Documente Academic
Documente Profesional
Documente Cultură
The ATCSoft project was launched, and steady progress was made When the team set out to integrate the ATCSoft application with existing RADAR equipment, however, they hit a snag
The team members could not figure out how to integrate the systems
The RADAR system did not have appropriate physical connections, nor was there an appropriate driver for the interconnection
The project manager had to hire engineering consultants to work out the integration details This diversion took 2 months and cost a significant amount of money (additional labour, consultancy fees, and business value)
Despite the large salary increase he was offered, Rory took a good offer with another firm
When some tests showed that the neural net was not fast enough to make real-time decisions, the team had no immediate answers A bug was found that sent the avatars wandering aimlessly around the maze in a circuit, when certain rare conditions were present Again, the team had no idea how to approach the problem
What happened?
What happened in both of these case studies?
What happened?
What happened in both of these case studies?
What happened?
What happened in both of these case studies?
What happened?
What happened in both of these case studies?
Risk Mitigation
In the ATCSoft project, the team should have investigated the integration of various systems at the start of the project
Given adequate time, the integration could have been worked out before it was needed
Risk Mitigation
In the ATCSoft project, the team should have investigated the integration of various systems at the start of the project
Given adequate time, the integration could have been worked out before it was needed
In the PathFinder project, Rory should have been the projects neural network consultant
He could have thoroughly documented the neural network code as it was developed He could have had seminars for team members, explaining the concepts of neural networks Understanding neural networks, the team would have a better chance of carrying on without Rory
Risk Assessment
Risk Assessment
The following describes the risk assessment process:
1. Identifying risks
2. Estimating a risks cost/effects
5. Evaluating/comparing alternatives
Once risks are assessed, a project manager should plan for them
Risk Assessment
Risk Identification
Risk Identification
The first step in risk analysis is to identify the projects risks
Each project has its own set of unique risks How do you identify something that could potentially be hidden until it is too late? However, risk identification can be made easier using categories of risk
This leverages the knowledge of many project managers who have experienced risks
Categories of Risk
Here is one way to categorize risks:
Organizational risks
Lack of support or resources Inadequate or inefficient management Interference from other projects & management agendas
p.65
Categories of Risk
Here is one way to categorize risks (continued):
Constraint risks
Deadlines Resources
Business risks
Marketability Timing Vendor delays Economic conditions
External risks
Changing laws and regulations Dependence upon suppliers and contractors
p.65
After creating the work breakdown structure Before creating the schedule
Common Risks
These risks are related to schedule:
Feature creep
New features are frequently added after development has started
Requirements gold-plating
Too much documentation
Implementation gold-plating
Developers are working on the perfect implementation
Inadequate design
Too little attention has been paid to design
Silver-bullet syndrome
A trendy technology was expected to produce the equivalent to 10,000 lines of code in only 50 lines of code
Contractor failure
A contractor lacked expertise/commitment needed to do the job on schedule
Risk Assessment
Estimating Risk Cost & Effects
e.g. A project using a new technology might realize that the technology is inadequate or unreliable
Now, the application must be retrofitted to another (trusted) technology Much of the software may need to be replaced The cost in this case is the cost of developing the obsolete components In addition, there may be hidden costs due to delays (such as customer confidence or personnel availability)
e.g. In some projects there is a risk that a key developer will leave the project
If the key developer leaves, what will it take to replace her? Given market conditions, you might estimate a replacement in 2 months Some project deliverables might be delayed by up to that amount in her absence Also, you may have to consider signing bonuses, relocation expenses, travel expenses, and other hiring costs It depends on the project whether or not these costs are considered high
Risk Assessment
Estimating Risk Likelihood
e.g. The likelihood that a technology will fail can usually be estimated accurately Tristan: How likely is it that the technology (e.g. PHP) will fail to meet our expectations? Carlos: PHP has been used for many projects successfully. There have been many failed PHP projects, but very few cite the technology as the cause of the failure. On the other hand, there have been many very high-profile PHP projects. Carlos: Consider FaceBook, which has similar (but more complex) functionality to our GroupWare application. Tristan: FaceBook uses PHP? That is similar to our project. Carlos: I cant forsee any features we will need that will be impossible in PHP.
e.g. How likely is it that Sarah Windermere will leave the project?
Her project manager may be aware of her job satisfaction, or her peers However, a face-to-face meeting to assess her job satisfaction has no substitute
Example:
Tristan: Sarah, weve been very happy with your performance on previous projects. You will be an integral part of this upcoming project. Are there any concerns you have about this project or your job? Sarah: Not really. I like the challenges. Tristan: If you do have any concerns, I want you to tell me right away. Your satisfaction and motivation are very important to me. Sarah: Actually, I have been having a tough time working with Gerard. He doesnt respect my leadership, and tries to rally the team against me. Tristan: How does the rest of the team feel about his actions? Sarah: Many of them either have confronted him about or have told me they dont agree with him. Tristan: Ill have a talk with your team to confirm what youve said, but it sounds like Gerard and I need to have a talk about each of your responsibilities.
e.g. For Sarah, the best person to ask would be her (followed by her direct supervisor) e.g. For PHP technology, anyone who has used PHP for a previous project
Risk Assessment
Identifying Alternatives
Identifying Alternatives
e.g. What are the alternatives to PHP?
Identifying Alternatives
e.g. Are there alternatives to Sarah?
Gerard Lepalme: Has leadership, but lacks the technological expertise Helen Driskoll: Knows some of the technology, but is very inexperienced
Risk Assessment
Evaluating & Comparing Alternatives
JSP/J2EE
Much of our existing staff is familiar with this technology Using this technology would require a few days of training Architecture should be more robust
ASP.NET
We have no in-house personnel trained in this technology Using this technology would require at least one month of training Development of user interfaces, however, should be made easier
Ruby/ROR
We have only a few in-house developers trained in this technology Using this technology would require weeks of training Development should be made easier Architecture should be more robust
Perl
We have no in-house personnel trained in this technology Using this technology would require at least one month of training
Assigning Probabilities
There are many approaches to assigning probabilities
It often doesnt matter if you only care about the value relative to other risks Very low: Low: Medium: High: Very High: 0.05 0.20 0.40 0.60 0.80
Risk Assessment
Bringing It All Together
Risk Assessment
Ok, weve collected data What is next?
Risks are evaluated and planned for if they have significant likelihood and significant costs Risks are given a score for each development phrase The stage scores are totaled to calculate the risks score The risk likelihood is expressed in percentages The risk cost is expressed in weeks These two are multiplied to calculate an expected loss Similar to risk exposure, but percentages are also used for cost
Medium
High
Ignore Ignore
Ignore Consider
Score
1 2 3 3 2 11
3 2 1 1 1 8
1 2 2 4 4 13
5 6 6 8 7 32
Cost
Risk Exposure
5%
40%
20 weeks 1 week
10 weeks 4 weeks
Impact
Risk Exposure
0.05
0.40
0.60
0.40
0.03
0.16
Evaluating Alternatives
When considering alternatives, you can apply the same techniques to all alternatives e.g. J2EE vs. ASP.NET vs. RoR
Cost
Risk Exposure