SYNERGY PROPERTY DEVELOPMENT SERVICES PVT LTD Weekly progress report

Divyasree NSL Orion- B7


(B+LG+G +14 + Terrace floor)

Project Update
2nd May 2012

PROJECT MILESTONES

FIRST TO LAST

Sl. No.
PM1 PM2 PM3 PM4 PM5 PM6 PM7 PM8 PM9 PM10 PM11 PM12 PM13 PM14 PM15 PM16 PM17 PM18 PM19 PM20 Project kick off

Milestone Description

Revised Target Projected / Date Ach. Date


09-Aug-2011 25-Feb-2012 03-Sep-2012 01-Apr-2013 01-Jun-2013 20-July-2013 18-Aug-2013 05-Sep-2013 07-Sep-2013 08-Sep-2013 10-Sep-2013 16-Sep-2013 18-Sep-2013 19-Sep-2013 21-Sep-2013 22-Sep-2013 24-Sep-2013 26-Sep-2013 29-Sep-2013 30-Sep-2013 09-Aug-2011 28-Mar-2012 03-Sep-2012 01-Apr-2013 01-Jun-2013 20-July-2013 18-Aug-2013 05-Sep-2013 07-Sep-2013 08-Sep-2013 10-Sep-2013 16-Sep-2013 18-Sep-2013 19-Sep-2013 21-Sep-2013 22-Sep-2013 24-Sep-2013 26-Sep-2013 29-Sep-2013 30-Sep-2013

Status (RAG)
Completed Completed On track On track On track On track On track On track On track On track On track On track On track On track On track On track On track On track On track On track

Lower Ground floor slab concreting Sixth floor slab concreting Roof slab concreting Hand over to Fit out (6th & 7th Floor) Completion of Block work & plastering HSD installation Electrical High side testing & commissioning Plumbing works in Office floor toilets & Terrace HVAC Low Side Testing & commissioning Fire Fighting testing & commissioning Electrical Low side testing & commissioning Chiller commissioning DG commissioning Common area finishes Faade granite cladding & painting works External Development Faade / Structural Glazing works Passenger and service elevators Base building completion

Today

STATUS REPORT

today

FIRST TO LAST

Project Manager: Cost Status: G

B. Sathyanarayana Resource Schedule G G

Content G

Plan: Act/LE:

PM1 09-08-2011 09-08-2011

PM2 25-02-2012 28-03-2012

PM3 03-09-2012 03-09-2012

PM4 01-04-2013 01-04-2013

Achievements (previous weeks):

Targets (next weeks):

Works carried JMC completed following in building foot print area: Retaining wall from LGF to GF 99% completed. Pour-1 & 2 FF Slab concreting completed. Pour-3 FF Slab works 95% completed. Pour-4 & 5 FF Slab shuttering work 70% and reinforcement
30% completed.

Pour - 6 FF columns works in progress. Pour -1 SF column works in progress. South & East side retaining wall - External membrane water
proofing works 35% to complete.

Works planned JMC to complete following in building foot print area: Lift core area GF slab concreting to complete. Pour-3 & 4 FF Slab concreting to complete. Pour- 5 FF Slab works 90% to complete. Pour 6 FF columns to complete Pour 1 SF columns to complete Pour 2 SF columns 40% to complete South & East side retaining wall - External membrane
water proofing works 40% to complete.

2nd Tower Crane erection completed. Schedule: FF slab completion anticipated on 25th Apr 12 is deferred till
10th May 12 due to insufficient manpower and outsourced RMC. JMC to fulfill resources and manpower as committed in management meeting held on 27th April 12.

Back filling works to re-start with outsourced Murrum. Schedule: JMC to submit Micro schedule as per the committed
dates considering 14 days slab cycle.

Contractual: NA Procurement: Plumbing and fire fighting packages under review. Team reviewed on Lift Vendors Technical specifications for
further process.

Contractual: NA Procurement: Batching plant equipment to be mobilized to site. OTT for Electrical HT package to be scheduled. STP package - Final recommendation to be shared.

Achievements (previous weeks):

Targets (next weeks):

FIRST TOLAST CLIENT LIST

Quality & Safety: JMC submitted 7 days design mix report for Ultra tech cement
and to share for 28 days for consultant review.

Quality &Safety 2nd Tower Crane 3rd party test certificate to be


submitted for operation.

SYN issued NCRs15 & 16 on 26th Apr 12 , JMC to take


immediate action to rectify the same.

SYN generated Internal Quality and safety Audit report -02 and
fulfilled by site team .

JMC to closed balance NCRs by 7th May 12. JMC to submit 3rd party design mix with 100% ROBO
sand .

DNIPL shared material test certificates for cement . SYN highlighted on material stacking and safety measures on
site for JMC action.

JMC to increase team exclusively for housekeeping


works at site. QS/Billing/Variations

QS/Billing/Variations: SYN shared status on RA bills pending payment to DNIPL on RA-05 Adhoc for 54.73 lakhs RA-05 Final for 6.47 lakhs
SYN shared the outsource Murrum quantities to DNIPL for approval. Other Important :

27th Apr 12 for necessary action. DNIPL released payments for:

DNIPL to release payments for following: RA-06 Adhoc for 53.54 lakhs RA-06 Final for 24.11 lakhs NT-Item 02 for 3.64 lakhs DNIPL to approved the quantity of outsource Murrum
submitted for the back filling works.

Reinforcement steel indent 574MT, part PO to be


released by DNIPL.

Meeting with JMC higher management was held on

Apr 12 for discussing slab concreting delays and insufficient resources. design review submission on 2nd May 12.

27th

Other Important: RSP services to review on design requirements for


Atrium to share preliminary schemes.

DNIPL shared interior layout, Conserve is planning IGBC RSP team approved on 6th Floor Shuttering shared by PSC for
further process.

RSP Arch to share following: Revised elevations, sections, BOQ for faade by 5th
May 12

SYN shared comments on Atrium drawings for RSP review and


incorporation. RSP services shared Basement ventilation as separate package for review on 26th Apr 12. RSP services shared hard copies for tender drawings of fire fighting, Electrical, plumbing and HVAC low side packages.

Revised Common area presentation by 7th May 12 Updated architectural drawings for Atrium

FIRST TO LAST

Achievements (previous weeks):


Status of Block work, Plastering and IPS at site:Floor Basement LG Ground 1st 2nd 3rd 4th 5th 6th 7th 8th 9th 10th 11th 12th 13th 14th Terrace Slab N.A 100% 100% 60% 2% Block Work Plastering IPS

Targets (next weeks):

Target for Block work, Plastering and IPS at site:Floor Basement LG Ground 1st 2nd 3rd 4th 5th 6th 7th 8th 9th 10th 11th 12th 13th 14th Terrace Slab N.A 100% 100% 80% 8% Block Work Plastering IPS

FIRST TOLAST CLIENT LIST

Deviations and issues (previous weeks):

Important Risks & Corrective Actions: Insufficient man power, engineers to complete planned works at site by JMC. Corrective measure: Insufficient manpower for planned works. JMC to augment the manpower as committed on 27th Apr 12 for avoiding delays in slab concreting and to achieve fourth floor slab completion Batching plant production for B7 to be resolved by JMC. Corrective measure: Batching plant will be mobilized to campus for erection by 7th May 12 and production to start from 15th May 12. However, JMC to maintain required quantity of concrete for Orion B7 as agreed.

Execution of Atrium columns at grid I11 & H11 as per


proposed detail on anchoring to existing B6 footings. PSC to visit site on 2nd May 12 to inspect the existing footings and review the site condition for advice.

FIRST TO LAST

PROJECT STATUS PHOTOGRAPHS: 30-04-12 Vs 24-04-12 Previous Week Present Week

View from South East side of site

View from South East side of site

View from South side of site

View from South side of site

FIRST TO LAST

PROJECT STATUS PHOTOGRAPHS: 30-04-12 Vs 24-04-12 Previous Week Present Week

View from South West side of site

View from South West side of site

View from North West side of site

View from North West side of site

FIRST TO LAST

PROJECT STATUS PHOTOGRAPHS: 30-04-12 Vs 24-04-12 Previous Week Present Week

View from North East side of site

View from North East side of site

View from North side of site

View from North side of site