CONSTRUCTION OF KUND BYPASS WITH 2 LANE CONFIGURATIONS

FROM EXISTING KM. 33.130 KM. 41.260 (EXISTING LENGTH 8.130 KM.)
DESIGN CHAINAGE KM. 35.130 TO KM 47.700 (DESIGN LENGTH 12.570
KM FOR NH-109 THROUGH AN EPC CONTRACT IN THE STATE OF
UTTARAKHAND

NAME OF CONTRACTOR : – M/S. R.G. BUILDWELL PVT.LTD.


AUTHORITY ENGINEER : – TECHNICAL CONSULTANCY SERVICES, JOINT VENTURE WITH:
MAGOT ENGINEERING CONSULTANTS PVT. LTD. IN ASSOCIATION WITH P.K. ENGINEERS
Salient features of project
Project Name
Construction of Kund Bypass from Existing Chainage Km. 33+130 to Km. 41+260 (Existing Length -
8.130 Km.), Design Chainage Km. 35+130 to Km. 47+700 (Design Length - 12.570 Km.) of NH-109
(New NH - 107) in the State of Uttarakhand on EPC Mode.
 
NH No. (New/ Old) NH-109
Scheme/ Phase  
Mode of the Execution (BOT Toll/ BOT
Annuity/ EPC/ HAM/ Item Rate/ EPC
Others)
No. of Lanes/ Configuration
2-lane road with earthen shoulders configuration & strengthening of NH-109
Length of the Project (in Km) 12.570 km
Total Project Cost (in Cr)
INR 168.66 Cr.
No. of Major Bridges (Number and
Location) 01, Ch. 35+136
No. of Toll Plazas (Number and
Location) NIL
No. of Fly Overs / ROB/ Underpass
(Number and Location) NIL
DPR Consultant Name  
Contractor Name M/s. R.G. Buildwell pvt. ltd., Opp. Shri Shankar Services Station, Village- Raintoli, Rudraprayag, Uttarakhand-266471.
(SPV & Parent Company)
Date of Award (LOA Date) 27-03-2018
Appointed Date 07-05-2018
Construction Period (in Days) 24-Months (730 Days)
Scheduled Date of Completion 06-05-2020
Authority Engineer Technical consultancy services, joint venture with: MAGOT Engineering consultants pvt. ltd. in association with P.K.
Engineers
AE Agreement Date 08.03.2019
AE Mobilization Date 08.03.2019
Structural Consultants
Road Design Consultant
Project Milestone

Project Milestone Schedule date of Milestone as Revised milestone as per EOT Recommended
Schedule-J

Milestone I-180 days 02th November 2018 Achieved on time


Submitted payment for More than 10% of Contract Price.

Milestone II-365 days 06th May 2019


Submitted payment for More than 30% of Contract Price. Achieved on time

Milestone III-550 days 07th November 2019


Submitted payment for More than 60% of Contract Price. EOT Applied for 191 days (23 Nov 2020). Yet to
be sanctioned.

Schedule Completion Date 06th May 2020


PHYSICAL AND FINANCIAL PROGRESS UPTO DATE

• Project Value: 168.66 Cr.

• FINANCIAL PROGRESS AS ON 15 Feb 2020: 51.22 Cr. 30.36 %

• PHYSICAL PROGRESS AS ON 15 FEB 2020: 67.85 Cr. 40.23 %


PHYICAL PROGRESS AS ON DATE

Planned Value of
Cost in Scope % Physical
Cost %
Weightage (As per Progress Physical P ro g re ss
Weightage Physical
in Scope o f till Date in P ro gre ss Cr. Remark
in Project Progress
Com ponent W o r k ) in km/no All over
(%) this item
Component Item Description (%) Km/No Bond (7X4)

1 2 3 4 5 6 7 8 9
A) Widening and strengthening of
Existing road

1. Earthwork up to top of the Sub


7 .0 0 % 5 .5 3 0 4.200 75.95 1.60 26980903.14
Grade
2. Sub base courses
9 .7 9 % 5 .5 3 0 4 .2 0 0 7 5 .9 5 2 .2 4 3 7 7 3 4 7 2 0 .2 5

Road 3. Non Bituminous base course 7 .4 3 % 5 .5 3 0 4 .0 0 0 7 2 .3 3 1 .6 2 27274572.83


30.09%
works
5. Wearing coat 5 .3 9 % 5 .5 3 0 0 .0 0 0 .0 0 0 .0 0 0 .0 0

6. Widening and repair of culverts 0 .2 4 % 2 .0 0 0 .0 0 0 .0 0 0 .0 0 0 .0 0

B1) Reconstruction / New two lane


alignment/ bypass (Flexible
pavement)
1. Earthwork up to top of the Sub 1 2 .4 6 1 .0 6 1 7 8 3 0 5 1 5 .9 7
2 8 .1 9 % 6 .8 2 0 0 .8 5 0
Grade
2. Sub base courses
1 3 .7 1 % 6 .8 2 0 0 .8 0 0 1 1 .7 3 0 .4 8 8 1 6 1 6 3 8 .4 2

3. Non Bituminous base course 9 .3 2 % 6 .8 2 0 0 .8 0 0 1 1 .7 3 0 .3 3 5 5 4 8 2 4 7 .2 7

5. Wearing coat 6 .7 8 % 6 .8 2 0 0 .0 0 0 .0 0 0 .0 0 0 .0 0

d) Reconstruction and New culverts


on existing road, Realigments,
bypasses :
1 2 .1 5 % 50.00 2 3 .0 0 4 6 .0 0 1 .6 8 2 8 3 6 4 0 5 9 .8 7
Culvert (Resonstruction + New)

100 % 9.01 151894657.75


Total

A 2 – New Minor Bridge (leangth >


6 m and < 60m)
(1) Foundation + Sub Structure : On
1 6 .6 7 1 .1 3 1 9 0 9 4 5 2 9 .8 8
completion of foundation work 4 8 .2 1 % 6.00 1 .0 0
insluding fundation for wing and
Minor return wall, abutments, piers
14.09%
Bridge upto the abutments, pier cap.
(2) Superstructure : On completion of 5 1 .7 9 % 6.00 0 .0 0 0 .0 0 0 .0 0 0 .0 0
Superstructures in all respects
including wearing coat, bearings,
expansion signs & marking, tests on
completion etc. complete in all
respect.
100 % 1.13 19094529.88
Total
A 2- New Major Bridges

Major (1) Foundation 3 3 .5 9 % 1.00 0 .0 0 0 .0 0 0 .0 0 0 .0 0


Bridges 4.80%
(2) Substructue 1 7 .3 5 % 1.00 0 .0 0 0 .0 0 0 .0 0 0 .0 0
(4) Wearing coat (including expension 0 .0 0 0 .0 0 0 .0 0
1 .3 6 % 1.00 0 .0 0
joint)
1.10% 1.00 0 .0 0
(5) Miscellaneous item like hand rails, 0 .0 0 0 .0 0 0 .0 0
cras
100 % 0 .0 0 0.00
Total
12.100 3 .0 6 5 2 5 .3 3 0 .2 5 4 2 5 0 4 2 4 .1 5
(ii) Road side drains 1 .9 5 %
12.350 0 .0 0 0 .0 0 0 .0 0 0 .0 0
(iii) Road signs, markings, km stones, 0 .4 9 %
Boundary stones, safety device etc.
Other 51.02 % 3 .5 2 % 12.570 4 .3 2 5 3 4 .4 1 0 .6 2 1 0 4 2 1 8 7 9 .5 1
(iv) Utility duct
Works

2 .0 8 % 2.00 1 .0 0 5 0 .0 0 0 .5 3 8 9 4 9 2 3 4 .5 3
(d) Dumping Zone
0.31% 2518.00 0 .0 0 0 .0 0 0 .0 0 0 .0 0
(v) Road side plantation

(vi) Protection works other than appo


Aches to the bridges elevated sections
/flyovers/grade separators and ROB/
RUBs.
67.82 % 10.350 8 .0 6 0
(a) Reataining wall, Breast wall 7 7 .8 7 2 6 .9 5 4 5 4 4 6 9 7 9 8 .4 6
8.050 1 .1 0 0 1 3 .6 6 1 .4 6 2 4 6 9 2 7 0 3 .9 7
(b) Gabion breast wall 21.00%
4.00 2 .0 0 5 0 .0 0 0 .2 8 4 6 8 9 7 4 3 .1 0
(vii) Safety and traffic managements
1 .0 9 %
During consturction
1 .2 9 % 3.010 0 .0 0 0 .0 0 0 .0 0 0 .0 0
(viii) Thire Beam Crash Barrier
0.45% 6.00 0 .0 0 0 .0 0 0 .0 0 0 .0 0
(ix) Junctions
100% 30.09 507473783.72
Total
Grand Total 40.23 678462971.35
Subgrade preparation and Gabion work in progress at Ch. 40.310
Gabion work in progress in Ch. 40.400
Retaining wall construction in progress at Ch. 40.600
Retaining wall in progress in Ch. 42.100
Hill side protection work with Gabion and drain work in Ch. 42.460
Bridge-6: work in progress in Ch. 42+948
Hill side cutting work in progress in Ch. 44.370
WMM compaction work in Progress in Ch. 45.150
GSB Work in Progress in Ch. 45.500
WMM rolling and compaction work in progress at Ch. 45.950
THANK YOU