Documente Academic
Documente Profesional
Documente Cultură
By
CH CH KRISHNAJI
SCHOLAR NO : 1921303
STRUCTURAL ENGINEERING
DEPARTMENT OF CIVIL ENGINEERING
NIT SILCHAR
CONTENTS
• INTRODUCTION.
• DIRECT COST OF THE PROJECT.
• INDIRECT COST OF THE PROJECT.
• TOTAL COST OF THE PROJECT.
• TIME-SCALE DIAGRAM.
• CRASHING OF NETWORK.
INTRODUCTION
• For any project ,the two important aspects to be considered are
a) Project time
b) Project cost
• In actual projects, time is always related to cost but this
relationship is not linear.
• To find the minimum cost corresponding to an optimum
duration, time cost models are prepared.
• The total cost of a project constitutes direct cost and the
indirect cost.
DIRECT COST OF THE PROJECT
• Direct cost is the directly identifiable cost based on experience and
judgement.
Examples: Material cost,labour cost,equipment cost etc..,.
• Direct cost of a project is a summation of direct cost of all activities in the
project.
• Direct cost associated with an activity increases with decrease in its
duration below normal duration. This is because of involvement of extra
resources , use of advance technology , extra wages for over time which
are usually higher than the regular wages etc..,.
CRASH TIME
• Minimum time in which an
NORMAL TIME
activity can be completed
• Completion time of an activity and this time cannot be
under normal circumstances is reduced even with
called normal time. application of infinite
• The cost of an activity associated resources is called crash
with normal time is called normal time.
cost. • The cost associated with
crash time is called crash
cost.
DIRECT COST CURVE OF AN ACTIVITY
COST SLOPE(C.S):
The slope of the COST VS DURATION curve is
called cost slope of an activity.
Cost Slope =
CRASHING POTENTIAL(C.P):
The difference between the normal
duration and crash duration is called crashing potential
of an activity.
C.P = Normal time – Crash time.
INDIRECT COST
• Indirect cost of a project are those expenses which cannot be associated
to any individual activity of project.
• Indirect cost constitutes over head charges and outage losses.
Overhead charges:
These charges increases linearly with time at constant rate. They include
mantainance charges, insurance charges, establishment charges etc..,.
OUTAGE LOSSES:
Outage losses increases non linearly with time. They include the loss in
penalty, any mishappenings in the projects such as accidents, natural
calamities etc..,.
INDIRECT COST CURVES
INDIRECT COST CURVE OF
PROJECT
Minimum cost
duration
36000
36000
35500
35000 35000
TOTAL
COST
34500
34000 34000
33500
Minimum
cost 33000
7 8 9
DURATION (WEEKS)
Optimum duration
TOTAL COST VS DURATION
SUMMARY
• By the help of this concept cost modelling , we can get
minimum duration and optimum duration of the project.
THANK YOU