Documente Academic
Documente Profesional
Documente Cultură
- lei -
F3cp - LISTA cu cantitati de lucrari pe categorii de lucrari
Pretul unitar
Manopera
Transport
Material
Utilaj TOTALUL
(exclusiv
Nr. Capitolul de lucrari U.M. Cantitatea (excl TVA)
(exclusiv TVA)
TVA)
- lei - - lei -
- lei -
0 1 2 3 4 7 5
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: DRUM
STADIUL FIZIC: TERASAMENTE
1 TSG02A1 Curatarea amplasamentului de frunze, 100 576.19 97.91 56,414.99
crengi,etc MP material: 0.00 0.00
manopera: 97.91 56,414.99
utilaj: 0.00 0.00
transport: 0.00 0.00
1 TRA01A15P TRANSPORTUL RUTIER AL TON 146.33 15.00 2,194.95
PAMINTULUI SAU MOLOZULUI CU A material: 0.00 0.00
AUTOBASCULANTA DIST.=15 KM
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 15.00 2,194.95
2 TSG02A1 Curatarea amplasamentului de tufisuri 100 287.62 97.91 28,160.89
[ 1] si arbusti MP material: 0.00 0.00
manopera: 97.91 28,160.89
utilaj: 0.00 0.00
transport: 0.00 0.00
2 TRA01A15P TRANSPORTUL RUTIER AL TON 71.90 15.00 1,078.50
PAMINTULUI SAU MOLOZULUI CU A material: 0.00 0.00
AUTOBASCULANTA DIST.=15 KM
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 15.00 1,078.50
3 C.4.B Taierea manuala a tufisurilor, arbustilor buc 100.00 440.75 44,074.56
si arborilor subtiri cu scoaterea material: 0.00 0.00
radacinilor
manopera: 440.75 44,074.56
utilaj: 0.00 0.00
transport: 0.00 0.00
4 OD11E PICHETAREA DETALIATA A KM 4.80 597.60 2,868.48
[ 1] DRUMULUI material: 300.00 1,440.00
manopera: 297.60 1,428.48
utilaj: 0.00 0.00
transport: 0.00 0.00
5 DG06B1 SPARG SI DESF BET CIM PE MC 260.00 114.32 29,723.30
[ 4] SUPRAF LIMIT PT POZARE CABL material: 0.00 0.00
COND POD GURI,SCURG IN ALEI
manopera: 50.29 13,076.54
FUND DRUM
utilaj: 64.03 16,646.76
transport: 0.00 0.00
Pag 2
STADIUL FIZIC: TERASAMENTE
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: DRUM
STADIUL FIZIC: TERASAMENTE
5 TRA01A15P TRANSPORTUL RUTIER AL TON 624.00 15.00 9,360.00
PAMINTULUI SAU MOLOZULUI CU A material: 0.00 0.00
AUTOBASCULANTA DIST.=15 KM
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 15.00 9,360.00
6 TSC01B1 ASIMILAT-DECAPAREA SI MC 45,024.00 13.92 626,734.08
[ 3] DEPOZITAREA PAMANTULUI material: 0.00 0.00
VEGETAL
manopera: 0.00 0.00
utilaj: 13.92 626,734.08
transport: 0.00 0.00
6 TRA01A15P TRANSPORTUL RUTIER AL TON 170.00 15.00 2,550.00
PAMINTULUI SAU MOLOZULUI CU A material: 0.00 0.00
AUTOBASCULANTA DIST.=15 KM
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 15.00 2,550.00
7 TSC02B1 SAPATURA CU EXCAVAT.PE PNEURI 100 41.30 1,500.21 61,958.67
0,21-0,39 MC PAMINT UMIDIT.NATUR MC material: 0.00 0.00
DESC.DEP.TER.CAT. 2
manopera: 0.00 0.00
utilaj: 1,500.21 61,958.67
transport: 0.00 0.00
7 TRA01A15P TRANSPORTUL RUTIER AL TON 4,956.00 15.00 74,340.00
PAMINTULUI SAU MOLOZULUI CU A material: 0.00 0.00
AUTOBASCULANTA DIST.=15 KM
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 15.00 74,340.00
8 DA06B1 STRAT AGREG NAT CILINDRATE CU MC 12,150.00 102.20 1,241,771.37
[ 8] FUNC REZIST FILTRANTIZOLAT material: 62.00 753,300.00
AERISIRE SI ANTICAP CU ASTER
manopera: 10.97 133,326.87
MEC BALAST
utilaj: 29.23 355,144.50
transport: 0.00 0.00
8 TRA01A15 TRANSPORTUL RUTIER AL TON 19,440.00 15.00 291,600.00
MATERIALELOR, A material: 0.00 0.00
SEMIFABRICATELOR CU
manopera: 0.00 0.00
AUTOBASCULANTA PE DIST.= 15
KM. utilaj: 0.00 0.00
transport: 15.00 291,600.00
9 RCSA06B% Pamant vegetal pe taluzuri mc 7,220.00 16.89 121,946.52
material: 0.40 2,888.00
manopera: 15.18 109,582.27
utilaj: 1.31 9,476.25
transport: 0.00 0.00
10 TRA01A15 Transportul rutier al pamantului cu tona 8,664.00 15.00 129,960.00
autobasculanta pe dist.= 15 km. material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 15.00 129,960.00
11 RCSA06B% Pamant vegetal pe suprafete mc 1,240.00 16.89 20,943.72
orizontale, inlcusiv gropapa de material: 0.40 496.00
imprumut
manopera: 15.18 18,820.22
utilaj: 1.31 1,627.50
transport: 0.00 0.00
Pag 3
STADIUL FIZIC: TERASAMENTE
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: DRUM
STADIUL FIZIC: TERASAMENTE
12 TRA01A15 Transportul rutier al pamantului cu tona 1,488.00 15.00 22,320.00
autobasculanta pe dist.= 15 km. material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 15.00 22,320.00
13 RCSA06B% Umplutura din groapa imprumut mc 89,360.00 26.44 2,362,866.06
(balastiera Balta Doamnei) material: 9.95 889,310.72
manopera: 15.18 1,356,270.34
utilaj: 1.31 117,285.00
transport: 0.00 0.00
14 TRA01A15 Transportul rutier al pamantului cu tona 107,232.00 15.00 1,608,480.00
autobasculanta pe dist.= 15 km. material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 15.00 1,608,480.00
procent material manopera utilaj transport total
Cheltuieli directe: 1,647,434.72 1,761,155.17 1,188,872.76 2,141,883.45 6,739,346.10
Recapitulatia: 4/4 Recap 2019: CAM 2,25
Alte cheltuieli directe:
Contributie 2.2500 % 0.00 39,625.99 0.00 0.00 39,625.99
asiguratorie pentru
munca (CAM)
Total inclusiv Cheltuieli 1,647,434.72 1,800,781.16 1,188,872.76 2,141,883.45 6,778,972.09
directe:
Cheltuieli indirecte 4.0000 % 65,897.39 72,031.25 47,554.91 85,675.34 271,158.88
Total inclusiv Cheltuieli 1,713,332.11 1,872,812.41 1,236,427.67 2,227,558.79 7,050,130.98
indirecte:
Profit 4.0000 % 68,533.28 74,912.50 49,457.11 89,102.35 282,005.24
Total inclusiv Beneficiu: 1,781,865.39 1,947,724.90 1,285,884.78 2,316,661.14 7,332,136.22
TOTAL GENERAL (fara TVA): 7,332,136.22
TVA: 19.00% 1,393,105.88
TOTAL GENERAL: 8,725,242.10
OBIECTUL: DRUM
STADIUL FIZIC: SUPRASTRUCTURA
1 DA06B1 STRAT AGREG NAT CILINDRATE CU MC 23,650.00 102.20 2,417,110.52
[ 8] FUNC REZIST FILTRANTIZOLAT material: 62.00 1,466,300.00
AERISIRE SI ANTICAP CU ASTER
manopera: 10.97 259,521.02
MEC BALAST
utilaj: 29.23 691,289.50
transport: 0.00 0.00
1 TRA01A15 TRANSPORTUL RUTIER AL TON 37,840.00 15.00 567,600.00
MATERIALELOR, A material: 0.00 0.00
SEMIFABRICATELOR CU
manopera: 0.00 0.00
AUTOBASCULANTA PE DIST.= 15
KM. utilaj: 0.00 0.00
transport: 15.00 567,600.00
2 DA11B1 STRAT DE PIATRA SPARTA mc 2,200.00 191.68 421,686.10
material: 140.00 308,000.00
manopera: 32.74 72,019.20
utilaj: 18.94 41,666.90
transport: 0.00 0.00
Pag 4
STADIUL FIZIC: SUPRASTRUCTURA
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: DRUM
STADIUL FIZIC: SUPRASTRUCTURA
3 TRA01A50 TRANSPORTUL RUTIER AL tona 4,689.78 52.00 243,868.56
MATERIALELOR,SEMI material: 0.00 0.00
FABRICATELOR CU
manopera: 0.00 0.00
AUTOBASCULANTA PEDIST. 50 KM.
utilaj: 0.00 0.00
transport: 52.00 243,868.56
4 DA06A2 STRAT DIN NISIP mc 100.00 113.56 11,356.00
material: 70.00 7,000.00
manopera: 14.88 1,488.00
utilaj: 28.68 2,868.00
transport: 0.00 0.00
4 TRA01A15 TRANSPORTUL RUTIER AL TON 160.00 15.00 2,400.00
MATERIALELOR, A material: 0.00 0.00
SEMIFABRICATELOR CU
manopera: 0.00 0.00
AUTOBASCULANTA PE DIST.= 15
KM. utilaj: 0.00 0.00
transport: 15.00 2,400.00
5 DA07XB STRAT DIN AGREGATE NATURALE mc 5,380.00 382.45 2,057,580.95
STABILIZATE CU LIANTI material: 148.32 797,962.25
manopera: 38.06 204,779.16
utilaj: 196.07 1,054,839.55
transport: 0.00 0.00
5 TRA01A15 TRANSPORTUL RUTIER AL TON 11,836.00 15.00 177,540.00
MATERIALELOR, A material: 0.00 0.00
SEMIFABRICATELOR CU
manopera: 0.00 0.00
AUTOBASCULANTA PE DIST.= 15
KM. utilaj: 0.00 0.00
transport: 15.00 177,540.00
6 DB12B1 Strat din mixtura asfaltica AB31.5 tona 6,390.00 530.72 3,391,293.13
material: 450.62 2,879,438.80
manopera: 38.39 245,314.66
utilaj: 41.71 266,539.68
transport: 0.00 0.00
7 DB12B1+ Beton asfaltic deschis – strat de tona 5,470.00 500.72 2,738,931.84
legatura BAD22.4 material: 420.62 2,300,771.71
manopera: 38.39 209,995.49
utilaj: 41.71 228,164.64
transport: 0.00 0.00
8 DB12C% Strat de uzura din mixtura asfaltica mp 28,190.00 57.27 1,614,441.30
stabilizata – MAS– cu grosimea de 4 material: 44.82 1,263,566.01
cm
manopera: 5.36 151,008.19
utilaj: 7.09 199,867.10
transport: 0.00 0.00
9 DB12C# Strat de uzura tip – BA16– cu grosimea mp 11,710.00 48.81 571,565.10
de 4 cm material: 36.36 425,813.07
manopera: 5.36 62,728.13
utilaj: 7.09 83,023.90
transport: 0.00 0.00
10 DB02D+ Amorsare cu emulsie cationica cu 100 723.00 535.00 386,805.00
rupere rapida cu 0,6Kg/mp mp material: 449.90 325,279.30
manopera: 73.61 53,220.69
utilaj: 11.49 8,305.00
transport: 0.00 0.00
Pag 5
STADIUL FIZIC: SUPRASTRUCTURA
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: DRUM
STADIUL FIZIC: SUPRASTRUCTURA
11 DB02D1 Amorsare cu emulsie cationica cu 100 364.00 670.00 243,880.00
rupere rapida cu 0,9Kg/mp mp material: 616.53 224,416.73
manopera: 44.85 16,323.61
utilaj: 8.63 3,139.66
transport: 0.00 0.00
12 RpDB37B% Decaparea imbracamintilor asfaltice de mp 3,460.00 9.00 31,140.00
pana la 3 cm grosime formate din: material: 0.00 0.00
imbracaminti semipermanente, astfalt
manopera: 9.00 31,140.00
turnat pe binder, covoare si mortare
asfaltice la rece; utilaj: 0.00 0.00
transport: 0.00 0.00
13 RpDB37B- Decaparea imbracamintilor asfaltice de mp 1,850.00 19.34 35,786.40
1% pana la 3 cm grosime formate din: material: 0.00 0.00
imbracaminti semipermanente, astfalt
manopera: 19.34 35,786.40
turnat pe binder, covoare si mortare
asfaltice la rece; pentru fiecare utilaj: 0.00 0.00
centimetru in plus fata de cei 3 transport: 0.00 0.00
14 DG05A1 Indepartarea structurii rutiere la mc 380.00 40.00 15,200.00
marginea partii carosabile existente material: 0.00 0.00
manopera: 40.00 15,200.00
utilaj: 0.00 0.00
transport: 0.00 0.00
15 DG05XA Indepartarea structurii rutiere pe mc 1,650.00 47.00 77,550.00
intreaga suprafata a partii carosabile material: 0.00 0.00
existente
manopera: 47.00 77,550.00
utilaj: 0.00 0.00
transport: 0.00 0.00
16 DD04A01+ Geocompozit biodegradabil B2B mp 960.00 10.79 10,355.71
CONSPRODBIOFELT pt. protectie si material: 6.79 6,515.71
aparare taluzuri prin fixarea vegetatiei
manopera: 4.00 3,840.00
utilaj: 0.00 0.00
transport: 0.00 0.00
17 DB23G# Borduri pref.din beton pt.trotuare m 960.00 49.77 47,778.72
alei/spatii verzi, 10x 15cm, pe fundate- material: 29.77 28,578.72
beton de 10x 20cm
manopera: 20.00 19,200.00
utilaj: 0.00 0.00
transport: 0.00 0.00
18 DE08XC Borduri pentru trotuare avind m 260.00 92.49 24,047.68
dimensiunile: 20x25 pe fundatii de material: 64.49 16,767.68
beton 35x25 cm
manopera: 28.00 7,280.00
utilaj: 0.00 0.00
transport: 0.00 0.00
19 DB02D# Pavaj cu mat.de pavaj cal.i - pavele mp 815.00 105.33 85,840.93
normale, asezate pe 1 strat de nisip material: 69.67 56,777.87
manopera: 35.00 28,525.00
utilaj: 0.66 538.06
transport: 0.00 0.00
20 DA14A+ Fundatie din beton de ciment la strazi mc 120.00 506.13 60,735.28
alei si platforme carosabile material: 392.16 47,059.42
manopera: 91.96 11,035.01
utilaj: 22.01 2,640.85
transport: 0.00 0.00
Pag 6
STADIUL FIZIC: SUPRASTRUCTURA
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: DRUM
STADIUL FIZIC: SUPRASTRUCTURA
21 CZ0201A1 Mortar ciment M100 mc 30.00 381.19 11,435.68
material: 300.00 9,000.00
manopera: 15.48 464.26
utilaj: 65.71 1,971.42
transport: 0.00 0.00
procent material manopera utilaj transport total
Cheltuieli directe: 10,163,247.26 1,506,418.81 2,584,854.26 991,408.56 15,245,928.89
Recapitulatia: 4/4 Recap 2019: CAM 2,25
Alte cheltuieli directe:
Contributie 2.2500 % 0.00 33,894.42 0.00 0.00 33,894.42
asiguratorie pentru
munca (CAM)
Total inclusiv Cheltuieli 10,163,247.26 1,540,313.23 2,584,854.26 991,408.56 15,279,823.31
directe:
Cheltuieli indirecte 4.0000 % 406,529.89 61,612.53 103,394.17 39,656.34 611,192.93
Total inclusiv Cheltuieli 10,569,777.15 1,601,925.76 2,688,248.43 1,031,064.90 15,891,016.24
indirecte:
Profit 4.0000 % 422,791.09 64,077.03 107,529.94 41,242.60 635,640.65
Total inclusiv Beneficiu: 10,992,568.24 1,666,002.79 2,795,778.37 1,072,307.50 16,526,656.89
TOTAL GENERAL (fara TVA): 16,526,656.89
TVA: 19.00% 3,140,064.81
TOTAL GENERAL: 19,666,721.70
OBIECTUL: DRUM
STADIUL FIZIC: SCURGEREA APELOR
1 RLE2ICN30 Dezafectare santuri existente m 1,810.00 19.05 34,473.98
A material: 0.00 0.00
manopera: 19.05 34,473.98
utilaj: 0.00 0.00
transport: 0.00 0.00
2 CR34B# Rigole acostament din beton 60 cm m 985.00 101.65 100,123.46
material: 61.47 60,550.10
manopera: 40.18 39,573.36
utilaj: 0.00 0.00
transport: 0.00 0.00
3 RCSU06B# Santuri noi pavate cu elemente m 5,450.00 151.47 825,527.03
prefabricate din beton pe substrat de material: 113.19 616,869.15
nisip
manopera: 38.00 207,100.00
utilaj: 0.29 1,557.88
transport: 0.00 0.00
4 M.1.A Decolmatarea canalelor...decolmatat mc 4,900.00 100.00 490,000.00
canale material: 0.00 0.00
manopera: 100.00 490,000.00
utilaj: 0.00 0.00
transport: 0.00 0.00
procent material manopera utilaj transport total
Cheltuieli directe: 677,419.25 771,147.34 1,557.88 0.00 1,450,124.47
Pag 7
STADIUL FIZIC: SCURGEREA APELOR
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: DRUM
STADIUL FIZIC: SCURGEREA APELOR
Recapitulatia: 4/4 Recap 2019: CAM 2,25
Alte cheltuieli directe:
Contributie 2.2500 % 0.00 17,350.82 0.00 0.00 17,350.82
asiguratorie pentru
munca (CAM)
Total inclusiv Cheltuieli 677,419.25 788,498.16 1,557.88 0.00 1,467,475.29
directe:
Cheltuieli indirecte 4.0000 % 27,096.77 31,539.93 62.32 0.00 58,699.01
Total inclusiv Cheltuieli 704,516.02 820,038.09 1,620.20 0.00 1,526,174.30
indirecte:
Profit 4.0000 % 28,180.64 32,801.52 64.81 0.00 61,046.97
Total inclusiv Beneficiu: 732,696.66 852,839.61 1,685.01 0.00 1,587,221.27
TOTAL GENERAL (fara TVA): 1,587,221.27
TVA: 19.00% 301,572.04
TOTAL GENERAL: 1,888,793.31
OBIECTUL: DRUM
STADIUL FIZIC: RELOCARI DRUMURI LOCALE
1 TSC01B1 ASIMILAT-DECAPAREA SI MC 1,000.00 13.92 13,920.00
[ 3] DEPOZITAREA PAMANTULUI material: 0.00 0.00
VEGETAL
manopera: 0.00 0.00
utilaj: 13.92 13,920.00
transport: 0.00 0.00
1 TRA01A15P TRANSPORTUL RUTIER AL TON 1,200.00 15.00 18,000.00
PAMINTULUI SAU MOLOZULUI CU A material: 0.00 0.00
AUTOBASCULANTA DIST.=15 KM
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 15.00 18,000.00
2 RCSA06B% Umpluturi cu pamant din deblee sau mc 1,900.00 26.44 50,239.99
groapa de imprumut material: 9.95 18,908.80
manopera: 15.18 28,837.44
utilaj: 1.31 2,493.75
transport: 0.00 0.00
3 TRA01A15 Transportul rutier al pamantului cu tona 1,440.00 15.00 21,600.00
autobasculanta pe dist.= 15 km. material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 15.00 21,600.00
4 DA06B1 STRAT AGREG NAT CILINDRATE CU MC 670.00 102.20 68,476.28
[ 8] FUNC REZIST FILTRANTIZOLAT material: 62.00 41,540.00
AERISIRE SI ANTICAP CU ASTER
manopera: 10.97 7,352.18
MEC BALAST
utilaj: 29.23 19,584.10
transport: 0.00 0.00
4 TRA01A15 TRANSPORTUL RUTIER AL TON 1,072.00 15.00 16,080.00
MATERIALELOR, A material: 0.00 0.00
SEMIFABRICATELOR CU
manopera: 0.00 0.00
AUTOBASCULANTA PE DIST.= 15
KM. utilaj: 0.00 0.00
transport: 15.00 16,080.00
5 DA11B1 STRAT DE PIATRA SPARTA mc 950.00 191.68 182,091.73
material: 140.00 133,000.00
manopera: 32.74 31,099.20
utilaj: 18.94 17,992.53
transport: 0.00 0.00
Pag 8
STADIUL FIZIC: RELOCARI DRUMURI LOCALE
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: DRUM
STADIUL FIZIC: RELOCARI DRUMURI LOCALE
6 TRA01A50 TRANSPORTUL RUTIER AL tona 1,710.00 52.00 88,920.00
MATERIALELOR,SEMI material: 0.00 0.00
FABRICATELOR CU
manopera: 0.00 0.00
AUTOBASCULANTA PEDIST. 50 KM.
utilaj: 0.00 0.00
transport: 52.00 88,920.00
procent material manopera utilaj transport total
Cheltuieli directe: 193,448.80 67,288.82 53,990.38 144,600.00 459,328.00
Recapitulatia: 4/4 Recap 2019: CAM 2,25
Alte cheltuieli directe:
Contributie 2.2500 % 0.00 1,514.00 0.00 0.00 1,514.00
asiguratorie pentru
munca (CAM)
Total inclusiv Cheltuieli 193,448.80 68,802.82 53,990.38 144,600.00 460,841.99
directe:
Cheltuieli indirecte 4.0000 % 7,737.95 2,752.11 2,159.62 5,784.00 18,433.68
Total inclusiv Cheltuieli 201,186.75 71,554.93 56,149.99 150,384.00 479,275.67
indirecte:
Profit 4.0000 % 8,047.47 2,862.20 2,246.00 6,015.36 19,171.03
Total inclusiv Beneficiu: 209,234.22 74,417.13 58,395.99 156,399.36 498,446.70
TOTAL GENERAL (fara TVA): 498,446.70
TVA: 19.00% 94,704.87
TOTAL GENERAL: 593,151.57
OBIECTUL: DRUM
STADIUL FIZIC: PODETE
1 C9 Timpan prefabricat tip T2 buc 10.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
2 C22 Aripa prefabricata podet A3, C35/45 buc 12.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
3 C21 Aripa prefabricata podet A0, C35/45 buc 4.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
4 C20 Aripa prefabricata podet A1, C35/45 buc 16.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
5 C7b Element prefabricat podet C2', C35/45 buc 39.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
Pag 9
STADIUL FIZIC: PODETE
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: DRUM
STADIUL FIZIC: PODETE
6 C7c Element prefabricat podet C2'', C35/45 buc 7.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
7 C25 Element prefabricat podet tip L2, buc 130.00 0.00 0.00
C35/45 material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
8 C1b Tuburi PREMO DN 1000 mm m 60.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
9 20019285 Beton C30/37 mc 10.00 400.00 4,000.00
material: 400.00 4,000.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
in camera cadere
10 20019266 Beton C35/45 mc 10.00 520.00 5,200.00
material: 520.00 5,200.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
in elevatii monolite
11 20019251 Beton C25/30 in fundatii mc 500.00 390.00 195,000.00
material: 390.00 195,000.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
in fundatii
12 DD17B% Scarificare si stabilizare cu lianti mc 250.00 104.30 26,075.00
hidraulici (2% - 5%) material: 78.44 19,610.00
manopera: 0.00 0.00
utilaj: 25.86 6,465.00
transport: 0.00 0.00
13 CZ0301E1 CONFECT ARMAT PT PERETI GRINZI kg 1,000.00 4.13 4,125.89
STILPI LA CONST OBIS IN ATELIERE material: 3.91 3,910.39
CENTRALIZATE Bst 500
manopera: 0.22 215.51
utilaj: 0.00 0.00
transport: 0.00 0.00
14 20019285 Beton C30/37 mc 180.00 400.00 72,000.00
material: 400.00 72,000.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
pereu
Pag 10
STADIUL FIZIC: PODETE
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: DRUM
STADIUL FIZIC: PODETE
15 W1M30XA Podete din tabla zincata ondulata m 36.00 0.00 0.00
L=5m H= 3m material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
16 L1C51A1 Dale prefabricate D5 buc 130.00 1,870.30 243,138.48
material: 1,766.88 229,694.40
manopera: 103.42 13,444.08
utilaj: 0.00 0.00
transport: 0.00 0.00
procent material manopera utilaj transport total
Cheltuieli directe: 529,414.79 13,659.59 6,465.00 0.00 549,539.37
Recapitulatia: 4/4 Recap 2019: CAM 2,25
Alte cheltuieli directe:
Contributie 2.2500 % 0.00 307.34 0.00 0.00 307.34
asiguratorie pentru
munca (CAM)
Total inclusiv Cheltuieli 529,414.79 13,966.93 6,465.00 0.00 549,846.71
directe:
Cheltuieli indirecte 4.0000 % 21,176.59 558.68 258.60 0.00 21,993.87
Total inclusiv Cheltuieli 550,591.38 14,525.60 6,723.60 0.00 571,840.58
indirecte:
Profit 4.0000 % 22,023.66 581.02 268.94 0.00 22,873.62
Total inclusiv Beneficiu: 572,615.03 15,106.63 6,992.54 0.00 594,714.20
TOTAL GENERAL (fara TVA): 594,714.20
TVA: 19.00% 112,995.70
TOTAL GENERAL: 707,709.90
OBIECTUL: DRUM
STADIUL FIZIC: SIGURANTA CIRCULATIEI
1 RpDE07A% Parapet metalic H1 W3 m 1,050.00 274.58 288,312.26
material: 228.19 239,598.98
manopera: 33.03 34,685.28
utilaj: 13.36 14,028.00
transport: 0.00 0.00
2 RpDE07B% Parapet metalic H2 W3 m 230.00 331.51 76,248.24
material: 280.36 64,482.54
manopera: 37.80 8,692.90
utilaj: 13.36 3,072.80
transport: 0.00 0.00
3 RpDE07C% Parapet metalic H3 W3 m 4,887.00 467.40 2,284,179.97
material: 394.68 1,928,820.79
manopera: 52.68 257,423.70
utilaj: 20.04 97,935.48
transport: 0.00 0.00
4 RpDE07E% Parapet metalic H4B W3 m 100.00 227.97 22,797.00
material: 192.19 19,218.65
manopera: 35.71 3,571.20
utilaj: 0.07 7.15
transport: 0.00 0.00
Pag 11
STADIUL FIZIC: SIGURANTA CIRCULATIEI
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: DRUM
STADIUL FIZIC: SIGURANTA CIRCULATIEI
5 EQ1f Dispozitiv antisoc buc 2.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
6 CMj23D01 Demolare parapete metalic ml 2,050.00 5.95 12,201.60
material: 0.00 0.00
manopera: 5.95 12,201.60
utilaj: 0.00 0.00
transport: 0.00 0.00
7 DF19A1 Indicatoare rutiere cu suprafata < 2mp buc 265.00 166.46 44,112.54
material: 153.37 40,642.52
manopera: 13.09 3,470.02
utilaj: 0.00 0.00
transport: 0.00 0.00
8 DF19A1 Indicatoare rutiere cu suprafata > 2mp buc 32.00 266.46 8,526.80
material: 253.37 8,107.78
manopera: 13.09 419.02
utilaj: 0.00 0.00
transport: 0.00 0.00
9 DF16A1 Marcajul longitudinal cu efect rezonator km 9.80 3,500.00 34,300.00
material: 3,130.83 30,682.16
manopera: 230.26 2,256.56
utilaj: 138.91 1,361.28
transport: 0.00 0.00
10 DF09XA Marcaj longitudinal km 4.90 3,500.00 17,150.00
material: 3,184.10 15,602.09
manopera: 190.25 932.25
utilaj: 125.65 615.66
transport: 0.00 0.00
11 DF17A1 Marcaje transversale mp 3,500.00 46.71 163,496.62
material: 22.56 78,970.78
manopera: 14.28 49,996.80
utilaj: 9.87 34,529.04
transport: 0.00 0.00
12 ATD30A Console metalice zincate termic buc 9.00 120.02 1,080.19
material: 98.00 882.00
manopera: 22.02 198.19
utilaj: 0.00 0.00
transport: 0.00 0.00
13 EQ355 Portaluri buc 2.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
14 EQ358 Butoni reflectorizanti buc 800.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
Pag 12
STADIUL FIZIC: SIGURANTA CIRCULATIEI
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: DRUM
STADIUL FIZIC: SIGURANTA CIRCULATIEI
15 EQ360 Benzi rezonatoare mp 120.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
procent material manopera utilaj transport total
Cheltuieli directe: 2,427,008.28 373,847.51 151,549.42 0.00 2,952,405.21
Recapitulatia: 4/4 Recap 2019: CAM 2,25
Alte cheltuieli directe:
Contributie 2.2500 % 0.00 8,411.57 0.00 0.00 8,411.57
asiguratorie pentru
munca (CAM)
Total inclusiv Cheltuieli 2,427,008.28 382,259.08 151,549.42 0.00 2,960,816.78
directe:
Cheltuieli indirecte 4.0000 % 97,080.33 15,290.36 6,061.98 0.00 118,432.67
Total inclusiv Cheltuieli 2,524,088.61 397,549.44 157,611.39 0.00 3,079,249.45
indirecte:
Profit 4.0000 % 100,963.54 15,901.98 6,304.46 0.00 123,169.98
Total inclusiv Beneficiu: 2,625,052.16 413,451.42 163,915.85 0.00 3,202,419.43
TOTAL GENERAL (fara TVA): 3,202,419.43
TVA: 19.00% 608,459.69
TOTAL GENERAL: 3,810,879.12
OBIECTUL: CONSOLIDARI
STADIUL FIZIC: LUCRARI CONSOLIDARI TERASAMENTE
12 DD17B% Scarificare si stabilizare cu lianti mc 22,400.00 104.30 2,336,320.00
hidraulici (2% - 5%) material: 78.44 1,757,056.00
manopera: 0.00 0.00
utilaj: 25.86 579,264.00
transport: 0.00 0.00
procent material manopera utilaj transport total
Cheltuieli directe: 1,757,056.00 0.00 579,264.00 0.00 2,336,320.00
Recapitulatia: 4/4 Recap 2019: CAM 2,25
Alte cheltuieli directe:
Contributie 2.2500 % 0.00 0.00 0.00 0.00 0.00
asiguratorie pentru
munca (CAM)
Total inclusiv Cheltuieli 1,757,056.00 0.00 579,264.00 0.00 2,336,320.00
directe:
Cheltuieli indirecte 4.0000 % 70,282.24 0.00 23,170.56 0.00 93,452.80
Total inclusiv Cheltuieli 1,827,338.24 0.00 602,434.56 0.00 2,429,772.80
indirecte:
Profit 4.0000 % 73,093.53 0.00 24,097.38 0.00 97,190.91
Total inclusiv Beneficiu: 1,900,431.77 0.00 626,531.94 0.00 2,526,963.71
TOTAL GENERAL (fara TVA): 2,526,963.71
TVA: 19.00% 480,123.10
TOTAL GENERAL: 3,007,086.82
OBIECTUL: MEDIU
STADIUL FIZIC: Deviz
D11f Bazin de retentie tip 1 buc 3.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
Pag 13
STADIUL FIZIC: Deviz
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: MEDIU
STADIUL FIZIC: Deviz
D11f Bazin de retentie tip 2 buc 2.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
D11a+D11g Bazin decantor+separator tip 1 buc 3.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
D11b+D11h Bazin decantor+separator tip 2 buc 3.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
D11c+D11i Bazin decantor+separator tip 3 buc 2.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
D11d+D11j Bazin decantor+separator tip 4 buc 1.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
EQ4c Demolare imprejmuire m 1,990.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
EQ5a Imprejmuire m 4,630.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
EQ 354c Demolare panouri antifonice m 281.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
EQ354a Panouri antifonice (H=3m) mp 281.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
procent material manopera utilaj transport total
Cheltuieli directe: 0.00 0.00 0.00 0.00 0.00
Pag 14
STADIUL FIZIC: Deviz
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: MEDIU
STADIUL FIZIC: Deviz
Recapitulatia: 4/4 Recap 2019: CAM 2,25
Alte cheltuieli directe:
Contributie 2.2500 % 0.00 0.00 0.00 0.00 0.00
asiguratorie pentru
munca (CAM)
Total inclusiv Cheltuieli 0.00 0.00 0.00 0.00 0.00
directe:
Cheltuieli indirecte 4.0000 % 0.00 0.00 0.00 0.00 0.00
Total inclusiv Cheltuieli 0.00 0.00 0.00 0.00 0.00
indirecte:
Profit 4.0000 % 0.00 0.00 0.00 0.00 0.00
Total inclusiv Beneficiu: 0.00 0.00 0.00 0.00 0.00
TOTAL GENERAL (fara TVA): 0.00
TVA: 19.00% 0.00
TOTAL GENERAL: 0.00
OBIECTUL: PEISAGISTICA
STADIUL FIZIC: LUCRARI MEDIU
1 NLST04 GAZON(SAPATURA,UMPLUTURA CU MP 1,900.00 75.39 143,234.71
[ 1] PAMANT VEGETAL,INSAMANTARE material: 58.70 111,524.05
GAZON,UDARE)
manopera: 14.88 28,272.00
utilaj: 1.81 3,438.66
transport: 0.00 0.00
1 TRA01A15P TRANSPORTUL RUTIER AL TON 54.80 15.00 822.00
PAMINTULUI SAU MOLOZULUI CU A material: 0.00 0.00
AUTOBASCULANTA DIST.=15 KM
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 15.00 822.00
2 DA27A# Plantare arbori buc 56.00 53.36 2,988.16
material: 0.09 4.85
manopera: 50.67 2,837.32
utilaj: 2.61 146.00
transport: 0.00 0.00
3 7202889 Acer tataricum buc 4.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
4 7201201 Acer platanoides buc 2.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
5 7203704 Acer saccharinum buc 4.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
6 7203077 Juniperus horizontalis buc 32.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
Pag 15
STADIUL FIZIC: LUCRARI MEDIU
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: PEISAGISTICA
STADIUL FIZIC: LUCRARI MEDIU
7 7201330 Cornus alba buc 14.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
8 DA27A# Plantare arbusti m 26.00 53.36 1,387.36
material: 0.09 2.25
manopera: 50.67 1,317.33
utilaj: 2.61 67.79
transport: 0.00 0.00
9 7202889 Ligustrum vulgare m 12.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
10 7201201 Tamarix ramosissima m 14.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
procent material manopera utilaj transport total
Cheltuieli directe: 111,531.15 32,426.64 3,652.44 822.00 148,432.23
Recapitulatia: 4/4 Recap 2019: CAM 2,25
Alte cheltuieli directe:
Contributie 2.2500 % 0.00 729.60 0.00 0.00 729.60
asiguratorie pentru
munca (CAM)
Total inclusiv Cheltuieli 111,531.15 33,156.24 3,652.44 822.00 149,161.83
directe:
Cheltuieli indirecte 4.0000 % 4,461.25 1,326.25 146.10 32.88 5,966.47
Total inclusiv Cheltuieli 115,992.39 34,482.49 3,798.54 854.88 155,128.31
indirecte:
Profit 4.0000 % 4,639.70 1,379.30 151.94 34.20 6,205.13
Total inclusiv Beneficiu: 120,632.09 35,861.79 3,950.48 889.08 161,333.44
TOTAL GENERAL (fara TVA): 161,333.44
TVA: 19.00% 30,653.35
TOTAL GENERAL: 191,986.79
OBIECTUL: PODURI
STADIUL FIZIC: Pasaj pe DJ 101C peste A3 la km 36+700 -solutia 1-reabilitare cale
1 SUPRASTRUCTURA
1.1 DG04B1 DESFACEREA DE BORDURI DE M 159.00 15.00 2,385.00
[ 2] PIATRA SAU DE BETON material: 0.00 0.00
ORICEDIMENSIUNE ASEZATA PE
manopera: 15.00 2,385.00
BETON
utilaj: 0.00 0.00
transport: 0.00 0.00
1.2 DG05XA Indepartarea structurii rutiere pe mc 25.00 47.00 1,175.00
intreaga suprafata a partii carosabile material: 0.00 0.00
existente
manopera: 47.00 1,175.00
utilaj: 0.00 0.00
transport: 0.00 0.00
Pag 16
STADIUL FIZIC: Pasaj pe DJ 101C peste A3 la km 36+700 -solutia 1-reabilitare cale
0 1 2 3 4 7 5
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: PODURI
STADIUL FIZIC: Pasaj pe DJ 101C peste A3 la km 36+700 -solutia 1-reabilitare cale
1.3 DB08A% Desfacere rosturi dilatatie m 23.00 6.50 149.50
material: 0.00 0.00
manopera: 6.50 149.50
utilaj: 0.00 0.00
transport: 0.00 0.00
1.4 CF37A+ Corectarea suprafetelor de beton cu mp 40.00 69.86 2,794.56
mortare speciale(grosime medie material: 57.96 2,318.40
0,50cm)
manopera: 11.90 476.16
utilaj: 0.00 0.00
transport: 0.00 0.00
1.5 IzAco06A Protectie anticoroziva a betonului din mp 3,360.00 85.94 288,754.70
suprastructura material: 65.70 220,759.06
manopera: 20.24 67,995.65
utilaj: 0.00 0.00
transport: 0.00 0.00
2 CALE TROTUAR PARAPET
2.1 DB12C% Strat de uzura din mixtura asfaltica mp 620.00 57.27 35,507.40
stabilizata – MAS– cu grosimea de 4 material: 44.82 27,790.38
cm
manopera: 5.36 3,321.22
utilaj: 7.09 4,395.80
transport: 0.00 0.00
2.2 IFA07A1 Dispozitive de acoperire a rosturilor de m 23.00 78.04 1,794.89
dilatare material: 76.61 1,762.03
manopera: 1.43 32.86
utilaj: 0.00 0.00
transport: 0.00 0.00
2.3 DE08XC ASIMILAT Borduri de granit 20x25 m 260.00 371.57 96,607.16
material: 340.72 88,588.24
manopera: 28.00 7,280.00
utilaj: 2.84 738.92
transport: 0.00 0.00
2.4 SR14a Reabilitare parapet pietonal existent m 170.00 0.00 0.00
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
2.5 SR14b Reabilitare parapete Directional m 159.00 0.00 0.00
existent material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
2.6 SR14C Reabilitare panouri protectieH=2.50m m 85.00 0.00 0.00
( curatare-vopsire) material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
3 RACORDARE CU TERASAMENTELE
Pag 17
STADIUL FIZIC: Pasaj pe DJ 101C peste A3 la km 36+700 -solutia 1-reabilitare cale
0 1 2 3 4 7 5
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: PODURI
STADIUL FIZIC: Pasaj pe DJ 101C peste A3 la km 36+700 -solutia 1-reabilitare cale
3.1 ACD26A% Curatare sfert con , etansare rosturi mp 1,000.00 84.65 84,647.38
material: 18.72 18,722.76
manopera: 65.71 65,710.00
utilaj: 0.21 214.62
transport: 0.00 0.00
procent material manopera utilaj transport total
Cheltuieli directe: 359,940.87 148,525.38 5,349.34 0.00 513,815.59
Recapitulatia: 4/4 Recap 2019: CAM 2,25
Alte cheltuieli directe:
Contributie 2.2500 % 0.00 3,341.82 0.00 0.00 3,341.82
asiguratorie pentru
munca (CAM)
Total inclusiv Cheltuieli 359,940.87 151,867.20 5,349.34 0.00 517,157.41
directe:
Cheltuieli indirecte 4.0000 % 14,397.63 6,074.69 213.97 0.00 20,686.30
Total inclusiv Cheltuieli 374,338.50 157,941.89 5,563.31 0.00 537,843.70
indirecte:
Profit 4.0000 % 14,973.54 6,317.68 222.53 0.00 21,513.75
Total inclusiv Beneficiu: 389,312.04 164,259.56 5,785.85 0.00 559,357.45
TOTAL GENERAL (fara TVA): 559,357.45
TVA: 19.00% 106,277.92
TOTAL GENERAL: 665,635.37
OBIECTUL: ILUMINAT
STADIUL FIZIC: Deviz
1 W2F02A# Corp de iluminat public montat cu buc 190.00 102.79 19,530.48
autotelescop pe stalp din otel, ridicat pe material: 0.00 0.00
pozitie - montare
manopera: 28.39 5,394.48
utilaj: 74.40 14,136.00
transport: 0.00 0.00
2 5104001 corp LED stradal max.50W + buc 37.00 402.15 14,879.55
unit.cda /b material: 402.15 14,879.55
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
3 5104034 corp LED stradal max.60W + buc 40.00 520.10 20,804.00
unit.cda /b material: 520.10 20,804.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
4 5104035 corp LED stradal max.70W + buc 16.00 550.29 8,804.64
unit.cda /b material: 550.29 8,804.64
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
5 5104036 corp LED stradal max.150W + buc 76.00 536.20 40,751.20
unit.cda /b material: 536.20 40,751.20
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
Pag 18
STADIUL FIZIC: Deviz
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: ILUMINAT
STADIUL FIZIC: Deviz
6 5104038 corp LED stradal max.170W + buc 21.00 615.18 12,918.78
unit.cda /b material: 615.18 12,918.78
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
7 TCC10XA Unitate senzori de comanda (trafic, buc 15.00 5,569.46 83,541.87
lumina) - procurare si montare material: 109.46 1,641.87
manopera: 5,460.00 81,900.00
utilaj: 0.00 0.00
transport: 0.00 0.00
procent material manopera utilaj transport total
Cheltuieli directe: 99,800.04 87,294.48 14,136.00 0.00 201,230.52
Recapitulatia: 4/4 Recap 2019: CAM 2,25
Alte cheltuieli directe:
Contributie 2.2500 % 0.00 1,964.13 0.00 0.00 1,964.13
asiguratorie pentru
munca (CAM)
Total inclusiv Cheltuieli 99,800.04 89,258.61 14,136.00 0.00 203,194.65
directe:
Cheltuieli indirecte 4.0000 % 3,992.00 3,570.34 565.44 0.00 8,127.79
Total inclusiv Cheltuieli 103,792.04 92,828.95 14,701.44 0.00 211,322.43
indirecte:
Profit 4.0000 % 4,151.68 3,713.16 588.06 0.00 8,452.90
Total inclusiv Beneficiu: 107,943.72 96,542.11 15,289.50 0.00 219,775.33
TOTAL GENERAL (fara TVA): 219,775.33
TVA: 19.00% 41,757.31
TOTAL GENERAL: 261,532.64
OBIECTUL: APA
STADIUL FIZIC: Retea apa l sant=0.8m; hsant=1.5m; L=393m
1 Retea apa l sant=0.8m; hsant=1.5m; L=393m
1.1 TSE05C1 Nivelarea cu autogreder de pana la 175 100 23.58 112.32 2,648.51
CP a suprafetei terenului natural si a mp material: 0.00 0.00
platformelor de terasamente,prin
manopera: 0.00 0.00
taierea damburilor si deplasarea in
goluri a pamantului sapat in:...teren utilaj: 112.32 2,648.51
catg.3 transport: 0.00 0.00
1.2 TSC02D1 Sapatura mecanica cu excavator pe 100 471.60 1,750.00 825,300.00
pneuri de 0.21-0.39 mc,cu comanda mc material: 0.00 0.00
hidraulica,in :...pamant cu umiditate
manopera: 0.00 0.00
naturala descarcare auto in teren catg
2 utilaj: 1,750.00 825,300.00
transport: 0.00 0.00
1.3 TSA04F1 Sapatura manuala de pamant in spatii mc 94.32 137.80 12,996.85
limitate,avand sub 1 m latime si material: 6.26 590.07
maximum 4.50 m adancime,executata
manopera: 131.54 12,406.78
cu sprijiniri,cu evacuare manuala,la
fundatii,canale,drumuri etc...in pamant utilaj: 0.00 0.00
cu umiditate naturala adancimea transport: 0.00 0.00
sapaturii 1,5-
1.4 TSF02C1 S prijiniri de maluri,cu dulapi de fag mp 1,179.00 42.15 49,689.03
asezati orizontal,la sapaturi executate material: 18.34 21,619.40
in spatii limitate,avand latimea de 1.51-
manopera: 23.81 28,069.63
2.50 m intre maluri...adancimea
sapaturii de2.01-2 m interspatii intre utilaj: 0.00 0.00
dulapi de 0.00-20 m transport: 0.00 0.00
Pag 19
STADIUL FIZIC: Retea apa l sant=0.8m; hsant=1.5m; L=393m
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: APA
STADIUL FIZIC: Retea apa l sant=0.8m; hsant=1.5m; L=393m
1.5 TRA01A30 Transportul rutier tona 441.00 30.00 13,230.00
al...materialelor,semifabricatelor cu material: 0.00 0.00
autobasculanta pe dist.= 30 km.
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 30.00 13,230.00
1.6 TRA02A50 Transportul rutier al tona 0.50 52.00 26.00
materialelor,semifabricatelor cu material: 0.00 0.00
autocamionul pe dist.= ...50 km.
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 52.00 26.00
1.7 ACF11E% Spalarea conductelor de apa potabila m 61.00 18.58 1,133.43
dupa montare si imbinare, inaintea material: 0.80 48.80
receptiei pentru tevi din PVC, fonta,
manopera: 2.38 145.23
azbociment, polietilena, etc 125mm
utilaj: 15.40 939.40
transport: 0.00 0.00
1.8 ACF11E% Spalarea conductelor de apa potabila m 332.00 18.58 6,168.83
dupa montare si imbinare, inaintea material: 0.80 265.60
receptiei pentru tevi din PVC, fonta,
manopera: 2.38 790.43
azbociment, polietilena, etc 180 mm
utilaj: 15.40 5,112.80
transport: 0.00 0.00
1.9 ACF03A% Umpluturi in santuri la conductele de mc 116.79 79.65 9,302.74
alimentare cu apa sau canalizare, ca material: 61.50 7,182.59
substrat, strat de protectie, strat de
manopera: 18.15 2,120.16
izolare sau strat filtrant la tuburile de
drenaj, executate cu: nisip utilaj: 0.00 0.00
transport: 0.00 0.00
1.10 TSD04B1 Compactarea cu maiul de mana a mc 281.61 22.72 6,398.18
umpluturilor executate in sapaturi material: 0.40 112.64
orizontale sau inclinate la 1/4,inclusiv
manopera: 22.32 6,285.54
udarea fiecarui strat de pamant in
parte,avand :...10 cm grosime pamant utilaj: 0.00 0.00
i transport: 0.00 0.00
1.11 TSD01C1 Imprastierea cu lopata a pamant. mc 281.61 12.80 3,603.71
afinat,strat uniform 10-30cm. gros cu material: 0.00 0.00
sfarim. bulg. teren...pamant coeziv
manopera: 12.80 3,603.71
utilaj: 0.00 0.00
transport: 0.00 0.00
1.12 ACA11C% Montarea in pamant a tevilor din m 61.00 285.68 17,426.30
polietilena de presiune, de inalta material: 44.12 2,691.09
densitate, densitate alimentarilor cu
manopera: 39.58 2,414.43
apa, asamblate prin metoda de sudare
mecanica, cu manson de polietilena, cu utilaj: 201.98 12,320.78
flanse, conform normativului I-6-PE, transport: 0.00 0.00
1.13 ACA11D% Montarea in pamant a tevilor din m 332.00 339.41 112,683.39
polietilena de presiune, de inalta material: 77.35 25,679.47
densitate, densitate alimentarilor cu
manopera: 52.08 17,290.56
apa, asamblate prin metoda de sudare
mecanica, cu manson de polietilena, cu utilaj: 209.98 69,713.36
flanse, conform normativului I-6-PE, transport: 0.00 0.00
1.14 DF26A1 Montare banda avertizoare cu 2 fire m 393.00 10.39 4,084.31
cupru de 1kV pe tot traseul conductei material: 9.50 3,733.44
manopera: 0.89 350.87
utilaj: 0.00 0.00
transport: 0.00 0.00
Pag 20
STADIUL FIZIC: Retea apa l sant=0.8m; hsant=1.5m; L=393m
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: APA
STADIUL FIZIC: Retea apa l sant=0.8m; hsant=1.5m; L=393m
1.15 DA06B1 STRAT AGREG NAT CILINDRATE CU MC 62.88 102.20 6,426.55
[ 8] FUNC REZIST FILTRANTIZOLAT material: 62.00 3,898.56
AERISIRE SI ANTICAP CU ASTER
manopera: 10.97 690.01
MEC BALAST
utilaj: 29.23 1,837.98
transport: 0.00 0.00
1.16 TSA24A1 Epuizarea mecanica a apelor din ora 16.00 112.00 1,792.00
sapaturi,in teren cu infiltratii puternice material: 0.00 0.00
de apa,executate cu:...motopompa de
manopera: 0.00 0.00
apa 6.6-12 Kw (9-16 CP)
utilaj: 112.00 1,792.00
transport: 0.00 0.00
1.17 ACF06A% Sustineri din lemn, pentru cabluri sau m 40.00 118.81 4,752.21
conducte in functiune, intalnite in material: 57.80 2,311.89
sapatura, de categoria: grele
manopera: 53.57 2,142.72
utilaj: 7.44 297.60
transport: 0.00 0.00
1.18 ACA37B% Inchiderea capetelor la conductele din buc 2.00 56.51 113.03
PVC sau poliesteri, pentru efectuarea material: 13.66 27.32
probei de etanseitate la presiune,
manopera: 42.85 85.71
avand diametrul de: 125-170mm
utilaj: 0.00 0.00
transport: 0.00 0.00
1.19 ACA37C% Inchiderea capetelor la conductele din buc 4.00 70.98 283.91
PVC sau poliesteri, pentru efectuarea material: 16.81 67.26
probei de etanseitate la presiune,
manopera: 54.16 216.65
avand diametrul de: 180mm
utilaj: 0.00 0.00
transport: 0.00 0.00
1.20 GA08C% Tub de...protectie, din teava de otel m 61.00 970.54 59,202.91
montat in sant la trav. de drumuri material: 707.03 43,128.77
pentru protectia conductei, tubul avand
manopera: 80.65 4,919.63
dn=324x8 mm
utilaj: 182.86 11,154.51
transport: 0.00 0.00
1.21 GD19D% Imbinarea ...prin sudura de tip buc 4.00 746.52 2,986.08
electrofuziune intre teava si fiting material: 389.62 1,558.48
(mufa, teu, cot) din polietilena avand
manopera: 37.20 148.80
dn 125 mm
utilaj: 319.70 1,278.80
transport: 0.00 0.00
1.22 GD19F% Imbinarea ...prin sudura de tip buc 11.00 851.26 9,363.86
electrofuziune intre teava si fiting material: 389.62 4,285.82
(mufa, teu, cot) din polietilena avand
manopera: 44.64 491.04
dn 180 mm
utilaj: 417.00 4,587.00
transport: 0.00 0.00
1.23 IZL06C Izolare anticoroziva executata manual mp 62.04 171.21 10,622.01
pe traseu, la tevi de otel cu protectie material: 149.80 9,293.65
exterioara din banda PVC, izolatia
manopera: 19.94 1,237.03
fiind...foarte intarita
utilaj: 1.47 91.34
transport: 0.00 0.00
1.24 IZL04C Protejare cu inele distantiere a izolatiei m 128.00 321.66 41,172.56
tevii otel + burduf. Capete la material: 288.44 36,920.45
subtraversari de drum si cf
manopera: 13.69 1,752.27
utilaj: 19.53 2,499.84
transport: 0.00 0.00
Pag 21
STADIUL FIZIC: Retea apa l sant=0.8m; hsant=1.5m; L=393m
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: APA
STADIUL FIZIC: Retea apa l sant=0.8m; hsant=1.5m; L=393m
1.25 Inele distantiere din PVC tip usor buc 122.00 25.76 3,142.72
Dn180mm material: 25.76 3,142.72
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
1.26 Burduf etansare si coliere de fixare buc 6.00 55.53 333.18
Dn180mm material: 55.53 333.18
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
1.27 GC06D% Proba de presiune hidraulica a trons. buc 0.06 468.55 28.11
de cond. care traverseaza drumuri, cai material: 5.14 0.31
ferate sau...alte obstacole dn= 125
manopera: 222.60 13.36
mm
utilaj: 240.80 14.45
transport: 0.00 0.00
1.28 GC06F% Proba de presiune hidraulica a trons. buc 0.33 763.54 251.97
de cond. care traverseaza drumuri, cai material: 12.62 4.17
ferate sau...alte obstacole dn= 200
manopera: 419.62 138.47
mm
utilaj: 331.30 109.33
transport: 0.00 0.00
2 Anod si priza de potential
2.1 M1K12C1 Priza potential pentru masurarea buc 3.00 1,082.65 3,247.96
param. electr. protectiacontra material: 483.84 1,451.53
coroziunii conduc. ingrop. tip...3 afara
manopera: 548.48 1,645.43
loc
utilaj: 50.34 151.01
transport: 0.00 0.00
2.2 M1K18A1 Anod activ supl. traseu pentru legarea buc 9.00 633.86 5,704.71
la pamant cu anod de...zinc material: 213.43 1,920.84
manopera: 405.33 3,647.96
utilaj: 15.10 135.90
transport: 0.00 0.00
2.3 W2G05A# Cablu de energie electrica armat, cu m 32.40 269.23 8,723.14
conductoare din cupru de 1KV, pozat în material: 267.89 8,679.75
sant pe pat de nisip, cu tractiune
manopera: 1.34 43.39
manuala...sectiunea pâna la 4x16
mmp, fara obstacole sau cu greutatea utilaj: 0.00 0.00
specifica transport: 0.00 0.00
2.4 DF26A1 Marcaj longitudinal cu banda din m 27.00 12.11 326.85
material termoplastic reflectorizant; material: 9.50 256.50
manopera: 1.79 48.21
utilaj: 0.82 22.14
transport: 0.00 0.00
2.5 ACF03A% Umpluturi in santuri la conductele de mc 2.10 79.65 167.27
alimentare cu apa sau canalizare, ca material: 61.50 129.15
substrat, strat de protectie, strat de
manopera: 18.15 38.12
izolare sau strat filtrant la tuburile de
drenaj, executate cu: nisip utilaj: 0.00 0.00
transport: 0.00 0.00
Pag 22
STADIUL FIZIC: Retea apa l sant=0.8m; hsant=1.5m; L=393m
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: APA
STADIUL FIZIC: Retea apa l sant=0.8m; hsant=1.5m; L=393m
2.6 TSC02D1 Sapatura mecanica cu excavator pe 100 0.18 1,750.00 315.00
pneuri de 0.21-0.39 mc,cu comanda mc material: 0.00 0.00
hidraulica,in :...pamant cu umiditate
manopera: 0.00 0.00
naturala descarcare auto in teren catg
2 utilaj: 1,750.00 315.00
transport: 0.00 0.00
2.7 TSF02C1 Sprijiniri de maluri,cu dulapi de fag mp 8.40 42.15 354.02
asezati orizontal,la sapaturi executate material: 18.34 154.03
in spatii limitate,avand latimea de 1.51-
manopera: 23.81 199.99
2.50 m intre maluri...adancimea
sapaturii de2.01-2 m interspatii intre utilaj: 0.00 0.00
dulapi de 0.00-20 m transport: 0.00 0.00
2.8 TSD01C1 Imprastierea cu lopata a pamant. mc 9.60 12.80 122.85
afinat,strat uniform 10-30cm. gros cu material: 0.00 0.00
sfarim. bulg. teren...pamant coeziv
manopera: 12.80 122.85
utilaj: 0.00 0.00
transport: 0.00 0.00
2.9 TRA01A30 Transportul rutier tona 18.90 30.00 567.00
al...materialelor,semifabricatelor cu material: 0.00 0.00
autobasculanta pe dist.= 30 km.
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 30.00 567.00
3 Dezafectari L retea dezafectata =340m
3.1 TSC02D1 Sapatura mecanica cu excavator pe 100 4.08 1,750.00 7,140.00
pneuri de 0.21-0.39 mc,cu comanda mc material: 0.00 0.00
hidraulica,in :...pamant cu umiditate
manopera: 0.00 0.00
naturala descarcare auto in teren catg
2 utilaj: 1,750.00 7,140.00
transport: 0.00 0.00
3.2 TSA04F1 Sapatura manuala de pamant in spatii mc 81.60 137.80 11,244.09
limitate,avand sub 1 m latime si material: 6.26 510.50
maximum 4.50 m adancime,executata
manopera: 131.54 10,733.60
cu sprijiniri,cu evacuare manuala,la
fundatii,canale,drumuri etc...in pamant utilaj: 0.00 0.00
cu umiditate naturala adancimea transport: 0.00 0.00
sapaturii 1,5-
3.3 RPACA52B D emontarea conductelor de apa din m 284.00 46.75 13,278.25
# OL avand diametrul de 180mm material: 1.43 406.01
manopera: 29.16 8,282.80
utilaj: 16.16 4,589.44
transport: 0.00 0.00
3.4 RPACA52A Demontarea conductelor de apa din OL m 56.00 31.97 1,790.26
# avand diametrul de 125mm material: 1.04 58.07
manopera: 20.83 1,166.59
utilaj: 10.10 565.60
transport: 0.00 0.00
3.5 TSD04B1 Compactarea cu maiul de mana a mc 408.00 22.72 9,269.76
umpluturilor executate in sapaturi material: 0.40 163.20
orizontale sau inclinate la 1/4,inclusiv
manopera: 22.32 9,106.56
udarea fiecarui strat de pamant in
parte,avand :...10 cm grosime pamant utilaj: 0.00 0.00
i transport: 0.00 0.00
Pag 23
STADIUL FIZIC: Retea apa l sant=0.8m; hsant=1.5m; L=393m
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: APA
STADIUL FIZIC: Retea apa l sant=0.8m; hsant=1.5m; L=393m
3.6 TSD01C1 Imprastierea cu lopata a pamant. mc 408.00 12.80 5,221.09
afinat,strat uniform 10-30cm. gros cu material: 0.00 0.00
sfarim. bulg. teren...pamant coeziv
manopera: 12.80 5,221.09
utilaj: 0.00 0.00
transport: 0.00 0.00
3.7 DA06B1 STRAT AGREG NAT CILINDRATE CU MC 54.40 102.20 5,559.87
[ 8] FUNC REZIST FILTRANTIZOLAT material: 62.00 3,372.80
AERISIRE SI ANTICAP CU ASTER
manopera: 10.97 596.95
MEC BALAST
utilaj: 29.23 1,590.11
transport: 0.00 0.00
procent material manopera utilaj transport total
Cheltuieli directe: 183,998.03 126,166.55 954,206.89 13,823.00 1,278,194.47
Recapitulatia: 4/4 Recap 2019: CAM 2,25
Alte cheltuieli directe:
Contributie 2.2500 % 0.00 2,838.75 0.00 0.00 2,838.75
asiguratorie pentru
munca (CAM)
Total inclusiv Cheltuieli 183,998.03 129,005.30 954,206.89 13,823.00 1,281,033.22
directe:
Cheltuieli indirecte 4.0000 % 7,359.92 5,160.21 38,168.28 552.92 51,241.33
Total inclusiv Cheltuieli 191,357.95 134,165.51 992,375.17 14,375.92 1,332,274.55
indirecte:
Profit 4.0000 % 7,654.32 5,366.62 39,695.01 575.04 53,290.98
Total inclusiv Beneficiu: 199,012.26 139,532.13 1,032,070.17 14,950.96 1,385,565.53
TOTAL GENERAL (fara TVA): 1,385,565.53
TVA: 19.00% 263,257.45
TOTAL GENERAL: 1,648,822.98
OBIECTUL: Retele distributie gaze naturale
STADIUL FIZIC: Retele distributie gaze naturale l=0.8m; h=1.5m;
1 TSG02A1 Curatarea terenului...de iarba si 100 5.80 97.91 567.88
buruieni mp material: 0.00 0.00
manopera: 97.91 567.88
utilaj: 0.00 0.00
transport: 0.00 0.00
2 RPCT09H1 Demolarea elementelor de beton mc 1.00 255.85 255.85
simplu si beton armat cu material: 0.00 0.00
mijloace ...mecanica si manuala a
manopera: 206.24 206.24
elementelor de constructii din beton
simplu si armat, în vederea modificarii utilaj: 49.62 49.62
racordarilor, executate cu deosebita transport: 0.00 0.00
grija pentru a nu se produce
3 MDTC4641 Trans port utilaj...100km-65123003- buc 1.00 3,000.00 3,000.00
100 automacara 0,045-0,059mn,h. max. material: 0.00 0.00
6,5m,des. max. 5,5m,moment max.
manopera: 0.00 0.00
15tfm
utilaj: 3,000.00 3,000.00
transport: 0.00 0.00
4 AUT1233 Ora pr. automacara cu brat zabrele 4,5- ora 24.00 280.00 6,720.00
5,8 tf 2 schimburi material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 280.00 6,720.00
transport: 0.00 0.00
Pag 24
STADIUL FIZIC: Retele distributie gaze naturale l=0.8m; h=1.5m;
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: Retele distributie gaze naturale
STADIUL FIZIC: Retele distributie gaze naturale l=0.8m; h=1.5m;
5 TSC02D1 Sapatura mecanica cu excavator pe 100 3.48 1,750.00 6,090.00
pneuri de 0.21-0.39 mc,cu comanda mc material: 0.00 0.00
hidraulica,in :...pamant cu umiditate
manopera: 0.00 0.00
naturala descarcare auto in teren catg
2 utilaj: 1,750.00 6,090.00
transport: 0.00 0.00
6 TSA04F1 Sapatura manuala de pamant in spatii mc 69.60 137.80 9,590.55
limitate,avand sub 1 m latime si material: 6.26 435.42
maximum 4.50 m adancime,executata
manopera: 131.54 9,155.13
cu sprijiniri,cu evacuare manuala,la
fundatii,canale,drumuri etc...in pamant utilaj: 0.00 0.00
cu umiditate naturala adancimea transport: 0.00 0.00
sapaturii 1,5-
7 TRA01A30 T ransportul rutier tona 318.00 30.00 9,540.00
al...materialelor,semifabricatelor cu material: 0.00 0.00
autobasculanta pe dist.= 30 km.
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 30.00 9,540.00
8 GD09B% Drenaj pentru conducte de distributie mc 83.52 76.39 6,380.26
din...polietilena material: 63.00 5,261.76
manopera: 13.39 1,118.50
utilaj: 0.00 0.00
transport: 0.00 0.00
9 TSD04B1 Compactarea cu maiul de mana a mc 264.48 22.72 6,008.99
umpluturilor executate in sapaturi material: 0.40 105.79
orizontale sau inclinate la 1/4,inclusiv
manopera: 22.32 5,903.19
udarea fiecarui strat de pamant in
parte,avand :...10 cm grosime pamant utilaj: 0.00 0.00
transport: 0.00 0.00
10 TSD01C1 Imprais tierea cu lopata a pamant. mc 264.48 12.80 3,384.50
afinat,strat uniform 10-30cm. gros cu material: 0.00 0.00
sfarim. bulg. teren...pamant coeziv
manopera: 12.80 3,384.50
utilaj: 0.00 0.00
transport: 0.00 0.00
11 GD17F% Teava din polietilena pentru...conducte m 290.00 153.74 44,585.08
de distributie montata in sant material: 62.80 18,211.49
dn=160mm
manopera: 18.87 5,471.67
utilaj: 72.08 20,901.91
transport: 0.00 0.00
12 DA06B1 STRAT AGREG NAT CILINDRATE CU MC 46.60 102.20 4,762.68
[ 8] FUNC REZIST FILTRANTIZOLAT material: 62.00 2,889.20
AERISIRE SI ANTICAP CU ASTER
manopera: 10.97 511.36
MEC BALAST
utilaj: 29.23 1,362.12
transport: 0.00 0.00
13 TSA24A1 Epuizarea mecanica a apelor din ora 16.00 112.00 1,792.00
sapaturi,in teren cu infiltratii puternice material: 0.00 0.00
de apa,executate cu:...motopompa de
manopera: 0.00 0.00
apa 6.6-12 Kw (9-16 CP)
utilaj: 112.00 1,792.00
transport: 0.00 0.00
Pag 25
STADIUL FIZIC: Retele distributie gaze naturale l=0.8m; h=1.5m;
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: Retele distributie gaze naturale
STADIUL FIZIC: Retele distributie gaze naturale l=0.8m; h=1.5m;
14 GD08A1% Rasuflatoare fara capac de buc 22.00 59.52 1,309.44
control...dn=1 - 2 toli - montare material: 0.00 0.00
manopera: 59.52 1,309.44
utilaj: 0.00 0.00
transport: 0.00 0.00
15 GC01E% Proba preliminara pentru...contr. km 0.29 1,375.86 399.00
etanseitatii imbinarilor, executate cu aer material: 21.95 6.37
la pn5, la conducte avand dn 160 mm
manopera: 585.97 169.93
utilaj: 767.93 222.70
transport: 0.00 0.00
16 GC05E% Proba de rezistenta si...regim pentru km 0.29 2,984.18 865.41
contr. etanseitatii imbinarilor si material: 112.33 32.58
armaturilor executate hidraulic dn=
manopera: 1,475.80 427.98
160 mm
utilaj: 1,396.05 404.85
transport: 0.00 0.00
17 GC04E1 Montarea control si Demontare echip la buc 4.00 4,080.05 16,320.21
proba de rezist si regim la cond ce se material: 208.20 832.81
prob cu aer cu dn 160 mm
manopera: 2,365.92 9,463.68
utilaj: 1,505.93 6,023.72
transport: 0.00 0.00
18 GA08C% Tub de...protectie, din teava de otel m 25.00 970.54 24,263.49
montat in sant la trav. de drumuri material: 707.03 17,675.73
pentru protectia conductei, tubul avand
manopera: 80.65 2,016.24
dn=324x8 mm
utilaj: 182.86 4,571.52
transport: 0.00 0.00
19 GD19E% Imbinarea ...prin sudura de tip buc 19.00 737.77 14,017.63
electrofuziune intre teava si fiting material: 379.38 7,208.26
(mufa, teu, cot) din polietilena avand
manopera: 38.69 735.07
dn 160 mm
utilaj: 319.70 6,074.30
transport: 0.00 0.00
20 M1K12C1 Priza potential pentru masurarea buc 1.00 858.95 858.95
param. electr. protectiacontra material: 260.14 260.14
coroziunii conduc. ingrop. tip...3 afara
manopera: 548.48 548.48
loc
utilaj: 50.34 50.34
transport: 0.00 0.00
21 M1K18A1 Anod activ supl. traseu pentru legarea buc 3.00 633.86 1,901.57
la pamant cu anod de...zinc material: 213.43 640.28
manopera: 405.33 1,215.99
utilaj: 15.10 45.30
transport: 0.00 0.00
22 W2G05A# Cablu de energie electrica armat, cu m 10.80 270.16 2,917.68
conductoare din cupru de 1KV, pozat în material: 268.82 2,903.22
sant pe pat de nisip, cu tractiune
manopera: 1.34 14.46
manuala...sectiunea pâna la 4x16
mmp, fara obstacole sau cu greutatea utilaj: 0.00 0.00
specifica â l 1 4k / transport: 0.00 0.00
23 DF26A1 Marcaj longitudinal cu banda din m 9.00 12.11 108.95
material termoplastic reflectorizant; material: 9.50 85.50
manopera: 1.79 16.07
utilaj: 0.82 7.38
transport: 0.00 0.00
Pag 26
STADIUL FIZIC: Retele distributie gaze naturale l=0.8m; h=1.5m;
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: Retele distributie gaze naturale
STADIUL FIZIC: Retele distributie gaze naturale l=0.8m; h=1.5m;
24 ACF03A% Umpluturi in santuri la conductele de mc 0.70 79.65 55.76
alimentare cu apa sau canalizare, ca material: 61.50 43.05
substrat, strat de protectie, strat de
manopera: 18.15 12.71
izolare sau strat filtrant la tuburile de
drenaj, executate cu: nisip utilaj: 0.00 0.00
transport: 0.00 0.00
25 TSF02C1 Sprijiniri de maluri,cu dulapi de fag mp 28.80 42.15 1,213.78
asezati orizontal,la sapaturi executate material: 18.34 528.11
in spatii limitate,avand latimea de 1.51-
manopera: 23.81 685.67
2.50 m intre maluri...adancimea
sapaturii de2.01- 2 m interspatii intre utilaj: 0.00 0.00
dulapi de 0.00-20 m transport: 0.00 0.00
26 TSD01C1 Imprastierea cu lopata a pamant. mc 3.20 12.80 40.95
afinat,strat uniform 10-30cm. gros cu material: 0.00 0.00
sfarim. bulg. teren...pamant coeziv
manopera: 12.80 40.95
utilaj: 0.00 0.00
transport: 0.00 0.00
27 TRA01A30 Transportul rutier tona 6.30 30.00 189.00
al...materialelor,semifabricatelor cu material: 0.00 0.00
autobasculanta pe dist.= 30 km.
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 30.00 189.00
28 TSC02D1 Sapatura mecanica cu excavator pe 100 3.07 1,750.00 5,372.50
pneuri de 0.21-0.39 mc,cu comanda mc material: 0.00 0.00
hidraulica,in :...pamant cu umiditate
manopera: 0.00 0.00
naturala descarcare auto in teren catg
2 utilaj: 1,750.00 5,372.50
transport: 0.00 0.00
29 TSA04F1 Sapatura manuala de pamant in spatii mc 61.44 137.80 8,466.14
limitate,avand sub 1 m latime si material: 6.26 384.37
maximum 4.50 m adancime,executata
manopera: 131.54 8,081.77
cu sprijiniri,cu evacuare manuala,la
fundatii,canale,drumuri etc...in pamant utilaj: 0.00 0.00
cu umiditate naturala adancimea transport: 0.00 0.00
sapaturii 1 5
30 RpAcA58B umiditate naturala adancimea sapaturii buc 256.00 27.38 7,009.08
% 1 5- Demontarea conductelor de apa material: 0.00 0.00
din PEHD avand diametrul de Dn
manopera: 27.38 7,009.08
160mm
utilaj: 0.00 0.00
transport: 0.00 0.00
31 TSD04B1 Compactarea cu maiul de mana a mc 307.20 22.72 6,979.58
umpluturilor executate in sapaturi material: 0.40 122.88
orizontale sau inclinate la 1/4,inclusiv
manopera: 22.32 6,856.70
udarea fiecarui strat de pamant in
parte,avand :...10 cm grosime pamant utilaj: 0.00 0.00
coeziv transport: 0.00 0.00
32 TSD01C1 Imprastierea cu lopata a pamant. mc 307.20 12.80 3,931.18
afinat,strat uniform 10-30cm. gros cu material: 0.00 0.00
sfarim. bulg. teren...pamant coeziv
manopera: 12.80 3,931.18
utilaj: 0.00 0.00
transport: 0.00 0.00
Pag 27
STADIUL FIZIC: Retele distributie gaze naturale l=0.8m; h=1.5m;
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: Retele distributie gaze naturale
STADIUL FIZIC: Retele distributie gaze naturale l=0.8m; h=1.5m;
33 DA06B1 STRAT AGREG NAT CILINDRATE CU MC 40.96 102.20 4,186.25
[ 8] FUNC REZIST FILTRANTIZOLAT material: 62.00 2,539.52
AERISIRE SI ANTICAP CU ASTER
manopera: 10.97 449.47
MEC BALAST
utilaj: 29.23 1,197.26
transport: 0.00 0.00
procent material manopera utilaj transport total
Cheltuieli directe: 60,166.47 69,303.34 63,885.51 9,729.00 203,084.32
Recapitulatia: 4/4 Recap 2019: CAM 2,25
Alte cheltuieli directe:
Contributie 2.2500 % 0.00 1,559.33 0.00 0.00 1,559.33
asiguratorie pentru
munca (CAM)
Total inclusiv Cheltuieli 60,166.47 70,862.66 63,885.51 9,729.00 204,643.64
directe:
Cheltuieli indirecte 4.0000 % 2,406.66 2,834.51 2,555.42 389.16 8,185.75
Total inclusiv Cheltuieli 62,573.13 73,697.17 66,440.94 10,118.16 212,829.39
indirecte:
Profit 4.0000 % 2,502.93 2,947.89 2,657.64 404.73 8,513.18
Total inclusiv Beneficiu: 65,076.05 76,645.05 69,098.57 10,522.89 221,342.56
TOTAL GENERAL (fara TVA): 221,342.56
TVA: 19.00% 42,055.09
TOTAL GENERAL: 263,397.65
OBIECTUL: RELOCARE/PROTEJARE RETEA TELECOMUNICATII
STADIUL FIZIC: SC ORANGE ROMANIA COMMUNICATIONS SA
1 TCA02A1 Lucrari de constructie, executate la mc 881.68 174.03 153,437.50
canalizatie cu tevi sau tuburi...sant material: 3.15 2,777.08
pentru instalatie tevi direct în pamânt-
manopera: 156.54 138,016.07
fara strate de nisip
utilaj: 14.34 12,644.35
transport: 0.00 0.00
2 20014199 Teava PN 10 bari 40 mm m 3,560.00 10.00 35,600.00
material: 10.00 35,600.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
3 3251545 TEAVA OL OTEL CAP FILET 114X5 m 36.00 173.45 6,244.20
OLT 65 STAS 715/1 material: 173.45 6,244.20
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
4 TCA03B1 Instalarea tevilor sau tuburilor în sant m 3,596.00 9.70 34,872.05
sau prin forare...de material plastic dn. material: 2.56 9,187.98
. **)montate in sant existent
manopera: 7.14 25,684.07
utilaj: 0.00 0.00
transport: 0.00 0.00
5 DF26A1 Marcaj longitudinal cu banda din m 1,816.00 12.11 21,983.50
material termoplastic reflectorizant; material: 9.50 17,251.73
manopera: 1.79 3,242.65
utilaj: 0.82 1,489.12
transport: 0.00 0.00
Pag 28
STADIUL FIZIC: SC ORANGE ROMANIA COMMUNICATIONS SA
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: RELOCARE/PROTEJARE RETEA TELECOMUNICATII
STADIUL FIZIC: SC ORANGE ROMANIA COMMUNICATIONS SA
6 TCA03C1 Instalarea tevilor sau tuburilor în sant m 67.00 244.71 16,395.64
sau prin forare...forare orizontala material: 4.17 279.51
manopera: 131.54 8,813.13
utilaj: 109.00 7,303.00
transport: 0.00 0.00
7 20014115 Teava PN 10 Bari 110mm m 67.00 51.00 3,417.00
material: 51.00 3,417.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
8 TCA14A1 Instalarea cablurilor de km 0.21 9,941.06 2,087.62
telecomunicatii...in conducte avand material: 9,809.52 2,060.00
greutatea pâna la 2,6 kg/m(manual)
manopera: 131.54 27.62
utilaj: 0.00 0.00
transport: 0.00 0.00
9 TCA14A1 Instalarea cablurilor de km 2.00 9,754.86 19,509.72
telecomunicatii...in conducte avand material: 1,089.05 2,178.10
greutatea pâna la 2,6 kg/m(manual)
manopera: 8,665.81 17,331.63
utilaj: 0.00 0.00
transport: 0.00 0.00
10 8000009 Fibra optica 48 km 2.00 7,400.00 14,800.00
material: 7,400.00 14,800.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
11 TCA14A2 Instalarea cablurilor de km 0.79 3,466.44 2,738.49
telecomunicatii...in conducte avand material: 0.00 0.00
greutatea pâna la 2,6 kg/m demontare
manopera: 3,466.44 2,738.49
utilaj: 0.00 0.00
transport: 0.00 0.00
12 TCA14U2 Instalarea cablurilor de km 0.04 1,638.59 65.54
telecomunicatii...pe stalpi cu cablu material: 0.00 0.00
autopurtat demontare
manopera: 1,638.59 65.54
utilaj: 0.00 0.00
transport: 0.00 0.00
13 TCA04A1 Camereta din beton buc 8.00 3,754.18 30,033.43
asimilat material: 3,164.18 25,313.43
manopera: 500.00 4,000.00
utilaj: 90.00 720.00
transport: 0.00 0.00
14 7337323 Markari buc 19.00 6.95 132.05
material: 6.95 132.05
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
15 TCA16U1 Inchiderea jonctiunilor la cabluri de buc 2.00 975.80 1,951.60
telecomunicatie...protectia jonctiunilor material: 174.07 348.13
la cabluri coaxiale
manopera: 801.73 1,603.47
utilaj: 0.00 0.00
transport: 0.00 0.00
Pag 29
STADIUL FIZIC: SC ORANGE ROMANIA COMMUNICATIONS SA
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: RELOCARE/PROTEJARE RETEA TELECOMUNICATII
STADIUL FIZIC: SC ORANGE ROMANIA COMMUNICATIONS SA
16 TCA17B1 JONCTION.CONDUCT.DIN CABLE buc 96.00 350.00 33,600.00
asim FIBRA OPTICA material: 150.00 14,400.00
manopera: 200.00 19,200.00
utilaj: 0.00 0.00
transport: 0.00 0.00
17 20011110 Manson 48 FO buc 2.00 104.08 208.16
material: 104.08 208.16
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
18 SB24B1 Dop din pvc tip...u,pentru conducte de buc 28.00 7.46 208.77
canalizare,avand d= 40 mm material: 1.80 50.45
manopera: 5.65 158.32
utilaj: 0.00 0.00
transport: 0.00 0.00
19 SB24E1 Dop din pvc tip...u,pentru conducte de buc 2.00 17.02 34.05
canalizare,avand d=110mm material: 8.69 17.38
manopera: 8.33 16.67
utilaj: 0.00 0.00
transport: 0.00 0.00
20 TCA22B1 Masuratori end-to-end fibra optica buc 96.00 156.69 15,042.62
material: 88.54 8,500.19
manopera: 68.15 6,542.44
utilaj: 0.00 0.00
transport: 0.00 0.00
procent material manopera utilaj transport total
Cheltuieli directe: 142,765.37 227,440.10 22,156.47 0.00 392,361.94
Recapitulatia: 4/4 Recap 2019: CAM 2,25
Alte cheltuieli directe:
Contributie 2.2500 % 0.00 5,117.40 0.00 0.00 5,117.40
asiguratorie pentru
munca (CAM)
Total inclusiv Cheltuieli 142,765.37 232,557.50 22,156.47 0.00 397,479.34
directe:
Cheltuieli indirecte 4.0000 % 5,710.61 9,302.30 886.26 0.00 15,899.17
Total inclusiv Cheltuieli 148,475.99 241,859.80 23,042.73 0.00 413,378.52
indirecte:
Profit 4.0000 % 5,939.04 9,674.39 921.71 0.00 16,535.14
Total inclusiv Beneficiu: 154,415.03 251,534.19 23,964.44 0.00 429,913.66
TOTAL GENERAL (fara TVA): 429,913.66
TVA: 19.00% 81,683.60
TOTAL GENERAL: 511,597.26
OBIECTUL: RELOCARE/PROTEJARE RETEA TELECOMUNICATII
STADIUL FIZIC: SC RCS&RDS SA
1 TCA02A1 Lucrari de constructie, executate la mc 369.52 174.03 64,307.03
canalizatie cu tevi sau tuburi...sant material: 3.15 1,163.90
pentru instalatie tevi direct în pamânt-
manopera: 156.54 57,843.77
fara strate de nisip
utilaj: 14.34 5,299.36
transport: 0.00 0.00
Pag 30
STADIUL FIZIC: SC RCS&RDS SA
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: RELOCARE/PROTEJARE RETEA TELECOMUNICATII
STADIUL FIZIC: SC RCS&RDS SA
2 20013945 Tubeta 3x14mm m 1,438.00 79.31 114,047.78
material: 79.31 114,047.78
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
3 20014115 Teava PN 10 Bari 110mm m 30.00 51.00 1,530.00
material: 51.00 1,530.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
4 TCA03B1 Instalarea tevilor sau tuburilor în sant m 30.00 9.70 290.92
sau prin forare...de material plastic dn. material: 2.56 76.65
. **)montate in sant existent
manopera: 7.14 214.27
utilaj: 0.00 0.00
transport: 0.00 0.00
5 DF26A1 Marcaj longitudinal cu banda din m 719.00 12.11 8,703.82
material termoplastic reflectorizant; material: 9.50 6,830.39
manopera: 1.79 1,283.85
utilaj: 0.82 589.58
transport: 0.00 0.00
6 TCA03C1 Instalarea tevilor sau tuburilor în sant m 80.00 244.71 19,576.88
sau prin forare...forare orizontala material: 4.17 333.74
manopera: 131.54 10,523.14
utilaj: 109.00 8,720.00
transport: 0.00 0.00
7 20014115 Teava PN 10 Bari 110mm m 80.00 51.00 4,080.00
material: 51.00 4,080.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
8 TCA14A1 Instalarea cablurilor de km 2.00 8,665.81 17,331.63
telecomunicatii...in conducte avand material: 0.00 0.00
greutatea pâna la 2,6 kg/m(manual)
manopera: 8,665.81 17,331.63
utilaj: 0.00 0.00
transport: 0.00 0.00
9 20013945 Tubeta 3x14mm m 220.00 79.31 17,448.20
material: 79.31 17,448.20
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
10 TCA14A1 Instalarea cablurilor de km 0.89 8,665.81 7,712.57
telecomunicatii...in conducte avand material: 0.00 0.00
greutatea pâna la 2,6 kg/m(manual)
manopera: 8,665.81 7,712.57
utilaj: 0.00 0.00
transport: 0.00 0.00
11 4700014 Fibra optica 96 km 0.89 14,560.00 12,958.40
material: 14,560.00 12,958.40
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
Pag 31
STADIUL FIZIC: SC RCS&RDS SA
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: RELOCARE/PROTEJARE RETEA TELECOMUNICATII
STADIUL FIZIC: SC RCS&RDS SA
12 TCA14E1 Instalarea cablurilor de km 0.02 24,684.85 493.70
telecomunicatii...pe zid avand material: 4,995.33 99.91
greutatea pânala 1,5 kg/m
manopera: 19,689.51 393.79
utilaj: 0.00 0.00
transport: 0.00 0.00
13 TCA06D1 Stâlpi de lemn, impregnati...8 m buc 1.00 2,720.66 2,720.66
instalare material: 2,504.31 2,504.31
manopera: 216.36 216.36
utilaj: 0.00 0.00
transport: 0.00 0.00
14 TCA05C1 , Aparatoare "U" de cablu...tip 50 mm, buc 3.00 160.20 480.61
montata pe stilp de lemn material: 119.14 357.41
manopera: 41.07 123.21
utilaj: 0.00 0.00
transport: 0.00 0.00
15 TCA14U3 Instalarea cablurilor de km 0.06 7,231.32 433.88
telecomunicatii...pe stalpi de beton material: 3,152.72 189.16
cablu autopurtat pe stalp de beton
manopera: 4,078.61 244.72
utilaj: 0.00 0.00
transport: 0.00 0.00
16 TCA08A1 Ancoraj la stâlpi...partea buc 1.00 76.71 76.71
aeriana,marimea 1-2 cu sarma material: 33.86 33.86
manopera: 42.85 42.85
utilaj: 0.00 0.00
transport: 0.00 0.00
17 TCA14A2 Instalarea cablurilor de km 1.48 3,466.44 5,130.34
telecomunicatii...in conducte avand material: 0.00 0.00
greutatea pâna la 2,6 kg/m demontare
manopera: 3,466.44 5,130.34
utilaj: 0.00 0.00
transport: 0.00 0.00
18 TCA14U2 Instalarea cablurilor de km 0.26 1,638.59 426.03
telecomunicatii...pe stalpi cu cablu material: 0.00 0.00
autopurtat demontare
manopera: 1,638.59 426.03
utilaj: 0.00 0.00
transport: 0.00 0.00
19 TCA04A1 Camereta din beton buc 5.00 3,754.18 18,770.89
asimilat material: 3,164.18 15,820.89
manopera: 500.00 2,500.00
utilaj: 90.00 450.00
transport: 0.00 0.00
20 7337323 Markari buc 12.00 6.95 83.40
material: 6.95 83.40
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
21 TCA16U1 Inchiderea jonctiunilor la cabluri de buc 2.00 975.80 1,951.60
telecomunicatie...protectia jonctiunilor material: 174.07 348.13
la cabluri coaxiale
manopera: 801.73 1,603.47
utilaj: 0.00 0.00
transport: 0.00 0.00
Pag 32
STADIUL FIZIC: SC RCS&RDS SA
0 1 2 3 4 5
7
6 = 3 x 4d5
8 4b
4c = 3 x 4
4e
OBIECTUL: RELOCARE/PROTEJARE RETEA TELECOMUNICATII
STADIUL FIZIC: SC RCS&RDS SA
22 TCA17B1 JONCTION.CONDUCT.DIN CABLE buc 192.00 350.00 67,200.00
asim FIBRA OPTICA material: 150.00 28,800.00
manopera: 200.00 38,400.00
utilaj: 0.00 0.00
transport: 0.00 0.00
23 20011134 MANSON FIBRA OPTICA 96 buc 2.00 392.92 785.84
material: 392.92 785.84
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
24 SB24E1 Dop din pvc tip...u,pentru conducte de buc 8.00 17.02 136.19
canalizare,avand d=110mm material: 8.69 69.53
manopera: 8.33 66.66
utilaj: 0.00 0.00
transport: 0.00 0.00
25 TCA22B1 Masuratori end-to-end fibra optica buc 192.00 156.69 30,085.25
material: 88.54 17,000.37
manopera: 68.15 13,084.88
utilaj: 0.00 0.00
transport: 0.00 0.00
procent material manopera utilaj transport total
Cheltuieli directe: 224,561.88 157,141.53 15,058.94 0.00 396,762.35
Recapitulatia: 4/4 Recap 2019: CAM 2,25
Alte cheltuieli directe:
Contributie 2.2500 % 0.00 3,535.68 0.00 0.00 3,535.68
asiguratorie pentru
munca (CAM)
Total inclusiv Cheltuieli 224,561.88 160,677.22 15,058.94 0.00 400,298.03
directe:
Cheltuieli indirecte 4.0000 % 8,982.48 6,427.09 602.36 0.00 16,011.92
Total inclusiv Cheltuieli 233,544.35 167,104.31 15,661.29 0.00 416,309.95
indirecte:
Profit 4.0000 % 9,341.77 6,684.17 626.45 0.00 16,652.40
Total inclusiv Beneficiu: 242,886.13 173,788.48 16,287.74 0.00 432,962.35
TOTAL GENERAL (fara TVA): 432,962.35
TVA: 19.00% 82,262.85
TOTAL GENERAL: 515,225.20
Corneanu Cosmin,