Documente Academic
Documente Profesional
Documente Cultură
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
1
All rights reserved.
4
Introduction PMBOK 63
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
2
All rights reserved.
4
Introduction PMBOK 64
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
3
All rights reserved.
4
Project Integration Management PMBOK 61
Monitoring and
Initiating Planning Executing Closing
Controlling
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
4
All rights reserved.
4
Introduction PMBOK 64
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
5
All rights reserved.
4
Introduction PMBOK 64
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
6
All rights reserved.
4.1
Develop Project Charter PMBOK 67
Inputs
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
7
All rights reserved.
4.1
Develop Project Charter PMBOK 71
Inputs
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
8
All rights reserved.
4
Develop Project Charter PMBOK
3. Agreements
4. Enterprise
environment factors
5. Organizational
process assets
Creating a document that formally authorizes a project or phase and empowers the Project Manager
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
9
All rights reserved.
4.1.1
Develop Project Charter PMBOK 68
Inputs
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
10
All rights reserved.
4.1.1
Develop Project Charter PMBOK 70
Inputs
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
11
All rights reserved.
4.1.2
Develop Project Charter PMBOK 71
2. Facilitation Techniques
- Have broad application in project management process and help with guide lines
- The Techniques include
• Brainstorming
• Conflict resolution
• Problem solving
• Meeting management
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
12
All rights reserved.
4.1.3
Develop Project Charter PMBOK 71
Outputs
1. Project Charter
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
13
All rights reserved.
4.1
Develop Project Charter PMBOK 67
©Project Management Institute. A Guide to the Project Management Body of Knowledge(PMBOK® Guide) – Fifith Edition
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
14
All rights reserved.
4.2
Develop Project Management Plan PMBOK 72
Introduction
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
15
All rights reserved.
Develop Project Management Plan PMBOK
3. Enterprise
environmental factors
4. Organizational
process assets
Creating a document that formally authorizes a project or phase and empowers the Project Manager
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
16
All rights reserved.
4.2.1
Develop Project Management Plan PMBOK 74
Inputs
1. Project Charter
At the minimum it defines the high level boundaries of the project and
provided a starting point for initial planning through out the initiating
process group
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
17
All rights reserved.
4.2.2
Develop Project Management Plan PMBOK 76
1. Expert judgment
– The expert judgment is utilized to
• Tailor the process to meet the project needs
• Determine resources and skill levels needed to perform the project work
• Prioritize the work in the project to ensure the project resources are allocated to
the appropriate work at the appropriate time.
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
18
All rights reserved.
4.2.2
Develop Project Management Plan PMBOK 76
2. Facilitation Techniques
- Have broad application in project management process and help
with guide lines
• Conflict resolution
• Problem solving
• Meeting management
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
19
All rights reserved.
4.2.3
Develop Project Management Plan PMBOK 76
Outputs
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
20
All rights reserved.
4.2.3
Develop Project Management Plan PMBOK 76
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
21
All rights reserved.
4.2
Develop Project Management Plan PMBOK 74
©Project Management Institute. A Guide to the Project Management Body of Knowledge(PMBOK® Guide) – Fifth Edition
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
22
All rights reserved.
4.3
Direct and Manage Project Work PMBOK 81
Introduction
• It is the process of leading and performing the work defined in Project Management Plan
and implementing approved changes to achieve the project objectives
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
23
All rights reserved.
4.3
Direct and Manage Project Work PMBOK 79
It is a process of leading and performing the work defined in the project management plan and implementing approved changes to achieve
the project’s objectives
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
24
All rights reserved.
4.3.1
Direct and Manage Project Work PMBOK 82
Inputs
1. Project Management Plan
– Subsidiary plans related to project work
– Scope management plan
– Requirements management plan
– Schedule management plan
– Cost management plan
– Stakeholder management plan
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
25
All rights reserved.
4.3.2
Direct and Manage Project Work PMBOK 83
• Asses the inputs needed to direct and manage execution of the Project Management
Plan.
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
26
All rights reserved.
4.3.2
Direct and Manage Project Work PMBOK 83
automated systems
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
27
All rights reserved.
4.3.2
Direct and Manage Project Work PMBOK 83
3. Meetings
• Used to discuss and address the pertinent topics of the project during the process
– Decision making
• Meetings should have appropriate agenda, well time framed and minutes should be
recorded
• Face to face meeting may be substituted by audio bridges and virtual conferences
with adequate prior preparation.
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
28
All rights reserved.
4.3.3
Direct and Manage Project Work PMBOK 85
Outputs
1. Deliverables
– A deliverable is any unique and verifiable product, result or capability to
perform a service that is required to be produced to complete a process,
phase or project
– Deliverables are typically tangible components completed to meet the project
objectives and can include the elements of project management plan.
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
29
All rights reserved.
4.3.3
Direct and Manage Project Work PMBOK 85
Outputs
3. Change Requests
- It is a formal proposal to modify any document, deliverable or baseline.
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
30
All rights reserved.
4.4
Monitor and Control Project Work PMBOK 86
Introduction
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
31
All rights reserved.
4.4
Monitor and Control Project Work PMBOK 86
7. Organizational
process assets
It is a process of leading and performing the work defined in the project management plan and implementing approved changes to achieve
the project’s objectives
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
32
All rights reserved.
4.4.1
Monitor and Control Project Work PMBOK 88
Inputs
1. Project Management Plan
– Including subsidiary plans and baselines
2. Schedule Forecasts
– These are derived from progress against the schedule baseline and computed time
estimate to complete (ETC)
– Typically expressed in terms of Schedule variance(SV) and Schedule performance
Index (SPI)
– For projects not using earned value management, variances against the planned
finish dates and forecasted finish dates are provided
3. Cost Forecasts
– These are derived from progress against the cost baseline and computed time estimate
to complete (ETC)
– Typically expressed in terms of cost variance(CV) and cost performance Index (CPI)
– Estimate at Completion (EAC) is compared with Budget at completion (BAC) to asses the
costs. Change request has to be initiated if it is not in tolerance limits.
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
33
All rights reserved.
4.4.1
Monitor and Control Project Work PMBOK 88
Inputs
4. Validated Changes
– A validated change provides the necessary data to confirm that the
change was appropriately executed
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
34
All rights reserved.
4.4.2
Monitor and Control Project Work PMBOK 91
1. Expert judgment
– The expert judgment is utilized by the project management team to
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
35
All rights reserved.
4.4.2
Monitor and Control Project Work PMBOK 91
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
36
All rights reserved.
4.4.2
Monitor and Control Project Work PMBOK 91
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
37
All rights reserved.
4.4.3
Monitor and Control Project Work PMBOK 92
Outputs
1. Change Requests
– These may be issued to expand, adjust, or reduce project scope, product scope, or
quality requirements and schedule or cost baselines.
– These are formal requests that may be initiated internally, externally, direct or indirect,
optional or mandatory, statutory etc.
– Approved Change Requests
1. These are output of Perform Integrated Change Control process
2. Are approved by Change Control Board (CCB)
3. Approved change may be a corrective action, preventive action, defect repair and/ or
updates
4. Are scheduled and implemented by the project team
5. May impact any project area or project management plan
6. May result in modification of policies, procedures, scope, cost, schedules and budgets
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
38
All rights reserved.
4.5
Perform Integrated Change Control PMBOK 94
Introduction
• Integrated change control process ensures that any change to the project
deliverables, project management plan including its subsidiary plans, baselines and
or organizational process assets is made only after comprehensive review of
impact on other deliverables, plans and baselines with identification of potential
risks and provision appropriate actions to manage the same.
• Change requests are subjected to processes specified in the change control and
configuration control systems
• Change request process may require information on estimated time impact and
estimated cost impact
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
39
All rights reserved.
4.5
Perform Integrated Change Control PMBOK 96
Introduction
• Change requests may be rejected and it is ensured that only approved changes are
incorporated in the revised baseline.
• Customer or sponsor approval may be required after CCB approval unless they are
part of the CCB
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
40
All rights reserved.
Perform Integrated Change Control
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
41
All rights reserved.
Perform Integrated Change Control
Change Request Path
Control Quality
.
.
.
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
42
All rights reserved.
Perform Integrated Change Control
What is Change Control System? Project Stakeholder
Change
Impact Analysis Open Request
Control Group
(Specific)
Recommendations
Decision
Change
Execution Group Implementation
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
43
All rights reserved.
4.5
Perform Integrated Change Control PMBOK 94
5. Organizational
process assets
Process to manage changes to project artifacts like Deliverables, Plans, baselines, Documents, Process Assets, etc.
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
44
All rights reserved.
4.5.1
Perform Integrated Change Control PMBOK 97
Inputs
1. Project Management Plan
– Elements of project management plan that may be used include but not limited to:
1. Scope management plan which contains procedure for scope changes
2. Scope baseline which provides product definition
3. Change management plan, which provides the direction form managing the change control
process and documents the formal change control board (CCB)
3. Change Requests
– Change requests result from executing, monitoring and controlling processes
– Change requests may include corrective action, preventive action and defect repairs
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
45
All rights reserved.
4.5.2
Perform Integrated Change Control PMBOK 99
2. Meetings
– For this process the meetings are usually referred to change control meetings in which;
• Change requests are discussed, reviewed, approved, disposed or rejected.
• Configuration management activities may also be reviewed
• CCB decisions are documented and communicated to the stakeholders for information and follow-up
actions.
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
46
All rights reserved.
4.5.3
Perform Integrated Change Control PMBOK 99
Outputs
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
47
All rights reserved.
4.6
Close Project or Phase PMBOK 100
Introduction
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
48
All rights reserved.
4.6
Close Project or Phase PMBOK 100
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
49
All rights reserved.
4.6.1
Close Project or Phase PMBOK 102
Inputs
1. Project Management Plan
The project management plan becomes the agreement between the project manager
and project sponsor, defining what constitutes project completion
– Elements of project management plan that may be used include but not limited to:
• Scope management plan which contains procedure for scope changes
• Scope baseline which provides product or service definition
• Change management plan, which provides the direction form managing the change control process and
documents the formal change control board (CCB)
2. Accepted Deliverables
̶ Accepted Deliverables my include:
• Product specifications
• Delivery receipts
• Work performance documents
• Partial or interim deliverables ( incase of phased or cancelled projects)
3. Organizational Process Assets
– Factors including but not limited to:
• Project or phase closure guidelines or requirements
• Historical and lessons learned knowledge base
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
50
All rights reserved.
4.6.2
Close Project or Phase PMBOK 102
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
51
All rights reserved.
4.6.3
Close Project or Phase PMBOK 103
Outputs
CAPM Certification Examination Training Material Version 5.0 Copyright © 2013 by PMI Mumbai Chapter.
52
All rights reserved.