Investitie: PLATFORMA Beneficiar: SC Executant: SC

Antemasuratoare
Normativ 1. TSG02A1 Curatirea terenului de iarba si buruieni V=37000 2. TSG08A1 Doborare arbori cu ferestraul mecanic si transportl manual in depozite.Diam 20-30cm. 3. TSC03F1 Scoaterea manuala a cioatelor si transportarea lor in depozite [Buc] 45 [Buc] 45 Unitati de masura [100mc] Cantitate 37

4. TSC01D1 Sapatura cu Scarificator V=(50 mx 20 m)+ (500 m x 5.4 m)x0.15 m=555 mc 5.6 mc Sapatura pamant -platforma V=(50 mx20 m)x0.3=300 mc -racord V=(500x5.4)x0.1=270 mc 2.7 +3.0= 5.7 mc Total: 5.6+5.7= 11.5 mc

[100mc]

5.6

5. TSC03F1 Incarcat in autocamion cu exacavator conform art 1 V=1130 mc

[100mc]

11.3

6. TRA01A10 Transport pamant -strat vegetal conform art 1 V=550 mc G=555 x 1.5= 332.5 tone => Total=832.5 tone -strat sapatura platforma + racord V=300+270= 570 mc G=570x1.9= 1083 tone Total: 1083+832.5= 1915.5 tone

[tone]

1915.5

7. Yc0105 cu balast 10 lei/mc -Platforma: V=50mx20mx0.25m= 250 mc -Racord V=4mx500mx0.25m=500 mc Total: 500mc+250 mc=750 mc Total lei: 750 x 10=7500 lei

[lei]

7500

8. Yc0103 cu pietris 16-32 mm, 12 lei/mc V=1.4mx500mx0.25m=175 mc Total lei: 175x12= 2100 lei

[lei]

2100

9. TRA01A15 -Transport autobetoniera balast conform art 5 V=750 mc G=V=750mcx1.7=1275 tone -Transport piatra sparta conform art 5 V=175 mc x1.5=262.5 tone Total: 262.5+1275=1537.5 tone 10. TSD16A1 Improscare balast si piatra Conform art 7 V=750 mc+175mc= 925 mc

[tone]

1537.5

[mc]

925

12. TRA06A10 Transport beton cu autobetoniera la distanta de 10 km V=20x50x0.2=200 mc

[mc]

200