ID Task Task Name DurationStart Finish Apr 4, '21 May 2, '21 May 30, '21 Jun 27, '21

Apr 4, '21 May 2, '21 May 30, '21 Jun 27, '21 Jul 25, '21 Aug 22, '21 Sep 19, '21 Oct 17, '21
Mode T S W S T M F T S W S T M F T S W S T
1 OBIECTIV:CONSTRUIRE HALA -UNITATE 119 Mon Thu
DE DEPOZITARE,SERVICII SI BIROURI, days 4/19/21 9/30/21
PLATFORME SI DRUMURI DE INCINTA,
DRUM ACCES, POST TRAFO, CABINA
POARTA, BAZIN DE RETENTIE,
IMPREJMUIRE,CASA POMPE, com.
Ghiroda, jud. TIMIS,
2 Executie lucrari de constructii 15 days Mon 4/19/21Fri 5/7/21
3 Procurare materiale si echipamente15 days Mon 4/19/21Fri 5/7/21
4 Fundatii - verficare DE, lansare comanda 15 days Mon Fri 5/7/21
armatura, cofraje, livrare santier
4/19/21
5 Echipamente instalatii - verficare DE, 15 days Mon Fri 5/7/21
lansare comanda, livrare santier
4/19/21
6 Elemente metalice - verficare DE, 15 days Mon Fri 5/7/21
lansare comanda, productie, livrare
4/19/21
santier
7 Executie lucrari filiala 98 days Mon 4/19/21Wed 9/1/21
8 Predare amplasament 1 day Mon 4/19/21Mon 4/19/21
9 Organizare de santier - baraci, bransamente 5 days Mon Fri
provizorii, plaforme depozitare, gard
4/19/21 4/23/21
10 Fundatii hala, zona andocare si cabina poarta
59 days Wed 4/21/21Mon 7/12/21
11 Decopertare generala 5 days Wed 4/21/21Tue 4/27/21
12 Sapaturi 25 days Mon 4/26/21Fri 5/28/21
13 Umpluturi 25 days Mon 5/24/21Fri 6/25/21
14 Beton egalizare fundatii C8/10 12 days Wed 6/23/21Thu 7/8/21
15 Beton fundatii C25/30 10 days Tue 6/29/21Mon 7/12/21
16 Sistem Rutier - Fundatie pardoseala hala 30 days Mon 7/5/21Fri 8/13/21
17 Strat de fundatie din balast 7 days Mon 7/5/21 Tue 7/13/21
18 Strat de fundatie din piatra sparta 7 days Wed 7/14/21Thu 7/22/21
19 Strat de egalizare din nisip 3 days Thu 7/22/21Mon 7/26/21
20 Strat de separatie Hartie Kraft 14 days Tue 7/27/21Fri 8/13/21
21 Strat din beton armat cu fibre din otel 14 days Tue 7/27/21Fri 8/13/21
22 Structura metalica 29 days Fri 7/23/21 Wed 9/1/21
23 Montaj structura metalica contravantuiri 20 days Fri 7/23/21 Thu 8/19/21
24 Montaj structura metalica suprafete vitrate
2 days Tue 8/31/21Wed 9/1/21
25 Montaj structura metalica Billboard h=10m2 days Fri 8/20/21 Mon 8/23/21
26 Montaj structura metalica: Flag poles - 3 days Tue Thu
inaltimea h=8.0m,
8/24/21 8/26/21
27 Montaj structura metalica: Balustrade 3 days Tue Thu
scari interioare si exterioare
8/24/21 8/26/21
28 Montaj structura metalica - Cadre porti 2 days Fri 8/27/21 Mon
sectionale
8/30/21
29 Arhitectura si finisaje 41 days Tue 7/13/21Tue 9/7/21
30 Hidroizolatii fundatii 5 days Tue 7/13/21Mon 7/19/21
31 Panouri sandwich de fatada 18 days Tue 7/20/21Thu 8/12/21
32 Panouri sandwich de compartimentare 6 days Mon 8/16/21Mon 8/23/21

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Project1 Split External Tasks Inactive Summary Manual Summary Progress
Date: Thu 3/25/21 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 1
ID Task Task Name DurationStart Finish Apr 4, '21 May 2, '21 May 30, '21 Jun 27, '21 Jul 25, '21 Aug 22, '21 Sep 19, '21 Oct 17, '21
Mode T S W S T M F T S W S T M F T S W S T
33 Copertina 2x 1.2m -Sticla duplex -securizata 3 days Fri 9/3/21 Tue
2x10 mm grosime, fixata cu spyder de
9/7/21
structura metalica din otel inoxidabil

34 Invelitoare din tablă cutat și termo si 12 days Fri 8/13/21 Mon


hidroizolatii invelitoare,
8/30/21
35 Finisaje interioare 10 days Fri 8/13/21 Thu 8/26/21
36 Tamplarie 10 days Fri 8/13/21 Thu 8/26/21
37 Luminatoare si trape fum 6 days Tue 8/17/21Tue 8/24/21
38 Lucrari diverse 3 days Fri 8/20/21 Tue 8/24/21
39 Sistem anvelopant cladire 10 days Wed 8/25/21Tue 9/7/21
40 Sistem termoizolant acoperis 10 days Wed 8/25/21Tue 9/7/21
41 Sort tabla 6 days Wed 8/25/21Wed 9/1/21
42 Accesorii 6 days Wed 8/25/21Wed 9/1/21
43 Instalatii 88 days Mon 5/3/21Wed 9/1/21
44 Instalatii sanitare 23 days Mon 5/3/21Wed 6/2/21
45 Retea exterioara de alimentare cu apa rece
12 days Mon 5/3/21 Tue 5/18/21
46 Retea exterioara de canalizare menajera 10 days Fri 5/7/21 Thu 5/20/21
47 Retea exterioara de canalizare pluviala 10 days Thu 5/13/21Wed 5/26/21
48 Retele exterioare stingere cu sprinklere 5 days Wed 5/26/21Tue 6/1/21
49 Retea exterioara stingere cu hidranti 5 days Thu 5/27/21Wed 6/2/21
50 Instalatii electrice 71 days Wed 5/26/21Wed 9/1/21
51 Instalatii exterioare 12 days Wed 5/26/21Thu 6/10/21
52 Paratrasnet si priza pamant 2 days Tue 8/31/21Wed 9/1/21
53 Actionare electrica poarta 1 day Fri 6/11/21 Fri 6/11/21
54 Drumuri, sistematizare verticale 71 days Thu 6/24/21Thu 9/30/21
55 Parcare 10 days Wed 8/11/21Tue 8/24/21
56 Fundatie din balast 2 days Wed 8/11/21Thu 8/12/21
57 Strat din beton 4 days Fri 8/13/21 Wed 8/18/21
58 Strat de nisip 4 days Thu 8/19/21Tue 8/24/21
59 Pavaj carosabil 4 days Thu 8/19/21Tue 8/24/21
60 Sistem rutier 71 days Thu 6/24/21Thu 9/30/21
61 Strat de forma din pamant stabilizat 28 days Thu 6/24/21Mon 8/2/21
62 Fundatie din balast 6 days Tue 8/3/21 Tue 8/10/21
63 Fundatie din piatra sparta 6 days Wed 8/11/21Wed 8/18/21
64 Strat de nisip si hartie Kraft 7 days Tue 9/14/21Wed 9/22/21
65 Sistem rutier BCR4.5 11 days Thu 9/16/21Thu 9/30/21
66 Trotuare - PAVAJ DIN DALE PREF. DIN 10 days Tue Mon
BETON DE 6 CM GROSIME
8/17/21 8/30/21
67 Montare borduri pe pat din beton 5 days Tue 8/17/21Mon 8/23/21
68 Fundatie din balast 2 days Tue 8/24/21Wed 8/25/21
69 Strat de nisip 3 days Thu 8/26/21Mon 8/30/21
70 Pavaj h=6 cm 3 days Thu 8/26/21Mon 8/30/21
71 Spatii verzi 29 days Mon 8/23/21Thu 9/30/21

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Project1 Split External Tasks Inactive Summary Manual Summary Progress
Date: Thu 3/25/21 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 2
ID Task Task Name DurationStart Finish Apr 4, '21 May 2, '21 May 30, '21 Jun 27, '21 Jul 25, '21 Aug 22, '21 Sep 19, '21 Oct 17, '21
Mode T S W S T M F T S W S T M F T S W S T
72 Asternere pamant vegetal in strat 15 days Mon Fri
uniform cu grosimea de 20 cm
8/23/21 9/10/21
73 Semanarea gazonului 4 days Wed 9/8/21 Mon 9/13/21
74 Udarea suprafetelor 4 days Wed 9/8/21 Mon 9/13/21
75 Taierea gazonului 2 days Wed 9/29/21Thu 9/30/21

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Project1 Split External Tasks Inactive Summary Manual Summary Progress
Date: Thu 3/25/21 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only