Sunteți pe pagina 1din 14

June 28, 2011

PUC Project 34610- AMIT Stakeholder Steering Committee


Anna Grau
anna@enernex.com

6/28/2011
 Brief Review of the Smart Grid Interoperability
Panel (SGIP)
 Priority Action Plan (PAP) Progress
 SGIP Progress to date
 Major June Activities:

◦ Comment period on PAP 18: SEP 1.x to 2.0


Transition and Coexistance
 Upcoming Activities

6/28/2011
6/28/2011
Stakeholder Smart Grid
Category Identified
One Organization, One Vote Standards
Members
(22) Priority
SGIP Action
Plans
Standing
Committee Use
Members (2) Standing Priority Action Cases
At large Committees Plans
Members (3) Requirements

Ex Officio
(non- Standards
Descriptions
voting) Permanent Domain Expert
Members Working Groups Working Groups

SGIPGB SGIP Plenary Conceptual Model

Smart
Smart Grid
Grid Interoperability
Interoperability Panel
Panel and
and Governing
Governing
Board
Board
Products (IKB)
SGIP Administrator
6/28/2011
 Total # of Member Organizations: 672 # of Organizations by Country
• # of Participating Member Organizations: 340
• USA: 599 • North America
• # of Observing Member Organizations: 332
• # of Organizations who joined in March & April: 13 • Europe: 21 (non-US): 29
 Total # of Individual Members*: 1,742 • Asia: 17 • South America: 1
• Oceania: 4 • Africa: 1

Participating Member Organizations by Declared Stakeholder Category  

Stakeholder Categories
 
6/28/2011
* Omits non-active Signatory Authorities.
Priority Action Plan Standard(s) or Guideline(s)

PAP 1 - Role of IP in the Smart Grid Informational IETF RFC

PAP 2 - Wireless Communications for the Smart Grid IEEE 802.x, 3GPP,3GPP2, ATIS, TIA

PAP 3 - Common Price Communication Model OASIS EMIX, ZigBee SEP 2, NAESB

PAP 4 - Common Scheduling Mechanism OASIS WS-Calendar

PAP 5 - Standard Meter Data Profiles AEIC V2.0 Meter Guidelines (addressing use of ANSI C12)

PAP 6 - Common Semantic Model for Meter Data Tables ANSI C12.19-2008, MultiSpeak V4, IEC 61968-9
IEEE 1547.4, IEEE 1547.7, IEEE 1547.8, IEC 61850-7-420, ZigBee
PAP 7 - Electric Storage Interconnection Guidelines SEP 2
IEC 61850-7-420, IEC 61968-3-9, IEC 61968-13,14, MultiSpeak
PAP 8 - CIM for Distribution Grid Management V4, IEEE 1547
PAP 9 - Standard DR and DER Signals NAESB WEQ015, OASIS EMIX, OpenADR, ZigBee SEP 2
NAESB Energy Usage Information, OpenADE, ZigBee SEP 2, IEC
PAP 10 - Standard Energy Usage Information 61968-9, ASHRAE SPC 201P
PAP 11 - Common Object Models for Electric ZigBee SEP 2, SAE J1772, SAE J2836/1-3 , SAE J2847/1-3, ISO/IEC
Transportation 15118-1,3, SAE J2931, IEEE P2030-2, IEC 62196

PAP 12 - IEC 61850 Objects/DNP3 Mapping IEC 61850-80-5, Mapping DNP to IEC 61850, DNP3 (IEEE 1815)

PAP 13 - Time Synchronization, IEC 61850 Objects/IEEE IEC 61850-90-5, IEEE C37.118, IEEE C37.238, Mapping IEEE
C37.118 Harmonization C37.118 to IEC 61850, IEC 61968-9
PAP 14 - Transmission and Distribution Power Systems
IEC 61968-3, MultiSpeak V4
Model Mapping
DNP3 (IEEE 1815), HomePlug AV, HomePlug C&C, IEEE P1901 and
PAP 15 - Harmonize Power Line Carrier Standards for P1901.2, ISO/IEC 12139-1, G.9960 (G.hn/PHY), G.9961
Appliance Communications in the Home (G.hn/DLL), G.9972 (G.cx), G.hnem, ISO/IEC 14908-3, ISO/IEC
14543, EN 50065-1
PAP 16 - Wind Plant Communications IEC 61400-25

PAP 17 - Facility Smart Grid Information Standard New Facility Smart Grid Information Standard ASHRAE SPC 201P

6/28/2011
Milestone: Milestone: Milestone: Milestone: Milestone: Milestone: Milestone: Milestone:
GB PAP SSO Identified Requirements Handoff Standards Handback GB/SGIP Plenary Vote Post to Close PAP
Initiation Vote Catalog or IKB

GB PAPWG Develop SSO Standards Reviews: GB Plenary PAP Closure


Decision Startup Requirements Development PAP, CSWG, Recommendation Decision Paperwork
SGAC, PMO

Note: Some PAPs are in multiple places due


to the status of separate standards they
are involved in.

6/28/2011
2009 2010 2011 2012  
 

Q QQQQQQQQQQQQQ
PAP 3 4 1 2 3 4 1 2 3 4 1 2 3 4 Highlights
Remote meter upgradeability (COMPLETE). Bringing to GB for a vote in
PAP 00 - Meter Upgradeability Standard X                           March.

IETF Smart Grid Internet Protocols RFC. GB recommended addition to CoS


PAP 01 - Role of IP in the Smart Grid           X                 Dec 2010. (COMPLETE)

Wireless Guidelines Report (NISTIR) complete Dec 2010. Version 1


PAP 02 - Wireless Communications for the Smart Grid             X               COMPLETE Jan 2011. Board introduction in April, 2011. Vote by GB in
April.
Currently in public comment period at OASIS. Seeking more utility
PAP 03 - Common Price Communication Model                 X           involvement.

PAP 04 - Common Scheduling Mechanism                 X           Out of final public comment period at OASIS. SDO voting soon.
AEIC guideline completed. PMO requested additional work to address
PAP 05 - Standard Meter Data Profiles               X             technical issues raised by 5 meter manufacturers. AEIC plans to meet with
them in April.
Addressing scope to ensure alignment with NIST and PAP team objectives.
PAP 06 - Common Semantic Model for Meter Data Tables                 X           Difficulty getting participation from vendors and utilities.

PAP 07 - Electric Storage Interconnection Guidelines                       X    Awaiting standards handback from SDOs
PAP 08 - CIM for Distribution Grid Management                   X         Developing requirements affecting IEEE 1547 and IEC 61850-7-420
Close to public review at OASIS. Seeking additional utility stakeholder
PAP 09 - Standard DR and DER Signals                 X           involvement.

*NAESB Energy Usage Information Model complete in February 2011. PAP


PAP 10 - Standard Energy Usage Information             X               to close in Q1 of 2011.

2/3 SAE standards completed and voted on positively by Governing Board.


PAP 11 - Interoperability Standards to Support Plug-in Electric Vehicles             X             Last standard should be done Q2-2011

PAP 12 - IEC 61850 Objects/DNP3 Mapping                   X         IEEE and IEC currently working on standards development
PAP 13 - Time Synchronization, IEC 61850 Objects/IEEE C37.118 Requirements completed. Drafting standards in SDO committees.
                  X        
Harmonization
PAP 14 - Transmission and Distribution Power Systems Model Mapping                 X           Working on use cases and requirements
PAP 15 - Harmonize Power Line Carrier Standards for Appliance Completed BroadBand Coexistence. Working Narrow Band. BB standards
                X         under review, with GB introduction imminent.
Communications in the Home
Use cases and requirements complete. Guideline development by PAP
PAP 16 - Wind Plant Communications                    X         team complete. Passing to SDO when maintenance team established.

PAP 17 - Facility Smart Grid Information Standard                 X            Facility Smart Grid Information Standard
PAP 18 - SEP 1.x to SEP 2 Transition and Coexistence                 X           PAP has just started work;
1 0 0 0 0 1 3 1 7 5     1     
6/28/2011
Recent Accomplishments
• Catalog of Standards process established
• Standards efforts completed (confirmed by Governing Board)
• NEMA Meter Upgradability Standard (PAP 0)
• Wireless Guidelines NISTIR (PAP 2)
• Upcoming standards for confirmation
• OASIS WS-Calendar (PAP 4)
• IEEE 1815 DNP Protocol (PAP 12)
• IEEE & ITU-T G9972 Coexistence of Broadband PLC (PAP 15)
• AEIC Guidelines for Meter Interoperability (PAP 5)
• SGIP branded document format and process
• Initiated Smart Energy Profile (SEP) 1.x to 2 Transition &
Coexistence (PAP 18)
• International coordination
• Letter of Intent with Korea Smart Grid Standardization Forum in
review
• Draft Letter of Intent with European Telecommunications Standards
Institute (ETSI)

6/28/2011
 PAP 18: SEP 1.x to SEP 2.0 Transition and
Coexistance
 Accelerated 3-month timeline
 Leadership Team:
◦ PAP Co-Chair: Larry Kohrmann (Oncor)
◦ NIST Chair: Nada Golmie (NIST)
◦ SGIP Administrator Lead: Anna Grau (EnerNex)
◦ SGIP Architecture Liason: Jeremy McDonald (SCE)
◦ SGIP CSWG Liason: Dave Dalva, (Cisco)
◦ SDO/User Lead: Tobin Richardson (ZigBee Alliance)
◦ H2G Liason: Ken Wacks (GWAC)
◦ Regulator Liason: Paul Centolella (Ohio PUC)

6/28/2011
 Deliverable 1: SEP 1.x to SEP 2 Transition and
coexistence white paper

 Deliverable 2: Requirements document

 Deliverable 3: Governing Board progress report and


recommendation on migration and coexistence path

 Deliverable 4: Requirements transmittal letter to the


ZigBee Alliance

 Deliverable 5: Review of published standard, Best


Practices, and/or application guidelines from the
ZigBee Alliance

6/28/2011
 Comment period:
 Opened June 07, 2011
 Closed June 21, 2011
 Received 200 comments
 Meeting twice-weekly to resolve the
comments (accepted, noted, accomodated,
rejected)
 Presenting an update to the Governing Board at the
July 12 Montreal meeting

 Once consensus is reached on the White Paper, a


Governing Board package will be prepared with
reviews by the CSWG and SGAC

6/28/2011
 Register for meetings and email list:
http://collaborate.nist.gov/twiki-sggrid/bin/view/SmartGrid/
PAP18SEP1To2TransitionAndCoexistence

 Listserv has 140+ members, with 40-50


regularly participating in twice-weekly calls

 White paper (80+ pages) is near completion


and will be first official “SGIP” branded
document

6/28/2011
 Spring 2011 SGIP Meetings:
◦ F2F Meetings
July 12-14: Face-to-face in Montreal
December 5-8: Face-to-face in Phoenix
◦ Virtual Meetings
Sep 15; Nov 10

 Use and contribute to the Use Case Database:


http://collaborate.nist.gov/twiki-
sggrid/bin/view/SmartGrid/IKBUseCases

 Participate on the panel or working groups:


To join: http://collaborate.nist.gov/twiki-
sggrid/bin/view/SmartGrid/SGIP

6/28/2011

S-ar putea să vă placă și