 -

Excavation 3 -14.7 230.88 4.2 969.696 0.8 230.4 2 pc 200 2 -