ANEXA nr. 1b la Ordinul nr.

915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause Prevederi/Provisions Clauza 1 Prevederi Generale/ Clause 1 General Provisions Sub-Clauza 1.1 Definiii/ Sub-Clause 1.1 - Definitions Sub-Clauza 1.1.1 Contractul/ Sub-Clause 1.1.1 The Contract - Sub-Clauza 1.1.1.1/ Se terge Sub-Clauza 1.1.1.1 i se nlocuiete cu Sub-Clause 1.1.1.1 urmtoarele: Contract nseamn Acordul Contractual, Scrisoarea de Ofert, Condiiile de Contract, Specificaiile, Planele, Listele i alte documente (dac exist) care sunt incluse n Acordul Contractual./ Sub-Clause 1.1.1.1 shall be deleted and replaced with the followings: Contract means the Contractual Agreement, Letter of Tender, Conditions of Contract, Specifications, Drawings Lists and other documents (if any) which are included in the Contractual Agreement Se terge Sub-Clauza 1.1.1.3./

- Sub-Clauza 1.1.1.3/ Sub-Clause 1.1.1.3

Sub-Clause 1.1.1.3 shall be deleted Sub-Clauza 1.1.3 - Date, teste, perioade i terminare/ Sub-Clause 1.1.3 Dates, tests, periods and completion - Sub-Clauza 1.1.3.5 Se terge Sub-Clauza 1.1.3.5 i se nlocuiete cu Procesul Verbal urmtoarele: de Recepie la Procesul Verbal de Recepie la Terminarea Terminarea Lucrrilor nseamn procesul verbal ntocmit i semnat Lucrrilor/ n conformitate cu Legile n vigoare, de ctre comisia de recepie numit de ctre Beneficiar, la cererea Inginerului, Sub-Clause 1.1.3.5 recomandnd sau nu recepionarea Lucrrilor, a The Minutes of Sectorului sau a unei pri de Lucrare (dup caz) de ctre Reception at Beneficiar, potrivit prevederilor Clauzei 10./ Completion Sub-Clause 1.1.3.5 shall be deleted and replaced with the followings: The Minutes of Reception at Completion is the Minutes elaborated and signed by the Reception Committee appointed by the Beneficiary upon Engineers request, according to the law in force, recommending or not the reception of the works, of the section or part of works (accordingly) by the Beneficiary, as per the provisions of Clause 10 Se terge Sub-Clauza 1.1.3.8 i se nlocuiete cu urmtoarele: Procesul Verbal de Recepie Final nseamn procesul verbal ntocmit i semnat conform Legilor n vigoare de ctre comisia de recepie final numit de ctre Beneficiar, la cererea Inginerului, recomandnd sau nu recepionarea final a Lucrrilor, Sectorului sau a unei

- Sub-Clauza 1.1.3.8 Procesul Verbal de Recepie Final/ Sub-Clause 1.1.3.8 Minutes of Final Reception

p1 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause

Prevederi/Provisions pri de Lucrare (dup caz) de ctre Beneficiar, potrivit prevederilor Sub-Clauzei 11.9./ Sub-Clause 1.1.3.8 shall be deleted and replaced with the followings: The Minutes of Final Reception is the Minutes elaborated and signed by the Final Recption Committee upon Engineers request, according to the law in force, recommending or not the final reception of the Works (accordingly)by the Beneficiary, as per the provisions of the Sub-Clause 11.9. Se adaug o nou Sub-Clauz 1.1.3.10: Certificatul de Recepie la Terminarea Lucrrilor nseamn certificatul emis de Inginer preciznd data la care lucrrile sau Sectoarele au fost terminate n conformitate cu prevederile contractului, cu excepia unor lucrri minore rmase neexecutate i a defeciunilor care nu vor afecta semnificativ utilizarea Lucrrilor sau a Sectoarelor n scopul destinat (pn cnd sau n timp ce aceste lucrri sunt finalizate i defeciunile sunt remediate) / A new Sub-Clause 1.1.3.10 shall be added: Taking Over Certificate at Completion is the Certificate issued by the Engineer, stipulating the date when the Works or Section of Works have been completed according to the Contract, except some minor works which were unfinished and the defects which would not significantly affect the utilisation of the works or Sections of works for the intended purpose (until or while these works would be finished and the defects would be remediated) Se adaug o nou Sub-Clauz 1.1.3.11: Certificatul de Recepie Final nseamn certificatul emis de Inginer care precizeaz data la care Antreprenorul i-a ncheiat obligaiile prevzute n contract / A new Sub-Clause 1.1.3.11 shall be added:

- Sub-Clauza 1.1.3.10 Certificatul de Recepie la Terminarea Lucrrilor/ Sub-Clause1.1.3.10Taking Over Certificate at completion

- Sub-Clauza 1.1.3.11 Certificatul de Recepie Final/ Sub-Clause 1.1.3.11 The Final Reception Certificate (Performance Certificate)

The Final Reception Certificate (Performance Certificate) is the Certificate issued by the Engineer, which states the date when the Contractor has fulfilled his obligations provided in the Contract. Sub-Clauza 1.5 Prioritatea documentelor/ Sub-Clause 1.5 Priority of the documents Se terge SubClauza 1.5 i se nlocuiete cu urmtoarele: Documentele care alctuiesc Contractul trebuie considerate ca documente care se expliciteaz reciproc. n scopul interpretrii, prioritatea documentelor va fi n conformitate cu urmtoarea ordine: (a) Acordul Contractual, (b) Scrisoarea de Ofert,

p2 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause

Prevederi/Provisions (c) Condiiile Speciale, (d) aceste Condiii Generale, (e) Specificaiile, (f) Planele, (g) Listele, i (h) orice alte documente care fac parte din Contract. Actele adiionale i protocoalele vor avea prioritatea documentelor pe care le modific. n caz de ambiguitate sau discrepane ale documentelor, Inginerul are autoritatea de a emite dispoziiile pe care le consider necesare pentru rezolvarea ambiguitii sau discrepanelor. n cazul n care, pe parcursul ndeplinirii contractului, se constat faptul c anumite elemente ale ofertei tehnice sunt inferioare sau nu corespund cerinelor prevzute n caietul de sarcini, prevaleaz prevederile caietului de sarcini. SubClause 1.5 shall be deleted and replaced with the following:The documents which constitute the Contract must be considered as documents which explain each other. For interpretation purposes, the priority of the documents shall be as following: (a) Contractual Agreement, (b) Letter of the Offer, (c) Special Conditions, (d) the present General Conditions, (e) Specifications, (f) Drawings, (g) Lists, and (h) any other documents which are part of the Contract. The Addenda and the protocols shall have the precedency order of the documents they are amending. In case of ambiguity or discrepancies of documents, the Engineer has the authority of issuing the dispositions that he considers to be necessary in order to solve the ambiguities and discrepancies.

In case that, during the carrying out of the contract, it is found that certain elements of the technical offer are inferior or do not comply with the requirements of the Tender Documents, the provisions of the Tender Documents shall prevail. Sub-Clauza 1.6 Acordul contractual/ Sub-Clause 1.6 The Contract Agreement Se terge prima fraz a Sub-Clauzei 1.6. The first sentence of the Sub-Clause 1.6 shall be deleted.

p3 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause Prevederi/Provisions Clauza 3 Inginerul/ Clause 3 The Engineer Sub-Clauza 3.1 Responsabilitile i autoritatea Inginerului/ Sub-Clause 3.1 Engineers Authority and Responsibilities La sfritul Sub-Clauzei 3.1 se adaug urmtoarele: nainte de a aciona potrivit prevederilor urmtoarelor Sub-Clauze ale prezentelor Condiii, Inginerul va obine de la Beneficiar aprobrile specifice: a. Sub-Clauza 10.1: aprobarea expres a Beneficiarului este necesar nainte de emiterea Certificatului de Recepie la Terminarea lucrrilor; b. Sub-Clauza 11.9: aprobarea expres a Beneficiarului este necesar nainte de emiterea Certificatului de Recepie Final; c. Sub-Clauza 13.1: aprobarea expres a Beneficiarului este necesar nainte de dispunerea sau aprobarea oricrei Modificri care ar face ca Preul Contractului s depeasc Valoarea de Contract Acceptat sau orice valoare de contract convenit ulterior de Beneficiar i Antreprenor n cadrul unor acte adiionale la Contract. At the end of Sub-Clause 3.1 the following shall be added:Before acting according to the provisions of the following Sub-Clauses of the present Conditions, the Engineer shall obtain the specific approvals from the Beneficiary: a. Sub-Clause 10.1: the Beneficiarys special approval is necessary before the issuance of the Taking Over Certificate at completion; b. Sub-Clause 11.9: the Beneficiarys special approval is necessary before the issuance of the Final Reception Certificate (Performance Certificate); c. Sub-Clause 13.1: the Beneficiarys special approval is necessary before any disposition or approval of a modification which would lead to an increase in the Contract Price beyond the Accepted Value of the Contract or any Contract value subsequently agreed by the Beneficiary and the Contractor through Addenda to the Contract.. Clauza 4 Antreprenorul/ Clause 4 The Contractor Sub-Clauza 4.2 Garania de Bun Execuie Sub-Clause 4.2 The Performance Guarantee Se terge prima propoziie a paragrafului secund al SubClauzei 4.2 i se nlocuiete cu urmtoarele: Antreprenorul va furniza Beneficiarului Garania de Bun Execuie n termen de 15 zile de la data semnrii Acordului Contractual i va trimite o copie a acesteia i Inginerului. n cea de-a doua propoziie a celui de-al treilea paragraf al acestei Sub-Clauze 4.2 se terg cuvintele Procesul

p4 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause

Prevederi/Provisions Verbal de Recepie Final i se nlocuiesc cu Certificatul de Recepie Final Se terge ultimul paragraf al Sub-Clauzei 4.2 i de nlocuiete cu urmtoarele: Beneficiarul va elibera / restitui Antreprenorului Garania de Bun Execuie dup cum urmeaz: i. 70% din valoarea Garaniei de Buna Execuie n termen de 14 zile de la data ntocmirii Procesului Verbal de Recepie la Terminarea Lucrrilor, dac Beneficiarul nu a formulat pn la acea dat nicio reclamaie de executare a Garaniei de Bun Execuie i cu condiia emiterii Certificatului de Recepie la Terminarea Lucrrilor; ii. 30% din valoarea Garaniei de Bun Execuie la emiterea Certificatului de Recepie Final, dac Beneficiarul nu a formulat pn la acea dat nicio reclamaie de executare a Garaniei de Bun Execuie./ The first sentence from the second paragraph of the SubClause 4.2 shall be deleted and shall be replaced with the followings: The Contractor shall submit the Performance Guarantee to the Beneficiary within 15 days from the signing date of the Contract Agreement, and shall send a copy of it to the Engineer as well. In the second sentence of the third paragraph of the present Sub-Clause 4.2 the words Minutes of Final Reception shall be deleted and replaced with Final Reception Certificate (Performance Certificate???). The last paragraph of the Sub-Clause 4.2 shall be deleted and shall be replaced with the followings:

The Beneficiary shall release the Performance Bond as following: i. 70% of the value of the Performance Bond within 14 days from the date of elaboration of the Minutes of Receipt at completion of works if the Beneficiary has not issued any claim of execution for the Performance Bond by that date and provided that the Taking Over Certificate at Completion has been issued; ii. 30% of the Performance Bond upon the issuance of the Final Reception Certificate (Performance Certificate) if the Beneficiary has not issued any claim of execution for the Performance Bond by that date. Sub-Clauza 4.4 Subantreprenorii Sub-Clause 4.4 - Subcontractors Dup primul paragraf al Sub-Clauzei 4.4 se adaug urmtoarele paragrafe: n cazul n care pri din Lucrri urmeaz s se ndeplineasc de unul sau mai muli Subantreprenori, la semnarea Acordului Contractual, Antreprenorul va furniza

p5 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause

Prevederi/Provisions Beneficiarului contractele ncheiate de Antreprenor cu Subantreprenorii nominalizai n Ofert. Acesta contracte vor ndeplini condiiile din Ofert i vor constitui Liste la Contract. Antreprenorul nu va avea dreptul de a nlocui pe nici unul din Subantreprenorii nominalizai n Ofert fr acceptul prealabil al Inginerului.

After the first paragraph of the Sub-Clause 4.4 the following paragraphs shall be added:In case that parts of the works are to be executed by one or several subcontractors, upon the signature of the Contract Agreement the Contractor shall submit to the Beneficiary the contracts concluded between the Contractor and the Sub-contractors. These contracts shall comply with the offer and shall be considered Lists to the Contract. The Contractor shall not be entitled to replace any of his nominated subcontractors without the prior approval of the Engineer. Sub-Clauza 4.21 Rapoarte privind evoluia execuiei lucrrilor Sub-Clause 4.21 Progress Reports n cel de-al doilea paragraf al acestei Sub-Clauze 4.21 se terg cuvintele Procesul Vebal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificatul de Recepie la Terminarea Lucrrilor. In the second paragraph of this Sub-Clause 4.21 the words Minutes of Reception at Completion shall be deleted and shall be replaced by Taking Over Certificate at Completion. Sub-clauza 4.23 Activitile Antreprenorului pe antier Sub-Clause 4.23 Contractors activities on site n prima fraz al celui de-al treilea paragraf al acestei SubClauze 4.23 se terg cuvintele Procesului Verbal de Recepie la Terminarea Lucrrilor i Procesul Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificatului de Recepie la Terminarea Lucrrilor respectiv Certificatul de Recepie la Terminarea Lucrrilor/ In the first sentence of the third paragraph of this SubClause 4.23 the words Minutes of Reception at Completion and Minutes of Reception at Completion shall be deleted and replaced byTaking Over Certificate atCompletion and respectively Taking Over Certificate at Completion. Clauza 6 Personalul i Fora de Munc/ Clause 6 Staff and Labour Sub-Clauza 6.10 Raportri privind Personalul i Utilajele Antreprenorului/ Sub-Clause 6.10 Reporting on Contractors Staff and Equipment n ultima propoziie din aceast Sub-clauz 6.10 se terg cuvintele Procesul Verbal de Recepie la Terminarea

p6 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause

Prevederi/Provisions Lucrrilor i se nlocuiesc cu Certificatul de Recepie la Terminarea Lucrrilor.

In the last sentence of this Sub-Clause 6.10 the words Minutes of Reception at Completion shall be deleted and shall be replaced by Taking Over Certificate at Completion. Clauza 8 nceperea, ntrzierea i suspendarea Lucrrilor Clause 8 Start delay and suspension of Works Sub-Clauza 8.1 nceperea Lucrrilor Sub-Clause 8.1 Start of the Works n a doua propoziie a primului paragraf al Sub-Clauzei 8.1 se terg cuvintele Scrisoare de Acceptare i se nlocuiesc cu Acord Contractual. In the second sentence of the first paragraph of SubClause 8.1 the words Letter of acceptance shall be deleted and replaced by Contract Agreement. Sub-Clauza 8.7 Penaliti de ntrziere Sub-Clause 8.7 Delays penalties n prima propoziie din aceast Sub-Clauz 8.7 se terg cuvintele Procesul Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificatul de Recepie la Terminarea Lucrrilor. In the first sentence of this Sub-Clause 8.7 the words Minutes of Reception at Completion shall be deleted and shall be replaced by Taking Over Certificate at Completion. Clauza 9 Testele la Terminare Clause 9 Tests upon Completion Sub-Clauza 9.4 Rezultate Necorespunztoare ale Testelor la Terminare Sub-Clause 9.4 Failure of Tests upon Completion n subparagraful (c) din primul paragraf al acestei SubClauze 9.4 se terg cuvintele Proces Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificat de Recepie la Terminarea Lucrrilor n al doilea paragraf al acestei Sub-Clauze 9.4 se terg cuvintele Procesului Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificatului de Recepie la Terminarea Lucrrilor. In sub-paragraph (c) from the first paragraph of this SubClause 9.4 the words Minutes of Reception at Completion shall be deleted and shall be replaced by Taking Over Certificate at completion. In the second paragraph of this Sub-Clause 9.4 the words of the Minutes of Reception at Completion shall be deleted and shall be replaced by of the Taking Over Certificate at Completion. Clauza 10 Recepia Lucrrilor de ctre Beneficiar/ Clause 10 Taking Over by the Beneficiary Sub-Clauza 10.1 - Recepia Lucrrilor i a Sectoarelor

p7 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause Prevederi/Provisions Sub-Clause 10.1 Taking Over of the Works and Sections of Works Se terge Sub-clauza 10.1 i se nlocuiete cu urmtoarele: Cu excepia celor prevzute n Sub-Clauza 9.4 [Rezultate Necorespunztoare ale Testelor la Terminare], Beneficiarul va recepiona Lucrrile n situaia n care (i) acestea au fost terminate n conformitate cu prevederile Contractului, incluznd condiionrile descrise n Sub-Clauza 8.2 [Durata de Execuie], (ii) atunci cnd a fost emis un Proces Verbal de Recepie la Terminarea Lucrrilor prin care se recomand admiterea recepiei i (iii) Inginerul a emis un Certificat de Recepie la Terminarea Lucrrilor. Dac Beneficiarul nu i ndeplinete obligaiile privind organizarea recepiei i transmiterea deciziei sale privind admiterea cu sau fr obiecii, amnarea sau respingerea recepiei, lucrrile se vor considera recepionate n condiiile legii. Antreprenorul poate solicita Inginerului emiterea Certificatului de Recepie la Terminarea Lucrrilor cu cel puin 14 zile nainte ca Lucrrile, din punct de vedere al Antreprenorului, s fie terminate i pregtite de recepie. Dac Lucrrile sunt mprite pe Sectoare, Antreprenorul poate solicita emiterea Certificatelor de Recepie la Terminare pentru fiecare Sector n parte. Inginerul va solicita Beneficiarului nominalizarea unei comisii de recepie a Lucrrilor care, la terminarea Lucrrilor, va ntocmi i semna Procesul Verbal de Recepie la Terminarea Lucrrilor n conformitate cu Legile n vigoare Sub rezerva primirii deciziei Beneficiarului bazat pe recomandrile cuprinse n Procesul Verbal de Recepie la Terminarea Lucrrilor, n termen de 56 de zile de la data primirii solicitrii din partea Antreprenorului, Inginerul: (a) Va emite ctre Antreprenor Certificatul de Recepie la Terminarea Lucrrilor; sau (b) Va respinge solicitarea, prezentnd motivaia i specificnd lucrrile pe care s le realizeze Antreprenorul pentru a face posibil admiterea recepiei. Antreprenorul va finaliza lucrrile, nainte de a transmite o nou ntiinare potrivit prevederilor acestei Sub-Clauze. The Sub-Clause 10.1 shall be deleted and replaced by the following:Except the provisions of Sub-Clause 9.4 [Failure of Tests at Completion], the Beneficiary shall take over the works if: (i) The works have been completed according to the provisions of the Contract, including the conditionalities described in Sub-Clause 8.2 [Execution Period], (ii) The Minutes of Reception upon completion of

p8 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause

Prevederi/Provisions works has been issued, recommending the acceptance of the Taking Over and (iii) The Engineer has issued a Taking Over Certificate at Completion. If the Beneficiary does not fulfil their obligations with regards to organising the taking over and notifying their decision regarding acceptance of the taking over with or without objections, rejection or postponement of the taking over, the works shall be considered taken over under the law..

The Contractor can request the issuance of the Taking Over Certificate by the Engineer with at least 14 days prior to the completion of the works, from the Contractors point of view, and preparation of the works for the taking over. If the Works are subdivided per sections, the Contractor can request the issuance of the Taking Over Certificate for each section. The Engineer shall request the Beneficiary to appoint a Reception Committee for the works, which, upon completion of works, shall elaborate and sign the Minutes of Reception at Completion according to the law in force. Subject to receiving the Beneficiarys decision based on the recommendations included in the Minutes of Reception at Completion, within 56 days from the date of the Contractors application, the Engineer shall: (a) issue the Taking Over Certificate at Completion to the Contractor, or (b) reject the application, stating the reasons for it and the works which need to be executed by the Contractor in order for the Taking Over to be accepted. The Contractor shall complete the works before submitting another application, according to the provisions of this Sub-Clause. Sub-Clauza 10.2 Recepia unor pri ale Lucrrilor Sub-Clause 10.2 Taking Over of Parts of the Works Se terge primul paragraf al Sub-Clauzei 10.2 i se nlocuiete cu urmtoarele: Inginerul poate, la latitudinea exclusiv a Beneficiarului, emite un Certificat de Recepie la Terminarea Lucrrilor pentru orice parte a Lucrrilor Permanente, cu condiia ca acea parte s fie independent din punct de vedere fizic i funcional. Se terge paragraful secund al Sub-Clauzei 10.2 i se nlocuiete cu urmtoarele: Beneficiarul nu va putea folosi nicio parte a Lucrrilor (altfel dect ca msur temporar care fie este specificat n Contract, fie este convenit de ambele Pri), pn cnd Inginerul emite un Certificat de Recepie la Terminarea Lucrrilor pentru aceast parte. Dac Beneficiarul folosete totui orice parte a Lucrrilor nainte de emiterea Certificatului de Recepie la Terminarea Lucrrilor, Antreprenorul va nceta s mai aib

p9 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause

Prevederi/Provisions responsabilitatea ngrijirii acelei pri ncepnd cu aceast dat, moment n care rspunderea va trece n sarcina Beneficiarului.

The first paragraph of the Sub-Clause 10.2 shall be deleted and replaced with the following: Upon the Beneficiarys sole decision, the Engineer may issue a Taking Over Certificate for any Parts of the Permanent Works, provided that part is physically and functionally independent. The second paragraph of Sub-Clause 10.2 shall be deleted and replaced by the followings: The Beneficiary shall not be authorised to use any part of the Works (other than as a temporary measure which is either specified in the Contract or agreed by both parties), until the Engineer would issue a Taking Over Certificate at Completion for that part. If the Beneficiary yet uses any part of the works before the issuance of the Taking Over Certificate at Completion, the Contractors responsibility for taking care of that particular part of the works shall stop at that date, from there onwards being the Responsibility of the Beneficiary. Sub-Clauza 10.3 Recepia i Testele la Terminarea Lucrrilor/ Sub-Clause 10.3 Taking Over and tests at completion Se terge primul paragraf al acestei Sub-Clauze 10.3 i se nlocuiete cu urmtoarele: Dac Antreprenorul este mpiedicat cu mai mult de 14 zile s efectueze Testele la Terminare datorit unei cauze din responsabilitatea Beneficiarului, Antreprenorul va notifica Inginerul cu privire la acest aspect. ntiinarea va include detalii care s specifice motivul pentru care Testele la Terminare nu au putut fi efectuate precum i detalii referitoare la natura i durata ntrzierilor sau ntreruperilor care pot apare din aceast cauz. Se terge al doilea paragraf al acestei Sub-Clauze 10.3. The first paragraph of this Sub-Clause 10.3 shall be deleted and replaced by the following:If the Contractor is prevented from performing the Tests at completion with more than 14 days for reasons which are the Beneficiarys responsibility, the Contractor shall notify the Engineer regarding this aspect. The notification shall include details which should specify the reason for which the Tests at completion could not be performed as well as details referring to the nature and duration of the delays or interruptions which may incur due to that reason. The second paragraph of this Sub-Clause 10.3 shall be deleted. Sub-Clauza 10.4 Restabilirea Suprafeelor de Teren/ Sub-Clause 10.4 Reinstatement of the land surfaces n aceast Sub-Clauz 10.4 se terg cuvintele Procesului

p10 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause

Prevederi/Provisions Verbal de Recepie la Terminarea Lucrrilor i proces verbal i se nlocuiesc cu Certificatului de Recepie la Terminarea Lucrrilor respectiv certificat.

In this Sub-Clause 10.4 the words Minutes of Reception at Completion and minutes shall be deleted and shall be replaced by Taking Over Certificate at Completion and Certificate respectively. Clauza 11 Perioada de garanie/ Clause 11 Defects Liability Sub-Clauza 11.1 Terminarea lucrrilor neexecutate i remedierea defeciunilor / Sub-Clause 11.1 Completion of unexecuted works and defects remediation n sub-paragraful (a) al acestei Sub-Clauze 11.1 se terg cuvintele Procesului Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificatului de Recepie la Terminarea Lucrrilor Se terge sub-paragraful (b) al Sub-Clauzei 11.1 i se nlocuiete cu urmtorul sub-paragraf: (b) va executa toate lucrrile necesare pentru remedierea defeciunilor, fie ele aparente sau ascunse, sau degradrilor, conform solicitrilor Beneficiarului (sau n numele acestuia), pn la sau nainte de data de expirare a Perioadei de Notificare a Defeciunilor pentru Lucrri sau Sectoare de Lucrri (dup caz). In sub-paragraph (a) of this Sub-Clause 11.1 4 the words Minutes of Reception at Completion shall be deleted and shall be replaced by Taking Over Certificate at Completion. Sub-paragraph (b) of Sub-Clause 11.1 shall bedeleted and replaced by the following sub-paragraph: (b) shall execute all the necessary works for remediation of the defects, may those be hidden or visible, or of the damages, according to the Beneficiarys request (or in the Beneficiarys name), up to or before the expiry date of the DNP for works or sections of works (accordingly).. Sub-Clauza 11.7 Dreptul de Acces/ Sub-Clause 11.7 Right of access n aceast Sub-Clauz 11.7 se terg cuvintele Procesului Verbal de Recepie Final i se nlocuiesc cu Certificatului de Recepie Final. In this Sub-Clause 11.7 the words Minutes of Final Reception shall be deleted and shall be replaced by Final Reception Certificate (Performance Certificate). Sub-Clauza 11.9 Procesul Verbal de Recepie Final Sub-Clause 11.9 Minutes of Final Reception Se terge aceast Sub-Clauz 11.9 i se nlocuiete cu o nou Sub-Clauz Certificatul de recepie final avnd urmtorul coninut: ndeplinirea obligaiilor Antreprenorului nu se consider a fi ncheiat pn cnd Inginerul nu a emis Antreprenorului

p11 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause

Prevederi/Provisions Certificatul de Recepie Final, preciznd data la care Antreprenorul i-a ncheiat obligaiile prevzute n Contract. Sub rezerva primirii deciziei Beneficiarului bazat pe recomandrile fcute n Procesul Verbal de Recepie Final, Inginerul va emite Certificatul de Recepie Final n termen de 28 zile de la expirarea celei din urm Perioade de Notificare a Defectelor, sau ct mai repede dup acest termen cu condiia ca Antreprenorul s fi furnizat toate Documentele Antreprenorului i s fi terminat i testat toate Lucrrile, inclusiv remedierea oricror defecte. O copie a Certificatului de Recepie Final va fi trimis Beneficiarului. Certificatul de Recepie Final va fi singurul document considerat a certifica recepia Lucrrilor. This Sub-Clause 11.9 shall be deleted and replaced by a new Sub-Clause Final Reception Certificate (Performance Certificate), having the following content: The fulfilment of the Contractors obligations shall not be considered completed until the Engineer has issued to the Contractor the Final Reception Certificate, stating the date when the Contractor has completed his contractual obligations. Subject to receiving the Beneficiarys decision based on the recommendations from the Minutes of Final Reception, the Engineer shall issue the Final Reception Certificate (Performance Certificate) within 28 days from the expiry of the last DNP or as soon as possible after this date, provided that the Contractor has submitted all the Contractors documents and has completed and tested all the Works, included all the remediations. A copy of the Final Reception Certificate (Performance Certificate) shall be sent to the Beneficiary.

The Final Reception Certificate shall be the only document considered to certify the reception of the works Sub-Clauza 11.10 Obligaii nendeplinite/ Sub-Clause 11.10 Unfulfilled obligations n aceast Sub-Clauz 11.10 se terg cuvintele Procesului Verbal de Recepie Final i se nlocuiesc cu Certificatului de Recepie Final Se adaug un nou paragraf: Emiterea Certificatului de Bun Execuie de ctre Inginer nu va aduce atingere rspunderii Antreprenorului pentru viciile ascunse ale Lucrrilor pe durata termenelor de garanie impuse de Legile n vigoare./ In this Sub-Clause 11.10 the words Minutes of Final Reception shall be deleted and shall be replaced by Final Reception Certificate (Performance Certificate). A new paragraph shall be added: The issuance of the Final Reception Certificate

p12 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause

Prevederi/Provisions (Performance Certificate) by the Engineer shall not reflect on the Contractors responsibility for the hidden flaws of the works during the warranty periods imposed by the law in force. Sub-Clauza 11.11 Eliberarea antierului/ Sub-Clause 11.11 -Clearance of Site n primul paragraf al acestei Sub-Clauze 11.1e se terg cuvintele Procesului Verbal de Recepie Final i se nlocuiesc cu Certificatului de Recepie Final n al doilea paragraf al acestei Sub-Clauze 11.1e se terg cuvintele Procesului Verbal de Recepie Final i se nlocuiesc cu Certificatului de Recepie Final. In the first paragraph of this Sub-Clause 11.1e the words of the Minutes of Final Reception shall be deleted and shall be replaced by of the Final Reception Certificate (Performance Certificate). In the second paragraph of this Sub-Clause 11.1e the words of the Minutes of Final Reception shall be deleted and shall be replaced by of the Final Reception Certificate (Performance Certificate). Clauza 13 Modificri i actualizri Clause 13 Modifications and adjustments Sub-Clauza 13.1 Dreptul de a Modifica/ Sub-Clause 13.1 Right to vary n primul paragraf al acestei Sub-Clauze 13.1 se terg cuvintele Procesului Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificatului de Recepie la Terminarea Lucrrilor. In the first paragraph of this Sub-Clause 13.1 the words of the Minutes of Reception at Completion shall be deleted and replaced by of the Taking Over Certificate at Completion. Sub-Clauza 13.5 Sume provizionate/ Sub-Clause 13.5 Provisional sums La sfritul Sub-Clauzei 13.5 se adaug urmtoarele: Atunci cnd achiziioneaz Echipamente, Materiale sau servicii conform prevederilor paragrafului (b), n alt mod dect de la un Subantreprenor nominalizat (dup cum este definit n Clauza 5 [Subantreprenori nominalizai]) Antreprenorul va respecta regulile de achiziii publice potrivit prevederilor Legilor n vigoare. At the end of Sub-Clause 13.5 the following shall be added: When purchasing equipment, materials or services according to paragraph (b), in any other way than from a nominated sub-contractor (as defined in Clause 5 Nominated subcontractors), the Contractor shall comply with the public acquisitions regulations according to the law in force. Clauza 14 Preul Contractului i plile/ Clause 14 Contract Price and payments

p13 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause Prevederi/Provisions Sub-Clauza 14.1 Preul Contractului/ Sub-Clause 14.1 Contract Price La sfritul Sub-Clauzei 14.1 se adaug urmtoarele: Inginerul va ntiina Beneficiarul si Antreprenorul ori de cte ori ia cunotin de faptul c Preul Contractului depete Valoarea de Contract Acceptat sau orice valoare de contract convenit ulterior de Beneficiar i Antreprenor n cadrul unor acte adiionale la Contract. At the end of Sub-Clause 14.1 the followings shall be added: The Engineer shall inform the Beneficiary and the Contractor every time he acknowledges the fact that the Contract Price exceeds the Contract accepted value or any other Contract value subsequently agreed by the Beneficiary and the Contractor through addenda to the Contract. Sub-Clauza 14.2 Plata n avans/ Sub-Clause 14.2 Advance Payments Se terge Sub-Clauza 14.2 i se nlocuiete cu urmtoarele: Beneficiarul va efectua pli n avans, fr dobnd, n vederea executrii Lucrrilor, dup ce Antreprenorul va transmite garanii n conformitate cu prevederile prezentei Sub-Clauze. Valoarea total a fiecrei pli n avans, numrul i data tranelor (dac sunt mai multe dect una) i monedele de plat i proporiile acestora, vor fi cele specificate n Anexa la Ofert. Pn cnd Beneficiarul primete, dac primete, garaniile adecvate, sau dac valoarea total a fiecrei pli n avans nu este specificat n Anexa la Ofert, prevederile prezentei Sub-Clauze nu se vor aplica. Inginerul va emite un Certificat Interimar de Plat pentru prima tran a fiecrei pli n avans dup primirea unei Situaii de Lucrri (potrivit prevederilor Sub-Clauzei 14.3 [Prezentarea Situaiilor Interimare de Lucrri]) i dup primirea de ctre Beneficiar (i) a Garaniei de Bun Execuie n conformitate cu prevederile Sub-Clauzei 4.2 [Garania de Bun Execuie] i (ii) a unei garanii n cuantumul i n moneda stabilite pentru plata n avans. Aceast garanie va fi emis de o banc i dintr-o ar (sau alt jurisdicie) aprobate de ctre Beneficiar, i va avea forma anexat Condiiilor Speciale sau alt form aprobat de ctre Beneficiar. Antreprenorul se va asigura c fiecare garanie va rmne valabil i n vigoare pn la returnarea avansului, dar valoarea garaniei poate fi redus n mod progresiv cu sumele rambursate de ctre Antreprenor, aa cum acestea sunt indicate n Certificatele de Plat. Dac termenii unei garanii specific data de expirare a acesteia, iar plata n avans nu a fost rambursat cu 28 de zile nainte de data expirrii garaniei, Antreprenorul va

p14 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause

Prevederi/Provisions prelungi valabilitatea garaniei pn la returnarea integral a plii n avans. Fiecare plat n avans va fi rambursat prin deduceri din Certificatele de Plat pn la sfritul anului respectiv. Valoarea deducerilor va fi anunat periodic Inginerului de ctre Antreprenor, cu condiia ca fiecare plat n avans s fie integral rambursat pn la sfritul anului n curs. Dac o plat n avans nu este rambursat pn la sfritul anului respectiv, diferena rmas nerambursat va deveni imediat datorat i pltibil de ctre Antreprenor Beneficiarului. Beneficiarul va avea dreptul s aplice penaliti la diferena nerambursat la nivelul penalitilor prevzute pentru datoriile bugetare n conformitate cu Legile n vigoare, i calculate pentru perioada cuprins ntre primirea i returnarea plii n avans de ctre Antreprenor. Dac plata n avans nu a fost rambursat nainte de emiterea Certificatului de Recepie la Terminarea Lucrrilor sau nainte de reziliere potrivit prevederilor Clauzei 15 [Rezilierea Contractului de ctre Beneficiar], Clauzei 16 [Suspendarea i rezilierea Contractului de ctre Antreprenor] sau Clauzei 19 [Fora Major] (dup caz), diferena rmas nerambursat va deveni imediat datorat i pltibil de ctre Antreprenor Beneficiarului./ Sub-Clause 14.2 shall be deleted and replaced by the followings: The Beneficiary shall make advance payments without interest, towards the execution of the Works, after the Contractor shall submit guarantees in accordance with the provisions of the present Sub-Clause. The total value of each advance payment, the number and the dates of the instalments (if more than one) and the currencies and their proportions shall be as specified in the Annex to Tender. The provisions of the present Sub-Clause shall not apply before the Beneficiary receives the adequate guarantees or if the total value of each advance payment is not specified in the Annex to Tender. The Engineer shall issue an IPC for the first instalment of each advance payment after receiving an Application for IPC (according to the provisions of Sub-Clause 14.3 [Submittal of Applications for IPC) and after the Beneficiary has received

(i)

the Performance Guarantee according to the provisions of Sub-Clause 4.2 [Performance Guarantee] and an advance guarantee in the established amount and currency for the advance payment.This guarantee shall be issued by a bank and from a country (or any other

(ii)

p15 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause

Prevederi/Provisions jurisdiction) approved by the Beneficiary, and shall be in the form as annexed to the Special Conditions or any other form agreed by the Beneficiary. The Contractor shall ensure that every guarantee remains valid and in force until the repayment of the advance, but the value of the guarantee shall be progressively reduced by the amounts already repaid by the Contractor, as indicated in the IPC-s. If the terms of a guarantee specifies its expiry date and the advance payment has not been repaid 28 days before the guarantees expiry date, the Contractor shall extend the validity of the guarantee until the complete repayment of the advance payment. Each advance payment shall be repaid by deductions from the IPC-s up to the end of the respective year. The value of the deductions shall be periodically notified to the Engineer by the Contractor, provided that each advance payment is completely repaid up to the end of the current year. If one of the advance payments is not reimbursed until the end of the respective year, the balance to be reimbursed shall become immediately due and payable by the Contractor to the Beneficiary. The Beneficiary shall have the right to apply penalties to the non-reimbursed balance at the level of the penalties provided for budgetary debts according to the law in force and calculated for the period between the receipt date and the repayment date of the advance payment by the Contractor.

If the advance payment has not been reimbursed before the issuance of the Taking Over Certificate at Completion or before Termination according to Clause 15 [Termination of the Contract by the Beneficiary], Clause 16 [Suspension and Termination of the Contract by the Contractor] or Clause 19 [Force Majeure] (accordingly), the nonreimbursed balance shall become immediately due and payable by the Contractor to the Beneficiary. Sub-Clauza 14.4 Graficul de Pli Sub-Clause 14.4 Payment Schedule n ultima propoziie a celui de-al doilea paragraf al acestei Sub-Clauze 14.4 se terg cuvintele Procesului Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificatului de Recepie la Terminarea Lucrrilor/ In the last sentence of the second paragraph of this SubClause 14.4 the words Minutes of Reception at Completion shall be deleted and shall be replaced by Taking Over Certificate at Completion. Sub-Clauza 14.5 Echipamente i materiale destinate Lucrrilor/ Sub-Clause 14.5 Plant and Materials intended for Works Se terge al treilea paragraf al Sub-Clauzei 14.5 i se nlocuiete cu urmtoarele:

p16 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause

Prevederi/Provisions Inginerul va stabili i va aproba adugarea sumelor n Certificatele Interimare de Plat dac sunt ndeplinite urmtoarele condiii: (a) Antreprenorul: (i) a pstrat nregistrri satisfctoare (inclusiv notele de comand, chitanele, Costurile i folosirea Echipamentelor i Materialelor), iar aceste nregistrri sunt disponibile pentru verificare, i (ii) a transmis o situaie pentru Costurile de achiziionare i livrare a Echipamentelor i Materialelor pe antier, nsoit de documente justificative; i, de asemenea: (b) Echipamentele i Materialele respective: (i) sunt cele cuprinse n lista din Anexa la Ofert pentru plata la expedierea spre antier, i (ii) au fost livrate i depozitate corespunztor pe antier, sunt protejate mpotriva oricror pierderi, daune sau deteriorri i par a fi n conformitate cu prevederile Contractului./

The third paragraph of Sub-Clause 14.5 shall be deleted and replaced with the following:The Engineer shall establish and approve the adding of the amounts into the IPC-s provided that the following conditions are fulfilled: (a) The Contractor: (i) has maintained the records satisfactorily (including the orders, receipts, costs and use of the Plant and Materials) and these records are available for checking, and (ii) has submitted a record (breakdown) of costs for purchase and delivery of Plant and Materials on Site, accompanied by supporting documents; and also: (b) the respective Plant and Materials: (i) are the ones included in the list from the Annex to Tender for payment upon delivery on site, and (ii) have been delivered and stored on site accordingly, are protected against any loss, damage or deterioration and appear to be in compliance with the provisions of the Contract. Sub-Clauza 14.6 Emiterea Certificatelor de Plat Interimare/ Sub-Clause 14.6 Issue of IPC-s n cel de-al doilea paragraf al acestei Sub-Clauze 14.6 se terg cuvintele Procesului Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificatului de Recepie la Terminarea Lucrrilor. In the second paragraph of this Sub-Clause 14.6 the words Minutes of Reception at Completion shall be deleted and shall be replaced by Taking Over Certificate at Completion. Sub-Clauza 14.6 Emiterea Certificatelor Interimare de Plat / Sub-Clause 14.6 Issue of IPC-s

p17 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause

Prevederi/Provisions La sfritul Sub-Clauzei 14.6 se adaug un nou paragraf: Fr a lua n considerare prevederile Sub-Clauzei 2.5 [Revendicrile Beneficiarului], Beneficiarul este ndreptit s corecteze erorile aritmetice din orice Certificat de Plat. Se adaug un nou paragraf la sfritul Sub-Clauzei 14.6: Fr a prejudicia niciun alt drept al Antreprenorului ce decurge din Contract sau n alt mod, Inginerul nu poate emite un Certificat Interimar de Plat ce ar face ca valoarea cumulat aprobat pentru plat s depeasc Valoarea de Contract Acceptat sau orice valoare de contract convenit ulterior de Beneficiar i Antreprenor n cadrul unor acte adiionale la Contract./ At the end of Sub-Clause 14.6 a new paragraph shall be added:Without considering the provisions of the Sub-Clause 2.5 [The Beneficiarys Claims], the Beneficiary is entitled to correct the arithmetical errors from any IPC.

A new paragraph shall be added at the end of Sub-clause 14.6: Without prejudice to any of the Contractors rights which may arise from the Contract or in any other way, the Engineer cannot issue an IPC which would incur the increase the cumulated value approved for payment so that it would exceed the Accepted Contract Amount or any other contract value subsequently agreed by the Contractor and Beneficiary within addenda to the Contract. Sub-Clauza 14.7 Plile/ Sub-Clause 14.7 - Payments naintea primului paragraf al Sub-Clauzei 14.7 se adaug urmtoarele: n termen de 7 zile de la data emiterii Certificatului de Plat de ctre Inginer, Antreprenorul trebuie s emit ctre Beneficiar o factur n valoarea specificat n Certificatul de Plat corespunztor. Se terge paragraful (a) al Sub-Clauzei 14.7. Se terge paragraful (b) al Sub-Clauzei 14.7 i se nlocuiete cu urmtoarele: (a) valoarea specificat n fiecare factur corespunztoare fiecrui Certificat Interimar de Plat, n termen de 28 de zile de la data emiterii facturii de ctre Antreprenor. Se terge paragraful (c) al Sub-Clauzei 14.7 i se nlocuiete cu urmtoarele: (b) valoarea specificat n fiecare factur corespunztoare Certificatului Final de Plat, n termen de 56 de zile de la data emiterii facturii de ctre Antreprenor./ Before the first paragraph of Sub-Clause 14.7 the followings shall be added:

p18 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause

Prevederi/Provisions Within 7 days from the issue date of the IPC by the Engineer, the Contractor must issue to the Beneficiary an invoice for the specified value in the corresponding Payment Certificate. The paragraph (a) of Sub-Clause 14.7 shall be deleted. The paragraph (b) of Sub-Clause 14.7 shall be deleted and replaced by the following:(a) the specified value in each invoice corresponding to an IPC, within 28 days from the date of the invoice issue by the Contractor. The paragraph (c) of Sub-Clause 14.7 shall be deleted and replaced by the followings: (b) the specified value value in each invoice corresponding to an IPC, within 56 days from the date of the invoice issue by the Contractor. Sub-Clauza 14.8 ntrzieri n efectuarea plilor/ Sub-Clause 14.8 Delayed Payment Se terge ultimul paragraf al Sub-Clauzei 14.8 i se nlocuiete cu urmtoarele: Antreprenorul va fi ndreptit la aceast plat pe baza emiterii unei facturi, fr nicio alt ntiinare sau aprobare formal, i fr a afecta alt drept sau remediu./ The last paragraph of Sub-Clause 14.8 shall be deleted and replaced by the following:The Contractor shall be entitled to this payment on the basis of issuing an invoice, without any other notification or formal approval and without affecting any other right or remedy. Sub-Clauza 14.9 Plata Sumelor Reinute Sub-Clause 14.9 Payment of Retention Money n prima propoziie a primului paragraf al acestei SubClauze 14.9 se terg cuvintele Procesului Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificatului de Recepie la Terminarea Lucrrilor n a doua propoziie a primului paragraf al acestei SubClauze 14.9 se terg cuvintele Proces Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificat de Recepie la Terminarea Lucrrilor n cel de-al doilea paragraf al acestei Sub-Clauze 14.9 se terg cuvintele Proces Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificat de Recepie la Terminarea Lucrrilor/ In the first sentence of the first paragraph of this SubClause 14.9 the words Minutes of Reception at Completion shall be deleted and shall be replaced by Taking Over Certificate at Completion. In the second sentence of the first paragraph of this SubClause 14.9 the words Minutes of Reception at

p19 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause

Prevederi/Provisions Completion shall be deleted and shall be replaced by Taking Over Certificate at completion.

In the second paragraph of this Sub-Clause 14.9 the words Minutes of Reception at Completion shall be deleted and shall be replaced by Taking Over Certificate at Completion. Sub-Clauza 14.10 Situaia de Lucrri la Terminare/ Sub-Clause 14.10 Statement at Completion n primul paragraf al acestei sub-Clauze 14.10 se terg cuvintele Procesului Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificatului de Recepie la Terminarea Lucrrilor n sub-pargraful (a) al primului paragraf al acestei SubClauze 14.10 se terg cuvintele Procesul Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificatul de Recepie la Terminarea Lucrrilor. In the first paragraph of this Sub-Clause 14.10 the words Minutes of Reception at Completion shall be deleted and shall be replaced by Taking Over Certificate at Completion. In the sub-paragraph (a) of the first paragraph of this SubClause 14.10 the words Minutes of Reception at Completion shall be deleted and shall be replaced by Taking Over Certificate at Completion. Sub-Clauza 14.11 Prezentarea Situaiilor Finale de Lucrri/ Sub-Clause 14.11 Application for Final Payment Certificate n primul paragraf al acestei sub-Clauze 14.11 se terg cuvintele Procesului Verbal de Recepie Final i se nlocuiesc cu Certificatului de Recepie Final. In the first paragraph of this Sub-Clause 14.11 the words of the Minutes of the Final Receipt shall be deleted and replaced by of the Final Reception Certificate (Performance Certificate). SubClauza 14.13- Emiterea Certificatului Final de Plat/ Sub-Clause 14.13 - Issue of Final Payment Certificate La sfritul Sub-Clauzei 14.13 se adaug un nou paragraf: Fr a prejudicia niciun alt drept al Antreprenorului ce decurge din Contract sau n alt mod, Inginerul nu poate emite un Certificat Final de Plat dac valoarea cumulat aprobat pentru plat depete Valoarea de Contract Acceptat sau alt valoare de contract convenit ulterior de Beneficiar i Antreprenor n cadrul unor acte adiionale la Contract. At the end of the Sub-Clause 14.13 a new paragraph shall be added:Without prejudice to any other right of the Contractor arising from the Contract or in any other way, the Engineer cannot issue a Final Payment Certificate if the cumulated value approved for payment exceeds the Accepted

p20 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause

Prevederi/Provisions

Contract Amount or any other contract value subsequently agreed by the Contractor and Beneficiary within addenda to the Contract. Sub-Clauza 14.14 ncetarea Responsabilitii Beneficiarului/ Sub-Clause 14.14 Cessation of Beneficiarys Liability n sub-paragraful (b) al primului paragraf al acestei SubClauze 14.10 se terg cuvintele Procesului Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificatului de Recepie la Terminarea Lucrrilor / In sub-paragraph (b) of the first paragraph of this SubClause 14.10 the words Minutes of Reception at Completion shall be deleted and shall be replaced by Taking Over Certificate at Completion. Clauza 15 Rezilierea Contractului de ctre Beneficiar/ Clause 15 Termination by the Beneficiary Sub-Clauza 15.2 Rezilierea Contractului de ctre Beneficiar/ Sub-Clause 15.2 Termination by the Beneficiary Se terg ultimele dou fraze ale ultimului paragraf al SubClauzei 15.2. The last two sentences of the last paragraph of SubClause 15.2 shall be deleted. Clauza 16 Suspendarea i rezilierea Contractului de ctre Antreprenor/ Clause 16 Suspension and Termination by the Contractor Sub-Clauza 16.2 - Rezilierea Contractului de ctre Antreprenor/ Sub-Clause 16.2 - Termination by the Contractor Se terge subparagraful (e) al Sub-Clauzei 16.2 i se nlocuiete cu urmtoarele: "(e) Beneficiarul nu reuete sa respecte prevederile SubClauzei 1.7 [Cesionarea]. The sub-paragraph (e) of Sub-Clause 16.2 shall be deleted and replaced by the following:(e)The Beneficiary fails to comply with the provisions of Clause 1.7 (Cessation) Clauza 17 Clause 17 Sub-Clauza 17.2 Responsabilitatea Antreprenorului fa de Lucrri/ Sub-Clause 17.2 Contractors care of the Works Se terge prima propoziie din primul paragraf al acestei Sub-Clauze 17.2 i se nlocuiete cu urmtoarele: Antreprenorul i va asuma ntreaga responsabilitate pentru ngrijirea Lucrrilor i a Bunurilor de la Data de ncepere pn la data emiterii Certificatului de Recepie la Terminarea Lucrrilor sau pn cnd recepia se consider admis de Beneficiar n condiiile legii, dat la care responsabilitatea pentru grija fa de Lucrri va fi transferat Beneficiarului n a doua propoziie a primului paragraf al acestei SubClauze 17.2 se terg cuvintele Proces Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificat de

p21 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause

Prevederi/Provisions Recepie la Terminarea Lucrrilor n al doilea paragraf al acestei Sub-Clauze 17.2 se terg cuvintele Procesul Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificatul de Recepie la Terminarea Lucrrilor n prima propoziie a ultimului paragraf al acestei SubClauze 17.2 se terg cuvintele Procesului Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificatului de Recepie la Terminarea Lucrrilor n ultima propoziie a ultimului paragraf al acestei SubClauze 17.2 se terg cuvintele Procesul Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificatul de Recepie la Terminarea Lucrrilor. The first sentence of the first paragraph of this Sub-Clause 17.2 shall be deleted and replaced by the following:The Contractor shall take the entire responsibility for the care of the works and goods from the Commencement date until the date of issue of the Taking Over Certificate at Completion or until the reception is considered to be admitted by the Beneficiary, in conditions of the law, at which date the responsibility of the care for Works shall be transferred to the Beneficiary. In the second sentence of the first paragraph of this SubClause 17.2 the words Minutes of Reception at Completion shall be deleted and shall be replaced by Taking Over Certificate at Completion. In the second paragraph of this Sub-Clause 17.2 the words Minutes of Reception at Completion shall be deleted and shall be replaced by Taking Over Certificate at Completion. In the first sentence of the last paragraph of this SubClause 17.2 the words Minutes of Reception at Completion shall be deleted and shall be replaced by Taking Over Certificate at Completion. In the last sentence of the last paragraph of this SubClause 17.2 the words Minutes of Reception at Completion shall be deleted and shall be replaced by Taking Over Certificate at Completion.

Clauza 18 Asigurri/ Clause 18 - Insurance Sub-Clauza 18.1 Cerine generale pentru asigurri/ Sub-Clause 18.1 General requirements for insurance Se terge Scrisoare de Acceptare din a doua fraz a paragraful secund al Sub-Clauzei 18.1 i se nlocuiete cu Acord Contractual./ From the second sentence of the second paragraph of Sub-Clause 18.1 the words Letter of Acceptance shall be deleted and replaced by Contract Agreement.

p22 of 23

ANEXA nr. 1b la Ordinul nr. 915/465/415/2008 pentru aprobarea condiiilor contractuale generale si speciale la ncheierea contractelor de lucrri Condiii Speciale Obligatorii pentru Condiii de Contract pentru Construcii

__________________________________________________________________________

Clauza/Clause Prevederi/Provisions Sub-Clauza 18.2 Asigurarea Lucrrilor i a Utilajelor Antreprenorului/ Sub-Clause 18.2 Insurance for Works and Contractor Equipment n primul paragraf al acestei Sub-Clauze 18.2 se terg cuvintele Procesului Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificatului de Recepie la Terminarea Lucrrilor n al doilea paragraf al acestei sub-Clauze 18.2 se terg cuvintele Procesului Verbal de Recepie Final i Procesului Verbal de Recepie la Terminarea Lucrrilor i se nlocuiesc cu Certificatului de Recepie Final respectiv Certificatului de Recepie la Terminarea Lucrrilor. In the first paragraph of this Sub-Clause 18.2 the words Minutes of Reception at Completion shall be deleted and shall be replaced by Taking Over Certificate at Completion. In the second paragraph of this Sub-Clause 18.2 the words of the Minutes of Final Reception and of the Minutes of Reception at Completion shall be deleted and shall be replaced by of the Final Reception Certificate (Performance Certificate) and by Taking Over Certificate at Completion respectively. Sub-Clauza 18.3 Asigurare mpotriva Vtmrii Persoanelor i a Daunelor Aduse Proprietii Sub-Clause 18.3 Insurance against Injury to Persons and Damage to Property n primul paragraf al acestei Sub-Clauze 18.3 se terg cuvintele Procesului Verbal de Recepie Final i se nlocuiesc cu Certificatului de Recepie Final. In the first paragraph of this Sub-Clause 18.3 the words of the Minutes of Final Reception shall be deleted and shall be replaced by of the Final Reception Certificate (Performance Certificate).