h
[(2a + a ' )b + ( 2a '+a )b' ], m 3
6
h
5.200
V = [(2a + a' )b + (2a '+a )b' ] =
[(2 * 24.100 + 29.600)67.100 + (29.600 + 24.100)72.600] = 9758.0
6
6
V =
formulele
Coeficientul Ki=1.24-1.3 Kr=1.04-1.07
Vump=
Vinf =20.500*5.400*63.500=70.29
Vp =22.1*65.1*0.6-(34.8+66.15+132)=630.276
V1gr =0.6*0.5*2.9*4*10=34.8
V2gr =4.9*0.5*0.6*9*5=66.15
Vt=2.1*2.1*0.6*50=132
Scomp=
V 3229.615
=
=16148.075
n
0.2
Betonare fundatiei=Vt+V2gr+V1gr=232.95
Betonarea stratului de egalizare=6.92+14.4+26.45=48.46
Gr1=2700*0.1*0.7*4*10=6.92
Gr2=4700*0.1*9*5=14.4
F=2.3*2.3*0.1*5*10=26.45
Vt=2.1*2.1*0.6*50=132
Montarea Armaturii fundatiei
Continua 1 m3 beton 66 kg arm cont=(34.8+66.15)*66=6672.3
Izolata 1 m3 beton 58 kg arm=132*58=7716
Total=6672.3+7716=14388.3
Betonarea stilpului subsolului
V st=0.5*0.5*6=1.5
Vt=1.5*50=75
Armarea stilpului subsolului
1 m3 beton 80 kg arm=75*80=6000
Cofrarea stilpilor subsolului A=0.5*6*4*5*10=600
Betonarea peretilor exteriori subsolului
Va=4.5*0.2*6*8=40.3
Vb=6.5*0.2*6*18=140.4
Vt=140.4+40.3=180.7
Cofrareaperetilor exteriori
Aa=4.5*6*2*8=432
Ab=6.5*6*2*18=1404
At=432+1404=1836
Armarea grinzilor
Va=0.5*0.5*4.5*4*10=45 m3
Vb=0.5*0.5*63.5*5=79.37
Vt=45+79.37=124.37
1m3 grinda 77.6 kg arm =124.37*77.6=9651.11
Vpl =4.5*6.5*0.16*4*9=168.48
VT=124.37+168.48=292.85
1m3 de planseu176 kg arm=168.48*176=29652.48
Cofrare grinzilor si planseelor
Va=(4.5*0.34*2+0.5*4.5)*4*10=5.31*4*10=212.4
Vb=(5.5*0.34*2+0.5*6.5)*5*9=7.82*5*9=351.9
Vt=212.4+351.9=564.3
Vp=4.5*6.5*4*9=1053
VT=564.3+1053=1617.3
Executarea hidroizolatiei verticale=5.4(63.5+20.5)+2=907.2