Sunteți pe pagina 1din 3

Assignment - Crearea planului de proiect i monitorizarea realizrii

sale
Name Duration Start Finish Predecessors
trasare teren 1 day
7/21/14 8:00
AM
7/21/14 5:00
PM
aprovizionare materiale 2 days
7/18/14 8:00
AM
7/21/14 5:00
PM
sapatura mecanizata 2 days
7/22/14 8:00
AM
7/23/14 5:00
PM
turnare 1 day
7/22/14 8:00
AM
7/22/14 5:00
PM 2
montare armaturi in talpi 1 day
7/25/14 8:00
AM
7/25/14 5:00
PM
turnare beton in talpi 1 day
7/28/14 8:00
AM
7/28/14 5:00
PM 5
montare armaturi pereti subsol 6 days
7/29/14 8:00
AM
8/5/14 5:00
PM
turnare beton pereti subsol 1 day
8/6/14 8:00
AM
8/6/14 5:00
PM 7
umpluturi exterioare 1 day
8/7/14 8:00
AM
8/7/14 5:00
PM
umputuri interioare + pietris 2 days
8/8/14 8:00
AM
8/11/14 5:00
PM
montare armaturi in plaxa si grinzi subsol 4 days
8/12/14 8:00
AM
8/15/14 5:00
PM
turnare beton in placa si grinzi subsol 1 day
8/18/14 8:00
AM
8/18/14 5:00
PM 11

ID Name Initials Type
Material
Label
Max
Units
Standard
Rate
Cost Per
Use
1 Topometrist T Work 100% $200.00/h 0
2
Muncitor
necalificat M Work 300% $100.00/h 0
3 Betonist B Work 300% $150.00/h 0
4 Excavator E Work 100% $250.00/h 0
5 Camion 5 to. C Work 100% $200.00/h 0
6 Betoniera Be Work 200% $200.00/h 0
7 Plasa sudata P Material 500 kg $100.00 0
8 Balastru B Material 10 mc $150.00 0
9 Ciment C Material 40 saci $300.00 0
10 Formare F Cost 0

Task Name Resource Name % Work Work Units
Complete
trasare teren Topometrist 0 8h 100%
aprovizionare materiale Camion 5 to. 0 16h 100%
aprovizionare materiale
Muncitor
necalificat 0 16h 100%
sapatura mecanizata Excavator 0 16h 100%
turnare
Muncitor
necalificat 0 8h 100%
turnare Betoniera 0 8h 100%
turnare Ciment 0
1 40
saci
1 40
saci
turnare Betonist 0 8h 100%
montare armaturi in talpi
Muncitor
necalificat 0 8h 100%
turnare beton in talpi Betoniera 0 8h 100%
turnare beton in talpi Balastru 0
2 10
mc 2 10 mc
turnare beton in talpi
Muncitor
necalificat 0 8h 100%
montare armaturi pereti subsol
Muncitor
necalificat 0 48h 100%
turnare beton pereti subsol Balastru 0
1 10
mc 1 10 mc
turnare beton pereti subsol Betoniera 0 8h 100%
turnare beton pereti subsol Betonist 0 8h 100%
turnare beton pereti subsol
Muncitor
necalificat 0 8h 100%
umpluturi exterioare Balastru 0
1 10
mc 1 10 mc
umpluturi exterioare Betoniera 0 8h 100%
umpluturi exterioare Betonist 0 8h 100%
umpluturi exterioare
Muncitor
necalificat 0 8h 100%
umpluturi exterioare Plasa sudata 0
1 500
kg
1 500
kg
umputuri interioare + pietris Balastru 0
1 10
mc 1 10 mc
umputuri interioare + pietris Betoniera 0 16h 100%
umputuri interioare + pietris Betonist 0 16h 100%
umputuri interioare + pietris
Muncitor
necalificat 0 16h 100%
montare armaturi in plaxa si grinzi
subsol
Muncitor
necalificat 0 32h 100%
turnare beton in placa si grinzi subsol Balastru 0
1 10
mc 1 10 mc
turnare beton in placa si grinzi subsol Betoniera 0 8h 100%
turnare beton in placa si grinzi subsol Betonist 0 8h 100%
turnare beton in placa si grinzi subsol
Muncitor
necalificat 0 8h 100%


Analiza progresului la mijlocul proiectului
Rezultatele obinute pana acum merg in direcia planificata. Ne pregtim de turnarea subsolului.
Consumarea resurselor sa fcut conform planului.
Analiza finala
Proiectul sa finalizat conform planului. Nu au fost abateri de la buget.

S-ar putea să vă placă și