Total Project Cost (in Cr) INR1273.71Crore. (Construction Cost- INR 873.00 Crore as per CA)
EPC Agreement Date 10.11.2016
Appointed Date 14.01.2018
Schedule Completion Date 11.07.2020 (30 months, 910 days from Appointed Date)
Revised Completion Date 28.06.2022 (Submitted by Contractor)
4
Project Milestones
(Occurring Revised
from Financial Start Schedule completion
Milestone Remarks
Appointed Target Date completion as per
Date) Contractor
10% of
Milestone-I 180 days Contract 12.07.2018 28.06.2020
Price
30% of
Milestone-II 400 days Contract 17.02.2019 03.02.2021 Current Physical
Price Progress (In
financial terms) is
70% of 7.95%.
650 days Contract 14.01.2018 25.10.2019
Milestone-III 11.10.2021
Price Financial Progress
is 4.71%.
100% of
Schedule
910 days Contract 11.07.2020 28.06.2022
Completion Price
Scope of Work
Highway
Sr. No. Description Total Scope (in km)
1 Earthwork up to Subgrade 23.192
2 Granular Subbase 23.192
3 Base (WMM) 23.192
4 Dense Bituminous Macadam 24.007
5 Bituminous Course 24.007
Structure
Sr. No. Structure Type Total Scope (Nos.)
1 Major Bridge 6
2 Minor Bridge 11
3 Culvert 80
4 VUP 3
Tunnel
Sr. No. Chainage From Chainage To Length (m) Type of Tunnel
1 196+700 198+000 1300.00 Twin Tube
2 198+410 199+010 600.00 Twin Tube
3 212+500 212+883 383.40 Twin Tube
Work Progress Details as on 31-05-2020
Highway
Sr. No. Description Target (in km) Achieved (in km) Remarks
1 Earthwork up to Subgrade 23.192 5.50
2 Granular Subbase 23.192 5.20
3 Base (WMM) 23.192 5.00
4 Dense Bituminous Macadam 24.007 0.00
5 Bituminous Course 24.007 0.00
Tunnel
Sr. No. Chainage From Chainage To Length (m) Type of Tunnel Work Status Remarks
Heading
196+700 198+000 1300.00 115.00 m
done only.
1 Twin Tube
Heading
196+700 198+000 1300.00 38.00 m
done only
Work in
198+410 199+010 600.00
2 Twin Tube progress
198+410 199+010 600.00 - No Activity
212+500 212+883 383.40 -
3 Twin Tube
212+500 212+883 383.40 -
Work Progress Details as on 31-05-2020
Structure
Major Bridge
3 1 - 2
Culvert
80 17 10 53
Forest Clearance
NIL
Stage -1 approval received on 07.09.2017.
Tree cutting completed except at inaccessible
locations, which shall be taken up during hill
cutting/ excavation works at these locations.
Stage -2 (final approval) received on 13.11.2017.
Utility Shifting work Estimates
Estimat
Estima e
No. of Shifting
Sl. tes Date of Pendin
Utility Division Estimate Status Remarks
No. Appro approval g for
s (in %)
ved approv
al
Mandi 1 1 02-05-2018 0 0% (Dept. charges
deposited)
Gohar 8 8 17-05-2018 0 0%
1 HPSEBL
Sunder Contractor has
2 2 14-11-2018 0 0% recently taken
Nagar
up shifting of
Mandi 2 1 14-07-2018 1 20% I&PH &
2 I&PH
Baggi 2 1 14-07-2018 1 10% Electrical
utilities works
Additional 02
IPH Estimates
3 BBMB Pandoh 1 1 12-07-2018 0 0% are under
verification.