Sunteți pe pagina 1din 12

Hydro Power Potential in Pakistan

An Overview
Muhammad Adil Javed Matrikelnummer: 2709215

Hydro Power in Pakistan Comparison, Production and Potential


60000 50000 40000 MW 30000 20000 10000 0 Currently Producing Projects in Pipeline Potential 6464 1422 11,68% of potential 55300

Hydro Power Stations Currently in Operation

Hydro Power Stations Under Construction

Total HydroPower Potential : 55300 MW

Total Hydro Power Potential in Pakistan


Sr. 1 2 3 4 5 6 7 8 9 Category HYDEL STATIONS IN OPERATION UNDER CONSTRUCTION READY FOR IMPLEMENTATION (PUBLIC SECTOR) FEASIBILITY STUDY COMPLETED (PULIC SECTOR) FEASIBILITY STUDIES IN HAND (PUBLIC SECTOR) READY FOR IMPLEMENTATION (THROUGH PPPP) FEASIBILITY STUDIES IN HAND (THROUGH PPPP) PROJECTS ADVERTISED BY PPIB FOR PRIVATE SECTOR IDENTIFIED POTENTIAL FOR FEASIBILITY STUDY Capacity (MW) 6464 1422 9858 173 11351 1155 1909 1620 21247

TOTAL 55300

Analysis of Hydro Power Potential: By Provinces


PUNJAB AJK 11% GB 35% 12% KPK 42%

Imporant On Going Projects


Diamer Basha Dam 8,1 MAF Storage, 4500 MW Munda Dam, Multipurpose Project 1,3 MAF Storage, 740 MW New Bong Escape Project Run off River, 84 MW Jinnah HPP Jinnah Barrage, 86 MW

Diameer Basha Dam Project


8,1 MAF Annual Surface Water Storage Installed capacity of 4500 MW Reduce Siltation in TarbelaDam Pay back in 8 years Annual Earning of 1,98 Billion It ll be completed in 7-8 years

New Bong Escape Project


First Hydro Independent Power Producers (IPP) Run of River, 84 MW Success of PublicPrivate ownership

Problems
Lack of Public and Political Will Dispute over water Deficiency of Technical Capability Absence of Technology High Cost & Poor Government

Recommendations
Create Awareness & Educate people Encourage use of Run of River HPP Involve Foreign Consultants for Technical Training Work with ONLY those who Transfer Technology Encourage Private-Public Ownership Educate investors about high cost to benefit ratios

S-ar putea să vă placă și