Documente Academic
Documente Profesional
Documente Cultură
INGENIERA DE LA PRODUCTIVIDAD
NOVEMBER 13, 2008
NOMBRE Marco Antonio Silva Javier Snchez Flores Miguel Casillas Velasco Carlos Sergio Arrieta Serrato MATRICULA A01048110 A00266037 A00343715 A00343714 SEDE CD. JUAREZ SALTILLO COLIMA COLIMA
Problem Definition
Shipping costs in May increased $61k due to excessive overnight shipments of CPE
Root Causes
Unstable Supply Chain Shipping costs in May increased $61k due to excessive
overnight shipments of CPE
> Stock-out due to:
Delay in approving PO Delay from Vendor in getting the PO in their system Delay in normal vendor shipping time frame
Re-Stocking analysis is manual, time consuming, and cumbersome Systems provide pieces of data that must be manually manipulated
in Excel to obtain: > Field shipment orders > Stock replenishment quantity
Start
Sales
Information Systems
Inventory Inventory Gets the report Of products needed for two week period
Sub- System 2
Sub System #3
Current Process
INVENTORY HANDLING PROCESS
Inventory goes to MSS and pull Reports in order to find what's needed to be shipped to market sites CPE Summary Report is sent to warehouse Electronically Warehouse verifies report with current inventory (Manually) Warehouse prepares material to be shipped Warehouse ships the product/s to market sites Market sites receive equipment and enter it into the system Request of installation is needed and Market site assigns serial # to customer PO and change the classifications Field Technician return to the system and delete part from the system.
Installed YTD Report (IR) Supplier receives POs and send back a confirmation email with delivery time
Cleaning Reports
End
Delay Process
.1
.5
40
.5
.25
.5
.25
40
.1
.25
40
160
May situation
Balance RCP
-103
-206
-103
90
90
90
90
206
206
Demand 90 April
90
90
90
103
103
103
103
May
June
Supplier Lead time increased 2 weeks. Internal Approval process was delayed 1 week from our normal 1 week period. This causes overnight shipments from China and to US market
Improvement Opportunities
Quicker PO approval process Automatic shipping and re-stocking analysis Decrease supplier lead time Utilize bar code scanners to integrate with inventory system
Improvement Actions
Develop fully automated daily report to provide re-stock amounts and field shipping details.
Field Shipping detail:
> > > > > > > Order # CLLI TSP Date Market Equipment Part Number Quantity
Re-Stock Amounts
>
Stock Recovery
0 0
180
180
180
180
77
90
90
90
90
103
103
Demand 90 April
90
90
90
103
103
103
103
May
June
2 weeks ahead we see a change in demand and we place an order to compensate safety stock. 26 Supplier has been committed to supply every week. But what if they fail? We place and order for material taken from safety stock. What if they fail another week. We use remaining stock plus the one that came in. This Model shows that we are covered for two week period.
10
10
Contingency Plans
We considered the possibility of alternative company to stock equipment. Based of annual cost we did not considered beneficial. We will have safety stock of 3 weeks for the following products: 2431-8 Safety stock will be distributed as follows: 2 weeks on ware house 2431-16 1 week on the field. vwic-1mft-t1 vwic-2mft-t1 2432-24
1. 2. 3. 4. 5.
11
11
Start
Inv. Goes to the System and gets a report of what is needed to ship for the market sites
Inv. Ships products and enters data into Inventory Control System (Excel Spreadsheet)
No Is there any product colored Red? Save the document and exit. END
Yes
End
12
12
Summary
Enhanced PO approval process Automated Field distribution reporting
Eliminated manual labor increasing accuracy
13
13