PROJECT GUIDE
M.R.L. SHARMA(SR.MANAGER )
CONTENT
PROJECT OBJECTIVE
OVERALL
Project Objective
To meet design efficiency by applying necessary and corrective measures.
COOLING TOWERS
Frame and casing : RCC built counter flow cooling tower Fill : PVC Drift eliminators : Plastics Nozzles : PVC Fans : Glass reinforced polyester
COMPONENTS MAKE
COMPONENTS : MAKERS
CT-FAN
CT-MOTOR
FILLS
MEASURED PARAMETERS
Wet bulb temperature of air Dry bulb temperature of air Cooling tower inlet water temperature Cooling tower outlet water temperature Water flow rate
PERFORMANCE PARAMETERS
1. Range 2. Approach 3. Effectiveness 4. Evaporation 5. Cycles of concentration 6. Blow down
1. RANGE
Difference between cooling water inlet and outlet temperature: Range (C) = CW inlet temp CW outlet temp
Hot Water Temperature (In)
Range
Approach
2. APPROACH
Difference between cooling tower outlet cold water temperature and ambient wet bulb temperature: Approach (C) = CW outlet temp Wet bulb temp
Hot Water Temperature (In)
Range
Approach
3. EFFECTIVENESS
Effectiveness in % = Range / (Range + Approach) = (CW in temp CW out temp) (CW in temp Wet bulb temp) X 100
4. EVAPORATION
Water quantity (m3/hr) evaporated for cooling. = theoretically, 1.8 m3 for every 10,000,000 kcal heat rejected. (approx. value as the evaporation varies according to the atmospheric condition) = 0.00085 x 1.8 x circulation rate (m3/hr)x (T1-T2) T1-T2 = Temp. difference between inlet and outlet water
6. BLOW DOWN
Evaporation Loss = (C.O.C. 1)
Data Collection
COOLING TOWER RANGE = 8.60 COOLING TOWER APPROACH = 5.90 COOLING TOWER EFFICTIVENESS (%) RANGE/ (RANGE+APPROACH)x100 8.6/(8.6+5.90) x100 59.30 RATED COOLING TOWER EFFICTIVENESS (%) RANGE/ (RANGE+APPROACH) x100 10/(10+4) x100 71.42
EVAPORATION IN M3/Hr 0.00085x1.8x CIRCULATION RATE(m3/h)x(O/L-I/L) 0.00085 x1.8 x12000 x8.60 158 m3/hr DESIGN EVAPORATION IN M3/Hr 0.00085x1.8x CIR. RATE (m3/hr)x(O/L-I/L) 0.00085 x1.8 x 13300 x 10 = 203.49 m3/hr
BLOW DOWN (ACTUAL ON FORMULA BASIS) EVAPORATION LOSS/(C.O.C.-1) 158/(6.66-1) =27.9 M3/Hr DESIGN BLOW DOWN 203.49/(10-1) = 22.95 M3/Hr BLOWDOWN IS SLIGHTLY MORE THAN DESIGN VALUE
MAKE UP WATER REQUIRED EVAPORATION LOSS + BLOW DOWN LOSS 158 + 27.90 =185.9 M3/Hr
OBSERVATIONS: LESS EVAPORATION THAN DESIGN VALUE 1. LACK OF COOLING HENCE AFFECTING THE RANGE. 2. LESS AIR FLOW THAN REQUIRED. 3. BLOCKED SPRAY NOZZLES. 4. SCALING / FOULING ON FILL PACKS.
OVERALL.
(1) PERIODICAL CHECKING AND CLEANING OF ALL
(2) (3) (4) (5) SPARY NOZZLES. OPTIMISE COOLING TOWER BLADE ANGLE ON SEASONAL AND LOAD BASIS. DEFECTIVE DRIFT ELIMINATOR REPLACEMENT. DAMAGED COATED FILL PACK REPLACEMENT. CONSIDERATION SHOULD BE TAKEN IN ORDER TO MAINTAIN BALANCE BETWEEN AUXILLARY POWER COMSUMPTION & COOLING WATER TEMPERATURE. (6) MAINTAING WATER QUALITY PARAMETERS STRINGENTLY THERE BY MINIMIZING BLOWDOWN