Formular F3
Lista cu cantitati de lucrari pe categorii de lucrari
1.1 2100945 - Beton de ciment B 150 stas 3622 mc 0.270 288.00 77.76
2 ACD04A1 - Inaltatoare camine - cofrat, armat si turnat buc 1.000 1,481.87 1,481.87
material: 171.00 171.00
manopera: 1,310.87 1,310.87
utilaj: 0.00 0.00
transport: 0.00 0.00
2.1 2100971 - Beton de ciment B 300-BC22,5 stas 3622 mc 0.600 285.00 171.00
3 DD08A01^ - Rigola ml 12.000 60.92 731.10
material: 45.96 551.46
manopera: 14.97 179.64
utilaj: 0.00 0.00
transport: 0.00 0.00
Cheltuieli indirecte
Cheltuieli indirecte 10.0000 % 405.02 590.06 0.00 71.99 1,067.08
T3 = T2 + Cheltuieli indirecte 4,455.24 6,490.70 0.00 791.94 11,737.88
Beneficiu
Profit 5.0000 % 222.76 324.53 0.00 39.60 586.89
T4 = T3 + Beneficiu 4,678.00 6,815.23 0.00 831.54 12,324.77