Huawei Confidential
Agenda
Introduction SSV Audit SSV DT Test SSV Report SSV Trouble shooting
Introduction
Single Site On-Air Mode
Project Start
Nomin al Plan
Detail Plan
SSV
Project End
Project Start
Nomin al Plan
Detail Plan
Project End
Huawei Confidential
Page 3
Work flow
Start
SSV is to solve
SITE Audit Tuning Implementation Y SSV DT Approved
Basic Functions
Coverage
Rx Quality
N
Tuning Proposal
End
Huawei Confidential
Page 4
SSV Tools
M2000 LMT&MML Probe & Assistant TEMS & MapInfo NASTAR U-Net
Huawei Confidential
Page 5
Agenda
Introduction SSV Audit SSV DT Test SSV Report SSV Trouble shooting
SSV Audit
From BSS Part
Single Site Test Record from BSS engineer Site Activated All Cell/TRX/Channels Un-locked Idle Timeslot Test is closed No Alarm may influence SSV Test
Huawei Confidential
Page 7
Agenda
Introduction SSV Audit SSV DT Test SSV Report SSV Trouble shooting
SSV DT Overview
Establish DT Methodology
Tool Setup: Tool, Digital Map, FTP Server, APN, SIM Test Method: Idle, Long Call, Short Call, PS Special requirement: Locking BCCH or not. DT Route Planning SSV Report Template
Huawei Confidential
Page 9
SSV DT Methodology(0)
Special Requirement
Indoor Test or Outdoor Test Locking BCCH or not Forbid HO or not
Huawei Confidential
Page 10
SSV DT Methodology(1)
Test Method
Idle
Long Call
Short Call
PS
Huawei Confidential
Page 11
SSV DT Methodology(2)
SSV DT Route
Principles for Test route for SSV be defined together with customer The test routes should cover all sectors of each sites, main road and important areas
A1
A
C1 B1 A2
C2 A3 B2
C B
C3 B3
Huawei Confidential
Page 12
SSV DT Methodology(3)
A proposed DT Route Definition Principle
Suburban/Highway Site
Urban Site:
Huawei Confidential
Page 13
SSV DT Methodology(4)
PS Test
The setting of Mobile: APN SIM card information Selecting Test Item according to Customer Requirement
Huawei Confidential
Page 14
During DT test
Monitor the DT real results: Call setup, HO, Call drop, RxLev, RxQual, C/I Analyze as much as possible. Ask driver to stop when abnormal Pay attention to: bad quality, possible interfering sites, and topography and site locations Correct small problems discovered immediately
After DT Test
DT log files and DT problem records.
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Page 15
Agenda
Introduction SSV Audit SSV DT Test SSV Report SSV Trouble shooting
SSV Report
SSV report template
What is the usage for CI plot? What is the usage for BCCH plot? What is the usage for RxLev plot? What is the uasge for RxQual plot?
Huawei Confidential
Page 17
Agenda
Introduction SSV Audit SSV DT Test SSV Report SSV Trouble shooting
Huawei Confidential
Page 19
Basic Verification
To check basic parameters: LAC,CI,BCCH, BSIC, MA, MAIO To check downlink coverage
Normal cell
Huawei Confidential
Page 20
RxLev Verification
Check whether the receive level of the BCCH and TCH are greater than the predefined threshold and are stable.
Huawei Confidential
Page 21
RxQual Verification
RxQuality Non-FH FH 0 Good Good 1 2 3 4 5 Fair 6 Poor Poor 7 Poor Poor Good Good Good Fair
Huawei Confidential
Page 22
Event-Access Failure
Huawei Confidential
Page 23
Event-Call Drop
Huawei Confidential
Page 24
Event- Handover
Huawei Confidential
Page 25
Thank you
www.huawei.com