"Reabilitarea si extinderea conductelor de aductiune, retelelor de distributie si retelelor de canalizare din Anina"

GRAFIC EXECUTIE
ID Task Task Name Duration Start Finish Month -1 Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11 Month 12 Month 13 Month 14 Month 15 Month 16 Month 17 Month 18 Month 19 Month 20 Month 2
0 Reabilitarea si extinderea conductelor de aductiune, 403 days Fri 10/4/13 Tue 4/21/15
retelelor de distributie si retelelor de canalizare din Anina
1 Ordin de incepere si predare amplasament 2 days Fri 10/4/13 Mon 10/7/13
2 Plan mediu, SSM, Proceduri de lucru 10 days Tue 10/8/13 Mon 10/21/13
3 Examinare documente de catre inginer 5 days Tue 10/8/13 Mon 10/14/13
4 Organizare santier 3 days Tue 10/8/13 Thu 10/10/13
5 Sondaje, trasee de explorare 390 days Fri 10/11/13 Thu 4/9/15
6 Aprovizionare 390 days Fri 10/11/13 Thu 4/9/15
7 Reabilitare si extindere sistem alimentare cu apa (19,988 km) 391 days Fri 10/11/13 Fri 4/10/15
8 Trasare 378 days Fri 10/11/13 Tue 3/24/15
9 Semnalizare si cai de acces provizorii 378 days Fri 10/11/13 Tue 3/24/15
10 Sapatura si demontarea conductelor existente 378 days Fri 10/11/13 Tue 3/24/15
11 Montaj conducte 378 days Tue 10/15/13 Thu 3/26/15
12 Realizare camine vane/bransamente 378 days Mon 10/21/13Wed 4/1/15
13 Proba presiune si etanseitate 378 days Tue 10/22/13 Thu 4/2/15
14 Spalare si dezinfectare 378 days Tue 10/22/13 Thu 4/2/15
15 Umpluturi 378 days Wed 10/23/13Fri 4/3/15
16 Refacere sistem rutier 378 days Wed 10/30/13Fri 4/10/15
17 Subtraversari 378 days Fri 10/11/13 Tue 3/24/15
18 Detaliere la nivel de strazi 391 days Fri 10/11/13 Fri 4/10/15
293 Rezervor inmagazinare nou 30 days Fri 10/11/13 Thu 11/21/13
294 Reabilitare rezervoare 150 days Fri 10/11/13 Thu 5/8/14
295 Statii de pompare ( 3 buc.) 75 days Fri 10/11/13 Thu 1/23/14
296 Trasare 50 days Fri 10/11/13 Thu 12/19/13
297 Sapaturi 50 days Fri 10/11/13 Thu 12/19/13
298 Constructii 50 days Mon 10/14/13Fri 12/20/13
299 Montaj instalatii si echipamente 50 days Fri 10/25/13 Thu 1/2/14
300 Racord electric 50 days Mon 10/28/13Fri 1/3/14
301 Proba de etanseitate 50 days Fri 11/1/13 Thu 1/9/14
302 Refacere sistem rutier 50 days Fri 11/1/13 Thu 1/9/14
303 Testare si Punere in functiune 50 days Fri 11/15/13 Thu 1/23/14
304 Reabilitare si extindere retea de canalizare ( 28,668 km) 395 days Fri 10/11/13 Thu 4/16/15
305 Trasare 385 days Fri 10/11/13 Thu 4/2/15
306 Semnalizare si cai de acces provizorii 385 days Fri 10/11/13 Thu 4/2/15
307 Sapatura si asternerea patului de nisip 385 days Fri 10/11/13 Thu 4/2/15
308 Montaj conducte 385 days Mon 10/14/13Fri 4/3/15
309 Montaj camine si racorduri 385 days Thu 10/17/13 Wed 4/8/15
310 Proba de etanseitate 385 days Fri 10/18/13 Thu 4/9/15
311 Umpluturi 385 days Mon 10/21/13Fri 4/10/15
312 Refacere sistem rutier 385 days Fri 10/25/13 Thu 4/16/15
313 Subtraversari 385 days Fri 10/11/13 Thu 4/2/15
314 Detaliere la nivel de strazi 395 days Fri 10/11/13 Thu 4/16/15
782 Stratii de pompare ape uzate (8buc.) 200 days Fri 10/11/13 Thu 7/17/14
783 Trasare 175 days Fri 10/11/13 Thu 6/12/14
784 Sapaturi 175 days Fri 10/11/13 Thu 6/12/14
785 Constructii 175 days Mon 10/14/13Fri 6/13/14
786 Montaj instalatii si echipamente 175 days Fri 10/25/13 Thu 6/26/14
787 Racord electric 175 days Mon 10/28/13Fri 6/27/14
788 Proba de etanseitate 175 days Fri 11/1/13 Thu 7/3/14
789 Refacere sistem rutier 175 days Fri 11/1/13 Thu 7/3/14
790 Testare si Punere in functiune 175 days Fri 11/15/13 Thu 7/17/14
791 Conducte de refulare ( 3193 m) 106 days Fri 10/11/13 Fri 3/7/14
792 Trasare 100 days Fri 10/11/13 Thu 2/27/14
793 Semnalizare si cai de acces provizorii 100 days Fri 10/11/13 Thu 2/27/14
794 Sapatura 100 days Fri 10/11/13 Thu 2/27/14
795 Montaj conducte 100 days Mon 10/14/13Fri 2/28/14
796 Proba presiune si etanseitate 100 days Wed 10/16/13Tue 3/4/14
797 Spalare si dezinfectare 100 days Wed 10/16/13Tue 3/4/14
798 Umpluturi 100 days Thu 10/17/13 Wed 3/5/14
799 Refacere sistem rutier 100 days Mon 10/21/13Fri 3/7/14
800 Dezafectare santier 3 days Fri 4/17/15 Tue 4/21/15

Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only
Project: Reabilitarea si extinderea
Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Date: Wed 10/9/13
Milestone External Tasks Inactive Milestone Duration-only Start-only Progress