Documente Academic
Documente Profesional
Documente Cultură
DECEMBER 2019
LEFT AND RIGHT BANK IRRIGATION TUNNELS – GENERAL ARRANGEMENT
DECEMBER 2019
PREVIOUS ENGINEERING STUDIES FOR HYDROPOWER SCHEMES
ON IRRIGATION TUNNELS - COMMENTS
MDCG comments on engineering studies of hydropower schemes on left & right bank
irrigation tunnels (LBIT and RBIT):
Studies were not part of Terms of Reference of previous MDCG engineering services
contract.
Previous engineering studies of hydropower schemes were desk studies only with no
specific site visits to verify the suitability of selected sites.
Available topographic survey maps of the study areas were not detailed/precise. In addition,
for some of areas, topographic maps were not available for proper planning studies.
Geologic mapping and geotechnical investigations were not carried out for any of the
hydropower schemes.
DECEMBER 2019
PREVIOUS ENGINEERING STUDIES FOR HYDROPOWER
SCHEMES ON IRRIGATION TUNNELS - COMMENTS
Preliminary power and energy studies and conceptual layout studies of hydropower
schemes were based on 2012-13 irrigation water demand. Although irrigation
demands were revised in 2016, these studies were not revised.
The location and invert level of the tunnel outlet portals were not finalized in relation
to the irrigation canals.
No hydrological data of nullah was available to design the LBIT nullah crossing.
Conceptual level drawings of hydropower schemes were prepared to make
recommendations for subsequent and more detailed engineering studies. Cost
estimates were not performed and costs were not included in the Project Cost.
The intake structures for the irrigation tunnels were ungated. Gates would be
required for the hydropower schemes.
DECEMBER 2019
PRESENT SUDIES FOR POWER SCHEME ON
RIGHT BANK IRRIGATION TUNNEL (RBIT)
Reconnaissance visit of sites identified in previous and present studies. Generally, the sites were found suitable for
development of small hydropower schemes.
Preliminary design of identified scheme layout options based on previously available data and topographic maps,
hydraulic head loss calculations, power and energy studies, quantities take off, cost estimates, and economical analysis
Performed drone topographic surveys along RBIT to generate more accurate topographic maps.
An alternative location for the RBIT outlet was suggested by irrigation engineers to avoid huge canal crossings at nullah
locations.
Instead of ungated and submerged intake structure, A new gated intake structure for RBIT with the invert at El. 503.0
masl is proposed in the proximity of the intake location instead of the ungated deep setting intake configuration
contemplated in previous studies.
Several alternative RBIT alignments were evaluated based on the drone survey topographic maps and proposed new
intake locations and configuration to finalize the tunnel alignment.
DECEMBER 2019
ALTERNATIVE RBIT ALIGNMENTS
S.E
DECEMBER 2019
LOCATION OF SELECTED RBIT INTAKE SITE
Location of Intake
Structure
DECEMBER 2019
LOCATION OF SELECTED RBIT OUTLET PORTAL
DECEMBER 2019
SELECTED RBIT ALIGNMENT
DECEMBER 2019
GEOLOGICAL PLAN AND PROFILE ALONG RBIT
DECEMBER 2019
RBIT HYDROPOWER SCHEME LAYOUT OPTIONS
DECEMBER 2019
OPTION 1 - UNDERGROUND POWERHOUSE
DECEMBER 2019
OPTION 2 - SURFACE POWERHOUSE
DECEMBER 2019
STUDIES PERFORMED TO SELECT HYDROPOWER OPTION
3.5 4
Flow 3.5
3
3
2.5
Discharge (cumecs)
2.5
1.5
1.5
1
Energy 1
0.5
0.5
0 0
1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3
Jan Feb Mar Apr May Jun Jul Aug Sep Oct. Nov. Dec
DECEMBER 2019
OPTION 2 - FLOW, POWER & ENERGY (10-DAILY)
3.5 4
Flow 3.5
3
3
2.5
Discharge (cumecs)
2.5
1.5
1.5
1
Energy
1
0.5
0.5
0 0
1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3
Jan Feb Mar Apr May Jun Jul Aug Sep Oct. Nov. Dec
DECEMBER 2019
TYPICAL POWERHOUSE PLAN VIEWS
DECEMBER 2019
TYPICAL POWERHOUSE SECTIONS
DECEMBER 2019
COMPARISON OF RBIT POWERHOUSE OPTIONS
No. Description OPTION 1 OPTION 2 Remarks
(underground PH) (Surface PH)
Difference in net head for the two options is less than 1% and the same applies to the installed capacity
and energy production.
The length of the pressurized power conveyance system is 125 m for Option 1 and 3574 m for Option 2.
A 102 m high surge tank above ground would be required for Option 2 to meet standard operation stability
criteria. Above ground Surge tank of so much height with high seismic load will not be technically viable.
Without surge tank, Option 2 would not meet operation stability criteria.
Lower environmental impacts and shorter transmission line for Option 1
Land acquisition not required for Option 1 powerhouse.
DECEMBER 2019