Documente Academic
Documente Profesional
Documente Cultură
1. LOCATION
2. PROJECT INTRODUCTION
3. EXCAVATION SEQUENCE
4. TOOLS AND MATERIAL
5. SCHEDULE
1. LOCATION
Delete Strut
10000 mm
Floor LEVEL (M) SLAB THICK (mm) AREA (m2) EXCAVATION (m) EARTH QTY (M3)
STEP 1
- Construct capping beam
- Perform dewatering to decrease ground water level down
to 1M below targeted excavation level
- Excavate down to EL. -6.900
- Construct slab B1 EL. -4.300
- Install strut 1 EL. -4.300
3. Excavation Sequence
3.2 Construction Sequences 2
STEP 2
- Perform dewatering to decrease ground water level down
to 1M below targeted excavation level
- Excavate down to EL. -10.500
- Install strut 2 EL. -9.800
3. Excavation Sequence
3.3 Construction Sequences 3
STEP 3
- Perform dewatering to decrease ground water level down
to 1M below targeted excavation level
- Excavate down to EL. -13.200 (bottom of slab B2) and until
raft EL. -14.700
- Construct slab B2 EL.-13.200
- Casting lean concrete
4. Tools and Material
2970 mm
3275 mm
4070 mm
4815 mm
5. Schedule