Sunteți pe pagina 1din 5

Antet stanga eDevize

Beneficiar: TRANSGAZ Sucursala Medias


Executant:
Proiectant: MDI PROCAD INSTAL
Obiectivul: Construire baza de productie F.I.R. DEJ
Obiectul: 1 CORP ADMINISTRATIV SI GARAJ
Stadiul fizic: 4 INST ELECTRICE

Formular F3
Lista cu cantitati de lucrari pe categorii de lucrari

SECTIUNEA TEHNICA SECTIUNEA FINANCIARA

Pretul unitar TOTALUL


Nr. Capitol de lucrari U.M. Cantitatea (fara TVA) (fara TVA)
- Lei - - Lei -
0 1 2 3 4 5=3x4
1 EF01C01> - Montare tablou electric complet echipat buc 3.00 186.79 560.38
material: 0.00 0.00
manopera: 186.79 560.38
utilaj: 0.00 0.00
transport: 0.00 0.00
1 100014263 - Tablou electric secundar administrativ buc 1.00 1,250.00 1,250.00

1 100014264 - Tablou electric secundar garaj buc 1.00 1,250.00 1,250.00

1 100014265 - Tablou electric TEG buc 1.00 4,000.00 4,000.00


2 EF01C01> - Montare tablou electric complet echipat buc 1.00 186.79 186.79
material: 0.00 0.00
manopera: 186.79 186.79
utilaj: 0.00 0.00
transport: 0.00 0.00
2 100014222 - Tablou electric pentru compensarea factorului de putere buc 1.00 1,200.00 1,200.00

3 EH03A01> - Incercarea tablourilor de distributie, de comanda de buc 3.00 234.97 704.90


protectie, de semnalizare, a pupitrelor de comanda si a cutiilor metalice cu
material: 0.00 0.00
cleme panouri metalice sau dulapuri metalice
manopera: 197.03 591.08
utilaj: 37.94 113.82
transport: 0.00 0.00
4 EE02A01> - Montarea corpurilor de iluminat cu led buc 91.00 87.49 7,961.98
material: 2.20 200.29
manopera: 85.29 7,761.69
utilaj: 0.00 0.00
transport: 0.00 0.00
4 100014231 - Corp de iluminat led cu brat reglabil si senzor crepuscular, buc 6.00 850.00 5,100.00
montat pe stalp
4 100014232 - Corp de iluminat led exterior, montat pe imobil buc 6.00 600.00 3,600.00

4 100014236 - Corp de iluminat led buc 37.00 180.00 6,660.00

4 100014237 - Corp de iluminat led tip plafoniera, montaj aparent/suspendat buc 24.00 180.00 4,320.00

Deviz "4" - Formular F3 Pagina 1 din 5


Formular generat cu programul (www.eDevize.ro)
Antet stanga eDevize

SECTIUNEA TEHNICA SECTIUNEA FINANCIARA

Pretul unitar TOTALUL


Nr. Capitol de lucrari U.M. Cantitatea (fara TVA) (fara TVA)
- Lei - - Lei -
0 1 2 3 4 5=3x4
4 100014238 - Corp de iluminat led, tip plafoniera, montaj buc 9.00 130.00 1,170.00
aparent/suspendat IP 20 montaj spatii uscate IP 23 montaj in grupuri
sanitare
4 100014239 - Corp de iluminat led tip aplica etans IP44 buc 9.00 175.00 1,575.00
5 ED01A01> - Intrerupator manual unipolar, constructie normala sau buc 33.00 7.11 234.61
impermeabila (flansa), montat ingropat
material: 0.29 9.43
manopera: 6.82 225.17
utilaj: 0.00 0.00
transport: 0.00 0.00
5 100014212 - Intrerupator simplu ST buc 9.00 6.00 54.00
5 100014245 - Intrerupator dublu ST buc 18.00 9.00 162.00
5 100014246 - Comutator cap scara 10A, 230V, inclusiv doza de aparat buc 6.00 6.00 36.00

6 ED05A01> - Montare prize electrice buc 86.00 7.11 611.40


material: 0.29 24.58
manopera: 6.82 586.82
utilaj: 0.00 0.00
transport: 0.00 0.00
6 100014247 - Priza monofazata simpla ST buc 86.00 16.00 1,376.00
7 ED07A01> - Priza tripolara, de 10 sau 25 a, cu fisa, in carcasa de buc 24.00 7.38 177.18
bachelita, montata aparent pe dibluri de lemn
material: 0.13 3.18
manopera: 7.25 174.00
utilaj: 0.00 0.00
transport: 0.00 0.00
7 100014249 - Priza trifazata buc 24.00 40.00 960.00
8 EA06A01> - Doza de derivatie, pentru cabluri sau tevi de instalatii, buc 40.00 9.71 388.24
montata in mediu normal, tip nbu-pg 16
material: 4.59 183.54
manopera: 5.12 204.70
utilaj: 0.00 0.00
transport: 0.00 0.00
8.1 7319034 - Doza patrata buc 40.00 4.05 162.14
9 EC04A01> - Cablu de energie tras prin tub protejat metalic pentru racord m 413.00 2.14 884.12
motoare tablouri aparate conducte mai mici de 16mmp
material: 0.01 3.46
manopera: 2.13 880.65
utilaj: 0.00 0.00
transport: 0.00 0.00
9 100014215 - Cablu CYYF 3x1.5 m 553.00 4.00 2,212.00
9 100014216 - Cablu CYYF 3X2.5 m 885.00 6.00 5,310.00
9 100014217 - Cablu CYYF 5X2.5 m 280.00 7.00 1,960.00
9 100014250 - Cablu CYYF 5X10 m 40.00 10.00 400.00
9 100014252 - Cablu CYYF 5X35 m 8.00 20.00 160.00

9 100014256 - Cablu CYABY 3X70+35 m 30.00 25.00 750.00

Deviz "4" - Formular F3 Pagina 2 din 5


Formular generat cu programul (www.eDevize.ro)
Antet stanga eDevize

SECTIUNEA TEHNICA SECTIUNEA FINANCIARA

Pretul unitar TOTALUL


Nr. Capitol de lucrari U.M. Cantitatea (fara TVA) (fara TVA)
- Lei - - Lei -
0 1 2 3 4 5=3x4
10 YC01D01> - Diferenta pret material lei-Procurare si montare cablu lei 3,000.00 1.00 3,000.00
incalzitor antiinghet P=200W/ml 31 ml
material: 1.00 3,000.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 0.00 0.00
11 W1C02A01> - Montare pat cablu m 359.00 3.39 1,215.94
material: 0.15 52.32
manopera: 3.24 1,163.62
utilaj: 0.00 0.00
transport: 0.00 0.00
11 100014259 - Pat cablu inclusiv sisteme de sustinere si montaj 400x100 m 30.00 15.00 450.00

11 100014260 - Pat cablu inclusiv sisteme de sustinere si montaj 300x100 m 86.00 12.00 1,032.00

12 TSA01J01> - Sapatura manuala de pamant in spatii limitate, avand sub 1 mc 48.80 82.79 4,040.26
m latime si maximum 4,5 m adancime, executata cu sprijiniri, cu evacuare
material: 3.51 171.40
manuala, la fundatii, canale, drumuri, in pamant cu umiditate naturala,
adancimea sapaturii 1,5-3 m, teren tare manopera: 79.28 3,868.85
utilaj: 0.00 0.00
transport: 0.00 0.00
13 W2H01A01> - Strat nisip asezat in sant pentru protejarea cablurilor la mc 7.20 81.45 586.46
lucrari in profil netipizat
material: 66.72 480.40
manopera: 14.73 106.06
utilaj: 0.00 0.00
transport: 0.00 0.00
14 TRA01A04> - Transportul rutier al materialelor, semifabricatelor cu tona 7.20 6.86 49.36
autobasculanta, pe distanta de 10 km
material: 0.00 0.00
manopera: 0.00 0.00
utilaj: 0.00 0.00
transport: 6.86 49.36
15 TSD01A01> - Imprastierea cu lopata a pamantului afanat, strat uniform mc 48.80 3.28 160.18
10-30 cm gros, cu sfaramare bulgari teren, teren usor
material: 0.00 0.00
manopera: 3.28 160.18
utilaj: 0.00 0.00
transport: 0.00 0.00
16 TSD02B01> - Compactarea cu mai de mana a umpluturii executate pe mc 48.80 15.82 772.04
strat, cu udarea fiecarui strat de 10 cm grosime, teren necoeziv
material: 0.22 10.53
manopera: 15.60 761.52
utilaj: 0.00 0.00
transport: 0.00 0.00
17 W1R02A01> - Electrod din teava de otel de doi toli si jumatate pentru m 16.00 55.93 894.83
legarea la pamant, in teren normal
material: 26.40 422.35
manopera: 28.07 449.04
utilaj: 1.46 23.44
transport: 0.00 0.00

Deviz "4" - Formular F3 Pagina 3 din 5


Formular generat cu programul (www.eDevize.ro)
Antet stanga eDevize

SECTIUNEA TEHNICA SECTIUNEA FINANCIARA

Pretul unitar TOTALUL


Nr. Capitol de lucrari U.M. Cantitatea (fara TVA) (fara TVA)
- Lei - - Lei -
0 1 2 3 4 5=3x4
18 W1R01A01> - Conductor principal pentru legarea la pamant, montat in kg 25.00 32.13 803.30
exterior, in teren normal
material: 1.65 41.34
manopera: 30.48 761.96
utilaj: 0.00 0.00
transport: 0.00 0.00
18.1 3701412 - Banda otel lam.cald S908 4X40 OL 37-1N m 25.75 1.51 38.79
19 W1R03A01> - Imbinarea prizei de legare la pamant, cu suruburi buc 6.00 6.18 37.07
galvanizate M12X4
material: 3.40 20.40
manopera: 2.78 16.67
utilaj: 0.00 0.00
transport: 0.00 0.00
20 W1P01A01> - Verificarea prizei de legare la pamant la lea, sub 1KV buc 1.00 22.78 22.78
material: 0.00 0.00
manopera: 22.78 22.78
utilaj: 0.00 0.00
transport: 0.00 0.00
21 EG09A01> - Cutie cu eclisa de legatura, pentru centura de impamantare buc 3.00 62.49 187.48
material: 33.09 99.28
manopera: 29.40 88.20
utilaj: 0.00 0.00
transport: 0.00 0.00
22 W2E02A01> - Bloc de masura si protectie din material plastic cu limitator buc 1.00 2,947.59 2,947.59
de putere si loc pentru contor, ti
material: 2,906.56 2,906.56
manopera: 41.02 41.02
utilaj: 0.00 0.00
transport: 0.00 0.00
22.1 7322223 - Bloc de masura si protectie monofazat bmpm de 30a buc 1.00 2,901.46 2,901.46
reglabil in trepte ( 5, 10, 15, 20, 25, 30 )
TOTAL 1 (Cheltuieli directe)
Greutate Materiale (tone) Ore Manopera Material Manopera Utilaj Transport TOTAL
15.47 884.05 52,616.07 18,611.20 137.25 49.36 71,413.89

Recapitulatie Valoare Material Manopera Utilaj Transport TOTAL

Alte cheltuieli directe


Contribuția asiguratorie pentru 0.2700 % 0.00 50.25 0.00 0.00 50.25
muncă
T2 = T1 + Alte cheltuieli directe 52,616.07 18,661.45 137.25 49.36 71,464.14

Cheltuieli indirecte
Cheltuieli indirecte 10.0000 % 5,261.61 1,866.14 13.73 4.94 7,146.41
T3 = T2 + Cheltuieli indirecte 57,877.68 20,527.59 150.98 54.30 78,610.55

Beneficiu
Profit 5.0000 % 2,893.88 1,026.38 7.55 2.71 3,930.53
T4 = T3 + Beneficiu 60,771.57 21,553.97 158.53 57.01 82,541.08

Deviz "4" - Formular F3 Pagina 4 din 5


Formular generat cu programul (www.eDevize.ro)
Antet stanga eDevize

TOTAL GENERAL (fara TVA) 82,541.08


TVA (19.00%) 15,682.80
TOTAL GENERAL (inclusiv TVA) 98,223.88

Proiectant

Deviz "4" - Formular F3 Pagina 5 din 5