CAPITOLUL 6
Antemăsurătoarea lucrărilor de construcţie
Lucrare de Licenţă 98
Calculul Economic
Lucrare de Licenţă 99
Calculul Economic
ANTEMĂSURĂTOARE
9. CB10B1 575 MP
COFRAJE PT BET IN CUZINETI, FUND PAHAR SI CONTINUE
SIMPLE DIN PAN CU PLACAJ 15MM INCLUSIV SPRIJIN
10. TRA06A05 1035 T
TRANSPORTUL RUTIER AL BETONULUI CU AUTO
BETONIERA DE 5,5MC DIST. = 5 KM
11. CA07B1 431 MC
TURNARE BETON ARMAT CU POMPA IN FUNDATII
IZOLATE LA ADANCIME PANA LA 10M SI DISTANTE
INTRE 15-45 M
12. TSD02A1 4 100MC
IMPRAST.PAMANT AFANAT PROVENIT DIN TEREN
CATEG 1 SAU 2 CU BULD. DE 65-80CP IN STRAT. CU
GROSIMEA DE 15-20 CM
13. TSD05B1 4 100MC
COMPACTARE CU MAI MEC.DE 150-200KG A UMPL.
IN STRAT DE 20-30CM EXCLUSIV UDARE STRAT DIN
PAM.COEZIV
Extras resurse
Deviz 04 Infrastructura
Extras materiale
2000195 KG 3,752.15000 1.86 6,991.76
OTEL BETON PROFIL NETED OB37 STAS 438 D=16MM
2100397 KG 156,080.73600 0.45 70,236.33
CIMENT METALURGIC CU ADAOSURI M 30 VRAC S 1500
2200288 M CUB 172.87402 37.35 6,456.55
PIETRIS CIURUIT SPALAT DE MAL 7-15 MM
2200513 M CUB 295.13182 40.35 11,907.68
NISIP SORTAT NESPALAT DE RIU SI LACURI 0,0-3,0 MM
2200642 M CUB 138.93214 43.38 6,026.88
NISIP SORTAT SPALAT DE RIU SI LACURI 3,0-7,0 MM
2900888 M CUB 0.38790 184.72 71.65
LEMN ROT CONS RUR COJ FAG L MIN 1M D SUB MIN18CM S4342
2901167 M CUB 0.28750 259.12 74.50
MANELE D=7-11CM L=2-6M RASINOASE S.1040
2903995 M CUB 2.01250 422.50 850.28
SCIND RASIN LUNGA TIV CLS D GR=24MM L=4,00M S 942
2928347 MP 14.37500 59.04 848.68
PANOU DE COFRAJ TIP P FAG G 15MM PT PERETI
3803233 KG 28.75000 3.75 107.84
SARMA MOALE OBISNUITA D= 2,5 OL32 S 889
5886899 KG 4.31000 2.97 12.79
CUIE CU CAP CONIC TIP A1 2,8 X 50 OL34 S 2111
5886942 KG 46.00000 2.88 132.27
CUIE CU CAP CONIC TIP A1 3 X 70 OL34 S 2111
6201084 KG 69.00000 3.14 216.37
ULEI EMULSIONABIL PT.DECOFRARE BETOANE S11382
6202818 M CUB 137.43984 1.80 247.39
APA INDUSTRIALA PENTRU MORTARE SI BETOANE DELA RETEA
6309903 KG 12.93000 4.48 57.89
CONFECTII METALICE SUD.CORNIER < 70 MM PT.ESAFODAJE
6719093 BUCATA 5,400.00000 0.27 1,459.62
DISTANTIER DIN M.PLASTI.PT POZ.ARM.IN BETON PT GRINZI
Greutate totala:1161.942 Total materiale 105,698.47
Extras manopera
0010212 ORE 99.22248 8.01 794.77
BETONIST 12
0010222 ORE 30.17000 8.49 256.14
BETONIST 22
0010232 ORE 34.48000 9.01 310.66
BETONIST 32
0010242 ORE 4.31000 9.83 42.37
BETONIST 42
0010252 ORE 30.17000 10.86 327.65
BETONIST 52
0010712 ORE 158.11000 8.01 1,266.46
DULGHER CONSTRUCTII 12
0010722 ORE 293.25000 8.49 2,489.69
DULGHER CONSTRUCTII 22
0010732 ORE 99.16000 9.01 893.43
DULGHER CONSTRUCTII 32
0010742 ORE 40.25000 9.83 395.66
DULGHER CONSTRUCTII 42
0011111 ORE 40.86500 7.84 320.38
FIERAR BETON 11
0011112 ORE 540.00000 8.01 4,325.40
FIERAR BETON 12
0011121 ORE 40.86500 8.32 340.00
FIERAR BETON 21
0011132 ORE 574.48000 9.01 5,176.06
FIERAR BETON 32
0019921 ORE 92.00500 7.30 671.64
MUNCITOR DESERV.CTII MONTJ. 21
0019931 ORE 365.02000 7.61 2,777.80
MUNCITOR DESERV.CTII MONTJ. 31
0029932 ORE 0.00187 8.12 0.02
MUNCITOR DESERV.CTII MASINI 32
0319721 ORE 15.40000 7.41 114.11
MUNCITOR INC/DESC.MAT. 21
Total ore:2457.759 Total manopera 20,502.25
Extras utilaje
0003312 ORE 29.30800 314.50 9,217.37
AUTOPOMPA HIDRAULICA DE BETON 40-60 MC/H
0003501 ORE 33.75000 136.43 4,604.34
EXCAVATOR PE SENILE CU O CUPA, MOT.TERMIC, 0,40-0,70 MC
0003553 ORE 10.68923 89.68 958.56
BULDOZER PE SENILE 65- 80 CP
0003710 ORE 19.43978 159.80 3,106.48
CENTRALA DE BETON (SEMIAUTOMATIZATA) 21-40MC/H
0003716 ORE 60.34000 2.68 161.56
VIBRATOR DE INTERIOR PT.BETON ACTIONAT ELECTRIC 0,9-1,5 KW
0004021 ORE 37.72000 37.40 1,410.73
MAI MECANIC CU MOT.TERMICDE 6CP 150-200 KGF
OFERTANT
Deviz analitic
Deviz 04 Infrastructura
Pozitie Cod resursa U/M Cantitate Sp.mat Pret materiale Val. materiale
Corectii Sp.man Pret manopera Val. manopera
Denumire resursa Sp.uti Pret utilaj Val. utilaj
Observatii Pret transport Val. transport
Liste anexa Nr.ore/UM TOTAL A
Greutate/UM Greutate totala
0.00 0.00
7 CZ0301B1 82 KG 3,715.00000 1.88 6,991.74
0.18 660.38
CONFECT.ARMAT.FASONARE BARE PT.FUNDATII IZOL.CONTI 0.09 338.47
NUI SI RADIERE IN ATEL.CENT.OB 37 D=10- 16 MM $ 0.00 0.00
0.02 7,990.59
0.00 3.75
8 CC01A1 82 KG 36,000.00000 0.04 1,459.80
0.30 10,834.56
MONTARE ARMATURI DIN OTEL BETON D<18MM IN FUNDATII 0.00 0.00
IZOLATE CU DISTANTIERI DIN MASE PLASTICE 0.00 0.00
0.04 12,294.36
0.00 0.07
9 CB10B1 82 MP 575.00000 3.88 2,229.94
8.43 4,848.52
COFRAJE PT BET IN CUZINETI,FUND PAHAR SI DE UTILAJ 0.00 0.00
E,SIMPLE DIN PAN CU PLACAJ 15MM INCLUSIV SPIJIN 0.00 0.00
1.00 7,078.45
0.00 1.70
10 TRA06A05 82 TONE 1,035.00000 0.00 0.00
0.00 0.00
TRANSPORTUL RUTIER AL BETONULUI-MORTARULUI CU AUTO 0.00 0.00
BETONIERA DE 5,5MC DIST. =5 KM $ 13.65 14,127.75
0.00 14,127.75
0.00 0.00
11 CA07B1 82 M CUB 431.00000 212.60 91,632.09
5.98 2,576.56
TURNARE BETON ARMAT CU POMPA IN FUNDATII IZOLATE L 31.43 13,547.99
A ADINCIME PINA LA 10M SI DISTANTE INTRE 15-45M 0.00 0.00
0.69 107,756.64
2.58 1,111.24
L:10173 -0036:CZ0106A1 -PREPARARE BETON B 200,AGREG.GRELE,SORT.GRANUL.<16MM CIM.M30 ELEM.SECT.RED.PIL.FRANKI INST.CENTRAL. $
12 TSD02A1 82 SUTE MC 4.00000 0.00 0.00
0.00 0.00
IMPRAST.PAMINT AFINAT PROVENIT DIN TER.CAT.1 SAU 2 97.75 390.98
CU BULD.DE 65-80CP IN STRAT.CU GROS.DE 15-20CM 0.00 0.00
0.00 390.98
0.00 0.00
13 TSD05B1 82 SUTE MC 4.00000 0.00 0.00
64.39 257.54
COMPACTARE CU MAI.MEC.DE 150-200KG A UMPL.IN STRAT 352.68 1,410.73
.DE 20-30CM EXCLUSIV UDARE STRAT DIN PAM.COEZIV 0.00 0.00
8.82 1,668.27
0.00 0.00
Greutate totala 1161.960856 Total materiale 105,698.64
Total ore 2458 Total manopera 20,502.25
Ofertant,