Documente Academic
Documente Profesional
Documente Cultură
BSB20315-7
Lecture 7
Rethinking time planning:
The critical path approach
Learning Outcomes
Estimating (Continued)
• Time plans establish precedence relationships,
they should be treated as overviews only
– Changes need to be accommodated and
communicated
• Progress should be monitored by the critical path,
not the percent complete
– A time to finish is required from all sub-project
managers
– Represent by state of safety buffer
Estimating (Continued)
• The true consequences of a late finish should be
evaluated in financial terms
– Beware penalty clauses
– Or savings on running costs of completed project
• Always buffer a constraint when it has been
identified
• Adding buffers and removing due date constraints
leads to stability and robustness
• When a non-critical activity becomes critical, it
should be protected with a buffer
Module Code and Module Title Title of Slides
Using the critical chain approach
(Continued)
Control
• The project manager has ultimate responsibility
for control
– Determines the issues that are important and their
measures
– Determines the systems to monitor and apply
corrective action
• Remove due dates, start the activity directly after
the completion of the previous activity
– The relay race: runners are lined up (and beginning
to move) before their leg of the race
Module Code and Module Title Title of Slides
Using the critical chain approach
(Continued)
Control (Continue)
• With due dates there is no requirement or
incentive to finish early
• Without due dates early finishes can be added to
the buffer
• The project manager’s role becomes one of
– managing handovers
– encouraging early finishes
– ensuring that subsequent activities are ready to
start
Module Code and Module Title Title of Slides
Summary