1. AUTOSTRĂZI
STADIUL FINANCIAR
Nr. crt. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) PANA LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII
ACTUAL
SEMNARE CONTRACT PROIECTARE SI EXECUTIE IN DATA DE 28.12.2020. PRETUL PE KM DE AUTOSTRADA ESTE DE CCA. 46,261,293.92 LEI FARA TVA, REPREZENTAND CCA. 9,383,629 EURO
FARA TVA.
DURATA CONTRACTULUI ESTE DE 96 DE LUNI, DIN CARE:
SUBSECTIUNEA 3A2
SECTIUNEA 3A SI SECTIUNEA 3B, • 12 LUNI PERIOADA DE PROIECTARE,
NADASELU - MIHAIESTI KM
AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE AUTOSTRADA BRASOV - TARGU ASOCIEREA S.C. SPEDITION UMB S.R.L. – S.C. TEHNOSTRADE SUBSECTIUNEA 3A2: NADASELU - 25.01.2024, CONFORM 1.390,614 MIL. LEI FARA • 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,
2 AUTOSTRADA 8+700 38+760 8+700 - 25+500+ 3B1, 30,06 23% 19,42% 25.01.2021 25.01.2024, CONFORM CONTRACT
LUCRARI MURES - CLUJ - ORADEA S.R.L. – S.C. ELECTROMONTAJ S.A MIHAIESTI SI 3B1: MIHAESTI CONTRACT TVA • 60 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.
MIHAIESTI – ZIMBOR KM
ZIMBOR AUTORIZATIE DE CONSTRUIRE EMISA PENTRU SECTORUL 3A2 IN LUNA APRILIE 2021.
0+000 - 13+260
AUTORIZATIE DE CONSTRUIRE EMISA PENTRU SECTORUL 3B1 IN 01.07.2021
PROIECT TEHNIC DE EXECUTIE PENTRU 3A2 AVIZAT IN CTE - CNAIR IN DATA DE 20.08.2021
PROIECT TEHNIC DE EXECUTIE PENTRU 3B1 AVIZAT IN CTE-CNAR IN DATA DE 17.12.2021 - URMEAZA EMITEREA ORDINULUI DE INCEPERE A LUCRARILOR
IN DATA DE 31.08.2020, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL "PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA BUCURESTI KM 0+000-KM 100+900, SECTOR CENTURA NORD KM 0+000-
KM 52+770, LOT 4 KM 47+600 - KM 52+070”, CU OFERTANTUL DECLARAT CASTIGTOR, ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L.
VALOAREA CONTRACTULUI: 312.633.554,09 LEI FARA TVA.
LUNGIME: 4.47 KM
AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA A ASOCIEREA S.C. SA&PE CONSTRUCT S.R.L. - S.C. SPEDITION 312.63 MIL. LEI FARA SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE.
5 AUTOSTRADA 47+600 52+070 SECTOR NORD LOT 4 4,47 0% 0% 2021 2024 ESTIMAT TRIM. IV 2024
LUCRARI MUNICIPIULUI BUCURESTI (A0) UMB S.R.L. - S.C. TEHNOSTRADE S.R.L. TVA DURATA CONTRACTULUI ESTE DE 150 LUNI, DIN CARE:
12 LUNI PERIOADA DE PROIECTARE,
18 LUNI PERIOADA DE EXECUTIE A LUCRARILOR
120 LUNI PERIOADA DE GARANTIE A LUCRARILOR.
IN PREZENT SE LUCREAZA LA ELABORAREA STUDIULUI DE EVALUAREA ADECVATA (SEA), PENTRU LACUL SI PADUREA CERNICA (ARIE PROTEJATA)
IN DATA DE 17.05.2021, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL ""PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA BUCURESTI KM 0+000-KM 100+900, SECTOR CENTURA NORD KM
0+000-KM 52+770, LOT 2 KM 20+000 - KM 39+000”, CU OFERTANTUL DECLARAT CASTIGTOR, ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE
S.R.L.
VALOAREA CONTRACTULUI: 831.920.653,34 LEI FARA TVA.
LUNGIME: 19 KM
AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA A ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - 831.92 MIL. LEI FARA
6 AUTOSTRADA 20+000 39+000 SECTOR NORD LOT 2 19 0% 0% 2021 2024 ESTIMAT TRIM. IV 2024 SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE.
LUCRARI MUNICIPIULUI BUCURESTI (A0) SPEDITION UMB - TEHNOSTRADE S.R.L. TVA
DURATA CONTRACTULUI ESTE DE 154 LUNI, DIN CARE:
12 LUNI PERIOADA DE PROIECTARE,
22 LUNI PERIOADA DE EXECUȚIE A LUCRĂRILOR
120 LUNI PERIOADA DE GARANȚIE A LUCRĂRILOR
A FOST EMIS ORDIN DE INCEPERE IN DATA DE 16.08.2021
03.10.2019 - DATA DE
A FOST EMISA AUTORIZATIA DE CONSTRUIRE NR. 66/25.11.2020
SECTOR NORD - KM 52+070 – 29,29% - PROGRES INCEPERE A ACTIVITATII DE
AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA A 830.68 MIL. LEI FARA A FOST APROBAT PROIECTUL TEHNIC DE EXECUTIE IN DATA DE 11.02.2021.
8 AUTOSTRADA 52+070 69+000 ALSIM ALARKO SANAYI TESISLERI VE TICARET A.S. KM 52+770; SECTOR SUD - KM LOT 1: GLINA - VIDRA 16,93 17,24% FINANCIAR (INCLUSIV PROIECTARE IUNIE 2023 ANUL 2023
LUCRARI MUNICIPIULUI BUCURESTI (A0) TVA ORDIN DE INCEPERE LUCRARI 01.03.2021
52+770 – KM 69+000 AVANS LUCRARI) ORDIN INCEPERE LUCRARI
A FOST PUBLICAT IN MONITORIUL OFICIAL HG 861/2021 PRIVIND IMOBILELE AFLATE PE CULOARUL SUPLIMENTAR
01.03.2021
23.05.2019 - DATA DE ANTREPRENORUL A FINALIZAT DECLARATIA DE PROIECTARE (INREGISTRAND INTARZIERI MAJORE IN ACTIVITATEA DE PROIECTARE), FIIND PENALIZAT CONFORM CONTRACTULUI PENTRU
INCEPERE A ACTIVITATII DE NEINDEPLINIREA PUCTULUI DE REFERINTA NR 1 (FINALIZAREA DECLARATIEI DE PROIECTARE).
SECTOR SUD - KM 85+300 - KM 8,93% (PROGRES
AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA A 85+300 - 0+000 - 2+500 ASOCIEREA AKTOR TECHNICAL SOCIETE ANONYME (AKTOR PROIECTARE 853.42 MIL. LEI FARA PAC A FOST ANALIZAT SI APROBAT IN CADRUL CTE CNAIR IN DATA DE 11.06.2021.
9 AUTOSTRADA 100+765; SECTOR NORD - KM LOT 3: BRAGADIRU - JOITA 17,965 1,20% FINANCIAR INCLUSIV APRILIE 2024 APRILIE 2024
LUCRARI MUNICIPIULUI BUCURESTI (A0) 100+765 SUD NORD S.A.) - S.C. EURO CONSTRUCT TRADING 98 S.R.L. ORDIN INCEPERE LUCRARI KM TVA A FOST EMISA AUTORIZATIA DE CONSTRUIRE NR. 33/01.07.2021 - ETAPA I (KM 86+700 - KM 100+765, KM 0+000 - KM 2+500)
0+000 + KM 2+500 AVANS lucrari)
86+700 - KM 100+765 SI KM PTE A FOST ANALIZAT SI APROBAT IN CADRUL CTE CNAIR IN DATA DE 13.10.2021
0+000 - KM 2+500 - 25.10.2021 DATA DE INCEPERE A LUCRARILOR PENTRU ETAPA I (KM 86+700 - KM 100+765, KM 0+000 - KM 2+500) - 25.10.2021
IN DATA DE 15.11.2021 A FOST SEMNAT CONTRACTUL CU S.C. PORR CONSTRUCT S.R.L. CU PRETUL DE 1.678.873.121,77 LEI FARA TVA.
DURATA CONTRACTULUI ESTE DE 60 DE LUNI, DIN CARE 16 LUNI PERIOADA DE PROIECTARE SI 44 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,
PERIOADA DE GARANTIE A LUCRARILOR ESTE DE 60 DE LUNI.
AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE 2000.17 MIL. LEI FARA
12 AUTOSTRADA AUTOSTRADA SIBIU - PITESTI 81+900 91+761 PORR CONSTRUCT SRL TIGVENI - CURTEA DE ARGES SECTIUNEA 4 9,86 0% 0% 2021 2026 ESTIMAT 2026 OBIECTUL CONTRACTULUI IL REPREZINTA PROIECTAREA SI EXECUTIA LUCRARILOR PENTRU CONSTRUCTIA AUTOSTRAZII SIBIU - PITESTI, SECTIUNEA 4: TIGVENI - CURTEA DE ARGES IN
LUCRARI TVA
LUNGIME DE 9,86 KM.
SEMNAREA CONTRACTULUI DE ACHIZITIE PUBLICA VA FI POSIBILA DUPA EXPIRAREA DIN NOU A PERIOADEI DE DEPUNERE A EVENTUALELOR CONTESTATII SI RESPECTIV DUPA SOLUTIONAREA
TUTUROR CONTESTATIILOR/PLANGERILOR FORMULATE IN CADRUL PROCEDURII DE ATRIBUIRE.
DRUM BRAILA-JIJILA -
19,095 KM; SECTIUNEA 2 OCTOMBRIE 2022
AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE ASOCIEREA ASTALDI S.P. A - IHI INFRASTRUCTURE SYSTEM POD SUSPENDAT PESTE DUNARE DECEMBRIE 2022 SECTIUNEA 2 1.996 MLD. LEI FARA
13 DRUM NATIONAL POD BRAILA 1 DRUM DE LEGATURA CU 54,50% 61,84% 21.12.2018 TOTAL CONTRACT: ESTIMAT CONTRACT IN DERULARE.
LUCRARI CO. LTD. IN ZONA BRAILA PODUL SUSPENDAT TVA
DN22 SMARDAN-MACIN DECEMBRIE 2022
- 4,328 KM
1.2. AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI - IANUARIE 2022
STADIUL FINANCIAR
Nr. crt. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) PANA LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII
ACTUAL
18.09.2020 - NOD CHETANI (1.3 CTR. REZILIAT - IN DATA DE 11.03.2021 S-A TRANSMIS ANTREPRENORULUI INSTIINTAREA DE REZILIERE A CONTRACTULUI.
KM) - DESCHIDEREA PROCEDURA DE REZILIERE A FOST SUSPENDATA IN URMA DECIZIEI TRIBUNALULUI BUCURESTI.
TRONSON OGRA - CAMPIA 37.86% - PROGRES 41.97% - PROGRES TRAFICULUI 383.44 MIL. LEI FARA IN DATA DE 10.05.2021 S-A EMIS REZILIEREA CONTRACTULUI CATRE ANTREPRENOR PENTRU LIPSA GARANTIEI DE BUNA EXECUTIE.
AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI AUTOSTRADA BRASOV - TARGU ASOCIEREA SC STRACO GRUP SRL & SPECIALIST CONSULTING
3 AUTOSTRADA 21+500 37+191 TURZII LOT 3 15,691 INREGISTRAT LA DATA INREGISTRAT LA DATA 04.05.2016 2021 - INTARZIERI MAJORE ALE CTR REZILIAT - RELICITARE LUCRARI TVA (VALOARE HOTARAREA 5039/15.10.2021 EMISA DE CATRE TRIBUNALUL BUCURESTI DISPUNE CA CONTRACTUL ESTE REZILIAT DE PLIN DREPT IN BAZA REZILIERII PENTRU LIPSA GARANTIE DE BUNA
EXECUTIE LUCRARI MURES - CLUJ - ORADEA SRL & SC TOTAL ROAD SRL -CONTRACT REZILIAT
(2A3 CHETANI - CAMPIA TURZII) REZILIERII REZILIERII CONTRACTULUI DE ESTIMATA CONTRACT) EXECUTIE.
PROIECTARE SI EXECUTIE - IN DATA DE 04.11.2021 CNAIR SA A PRELUAT AMPLASAMENTUL DE LA ANTREPRENORUL STRACO GRUP SRL
CONTRACT REZILIAT CTR PROIECTARE SI EXECUTIE - PROCEDURA DE ATRIBUIRE CONTRACT IN DERULARE
AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI AUTOSTRADA DE CENTURA A 466.28 MIL. LEI FARA
5 AUTOSTRADA 39+000 47+600 SECTOR NORD LOT 3 8,5 0% 0% 2021 2024 ESTIMAT TRIM. IV 2024 A FOST DEPUSA CONTESTATIE LA CNSC IN URMA DESEMNARII OFERTATNTULUI CASTIGATOR.
EXECUTIE LUCRARI MUNICIPIULUI BUCURESTI (A0) TVA
IN DATA DE 31.12.2021 CNAIR A COMUNICAT REZULTATUL PROCEDURII DE ATRIBUIRE A CONTRACTULUI PENTRU PROIECTAREA SI EXECUTIA SECTIUNII 2 A AUTOSTRAZII SIBIU – PITESTI,
BOITA – CORNETU.
OFERTANTUL DESEMNAT CASTIGATOR ESTE ASOCIEREA MAPA INSAAT VE TICARET A.S. - CENGIZ INSAAT SANAYI VE TICARET A.S., CU PRETUL DE 4.250.006.315,00 LEI FARA TVA.
DURATA DE PROIECTARE SI EXECUTIE A ACESTEI SECTIUNI ESTE DE 68 LUNI, DIN CARE 18 LUNI DURATA DE PROIECTARE SI 50 DE LUNI DURATA DE EXECUTIE LUCRARI.
DURATA DE GARANTIE A LUCRARILOR ESTE DE 120 DE LUNI.
Asocierea Mapa Insaat Ve Ticaret AS - Cengiz Insaat Sanayi Ve SECTIUNEA 1: SIBIU - BOITA,
AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI SECTIUNEA 1, LOT 2 SI TRASEUL ARE O LUNGIME DE 31.33 KM.
7 AUTOSTRADA AUTOSTRADA SIBIU - PITESTI 13+170 44+500 Ticaret AS. - OFERTANT CASTIGATOR/ CTR IN CURS DE LOT 2 SI SECTIUNEA 2: BOITA - 31,33 0% 0% 2022 2025 ANUL 2025 4,25 MLD. LEI FARA TVA
EXECUTIE LUCRARI SECTIUNEA 2 SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE.
SEMNARE CORNETU
ACEASTA SECTIUNE CONTINE URMATOARELE LUCRARI PRINCIPALELE:
•
49 DE PODURI SI VIADUCTE
•
7 TUNELURI CU LUNGIMI CUPRINSE INTRE 250 M SI 1590 M
•
ECODUCT IN ZONA LOCALITATII LAZARET
SEMNAREA CONTRACTULUI DE ACHIZITIE PUBLICA VA FI POSIBILA DUPA FINALIZAREA PROCESULUI DE AVIZARE A ACESTUIA.
IN DATA DE 27 OCTOMBRIE 2021, CNAIR SA A FINALIZAT PROCESUL DE EVALUARE A CANDIDATURILOR DEPUSE IN CADRUL PROCEDURII DE ATRIBUIRE PROIECTARE SI EXECUTIE LUCRARI
PENTRU OBIECTIVUL MAJOR DE INVESTITII AUTOSTRADA LUGOJ –DEVA (A1), LOT 2: KM 27+620 - KM 56+220 - SECTIUNEA E SI FINALIZARE SECTIUNEA D.
IN URMA APLICARII CRITERIILOR DE SELECTIE, CONFORM ALGORITMULUI DE CALCUL AFERENT, S-AU CALIFICAT, PE PRIMELE 6 LOCURI, URMATORII OFERTANTI:
1560.50 MIL LEI FARA
1.ASOCIEREA MAPA INSAAT VE TICARET A.S. - CENGIZ INSAAT SANAYI VE TICARET A.S.
1. FINALIZAT SECT. A - C (KM TVA - REPREZINTA VAL
2.
ASOCIEREA SC ALSİM ALARKO SANAYİ TESİSLERİ VE TİCARET A.S - MAKYOL INSAAT SANAYI TURIZM VE TICARET A.S.
MARGINA - HOLDEA 28.6 (9.13 KM 27+620 - KM 43+060); ESTIMATA TOTALA,
3.KOLIN INSAAT TURIZM SANAYI VE TICARET ANONIM SIRKETI
AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI SECTIUNEA E (KM 47+090 - KM SECTIUNEA E SI 2. SECTIUNEA E SI REST DE CARE CONTINE ATAT
9 AUTOSTRADA AUTOSTRADA LUGOJ - DEVA 27+620 56+220 LOT 2 27.11.2013 2026 4.STRABAG SRL
EXECUTIE LUCRARI 56+220) SI FINALIZARE FINALIZARE SECTIUNE EXECUTAT DIN SECTIUNEA D VAL ESTIMATA A
5.
ASOCIEREA IMPRESA PIZZAROTTI & C SPA – PIZZAROTTI SA - RETTER PROJECTMANAGEMENT SRL
SECTIUNEA D D) (KM 43+060 - KM 56+220) - LUCRARILOR, CAT SI VAL
6.ASOCIEREA TERNA TOURIST TECHNICAL AND MARITIME SA - INTRACOM CONSTRUCTIONS SOCIETE ANONYME TECHNICAL AND STEEL CONSTRUCTIONS (INTRAKAT)
ESTIMAT DECEMBRIE 2023 POSIBILELOR LUCRARI
NOI SIMILARE
IN PERIOADA IMEDIAT URMATOARE, AUTORITATEA CONTRACTANTA VA TRANSMITE INVITATIA DE PARTICIPARE LA ETAPA A II-A A PROCEDURII DE ATRIBUIRE - ETAPA DE DEPUNERE A
OFERTELOR CANDIDATILOR ANTEMENTIONATI.
TERMENUL PENTRU DEPUNEREA OFERTELOR A FOST STABILIT PENTRU 31.01.2022.
1.3. AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) - IANUARIE 2022
STADIUL FINANCIAR
Nr. crt. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) PANA LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII
ACTUAL
IN DATA DE 08.04.2021 A FOST SEMNAT CONTRACTUL DE SERVICII COMPLETARE/ REVIZUIRE/ ACTUALIZARE STUDIU DE FEZABILITATE SI ELABORARE P.A.C., P.A.D. SI P.T.E. PENTRU
OBIECTIVUL „AUTOSTRADA TARGU-NEAMT – IASI – UNGHENI” CU SC CONSITRANS S.R.L.
PRETUL CONTRACTULUI ESTE DE 58.830.448,35 LEI FARA TVA
58.83 MIL. LEI FARA TVA
IN DATA DE 07.05.2021 A AVUT LOC SEDINTA DE INCEPUT
2021 - SERVICII DE (VALOARE CONTRACT
ANUL 2025 - PERIOADA ESTIMATA IN DATA DE 08.10.2021 A FOST INAINTATA DOCUMENTATIA ANALIZA MULTICRITERIALA ETAPA 1 REVIZIA 1. ACEASTA A FOST ANALIZATA DE CATRE EXPERTII JASPERS, IN DATA DE 21.12.2021
AUTOSTRADA TARGU NEAMT - IASI - TARGU NEAMT - IASI (LETCANI) - PROIECTARE FAZA S.F. + P.A.C. 2023 - FINALIZARE PROIECTARE COMPLETARE/REVIZUIR
4 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA 0+000 100+140 SC CONSITRANS S.R.L. 100,14 DESCHIDERE TRAFIC PENTRU A FOST EMIS DOCUMENTUL GUIDANCE NOTE NR. 1. IN PREZENT FIIND IN CURS DE REVIZUIRE DE CATRE PRESTATOR.
UNGHENI UNGHENI + P.T.E. SECTIUNE TARGU E/ACTUALIZARE S.F. SI
PRIMELE SECTIUNI
NEAMT - IASI-UNGHENI ELABORARE P.A.C. +
DURATA DE REALIZARE A SERVICIILOR DE PROIECTARE ESTE DUPA CUM URMEAZA:
P.A.D. + P.T.E)
12 LUNI PENTRU REALIZAREA STUDIULUI DE FEZABILITATE;
5 LUNI PENTRU REALIZAREA PROIECTULUI PENTRU AUTORIZAREA EXECUTARII LUCRARILOR DE CONSTRUIRE (PAC) SI OBTINEREA AUTORIZATIEI DE CONSTRUIRE;
5 LUNI PENTRU REALIZAREA PROIECTULUI TEHNIC DE EXECUTIE (PTE)
TRIM. I 2022/ FINALIZARE CONTRACT REVIZUIRE STUDIU DE FEZABILITATE IN DERULARE - STUDIUL DE FEZABILITATE A FOST AVIZAT IN CADRUL CTE, PROCEDURA DE MEDIU IN DERULARE
CONSITRANS ORDIN DE INCEPERE FINALIZARE PROIECTARE (EMITERE
5 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA SIBIU - BRASOV 0+000 68+050 SIBIU - FAGARAS LOT 1 68,05 22,00% PROIECTARE FAZA REVIZUIRE 5170 MIL. LEI FARA TVA 17.12.2021 – S-A AVIZAT IN CTE -CNAIR – STUDIUL DE FEZABILITATE; AVIZ NR. 5139
(VALOARE CONTRACT PROIECTARE: 16.313.855,49 FARA TVA) 11.05.2015 ACORD DE MEDIU) - TRIM. I 2022
STUDIU DE FEZABILITATE 29.12.2021 - S-A AVIZAT IN CTE -MTI – STUDIUL DE FEZABILITATE; AVIZ NR. 88/96
IN DATA DE 23.08.2021, CNAIR A SEMNAT CONTRACTUL PENTRU „COMPLETARE STUDIU DE FEZABILITATE ȘI PROIECT TEHNIC PENTRU ""AUTOSTRADA BRAȘOV - FĂGĂRAȘ”, CU OFERTANTUL
DECLARAT CÂȘTIGĂTOR ASOCIEREA SEARCH CORPORATION S.R.L. - PROTELCO S.A. - LIKE CONSULTING S.R.L. – MEGA MUHENDISLIK MUSAVIRLIK A.S. (MEGA ENGINEERING CONSULTING
INC.).
VALOAREA CONTRACTULUI ESTE DE 18.174.952,71 LEI FĂRĂ TVA.
SURSA DE FINANȚARE: POIM 2014-2020
CONTRACTUL DE SERVICII ESTE STRUCTURAT ASTFEL:
• ETAPA I: 25 LUNI
2022 - FINALIZARE INTEGRALA STUDIU DE FEZABILITATE: 22 LUNI
A PROIECTARII, REAPROBARE PROIECT PENTRU AUTORIZAREA EXECUTĂRII LUCRĂRILOR DE CONSTRUIRE (P.A.C.) ȘI
ASOCIEREA SEARCH CORPORATION S.R.L. - PROTELCO S.A. - INDICATORI TEHNICO - ASISTENȚĂ TEHNICĂ ACORDATĂ BENEFICIARULUI PENTRU SUSŢINEREA APLICAŢIEI DE FINANŢARE: 3 LUNI
2025 - ESTIMARE FINALIZARE
6 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA SIBIU - BRASOV 0+000 48+410 LIKE CONSULTING S.R.L. – MEGA MUHENDISLIK MUSAVIRLIK FAGARAS - BRASOV LOT 2 48,41 0% 0% ECONOMICI AI INVESTITIEI 2025 18.17 MIL LEI FARA TVA • ETAPA II: 6 LUNI
LUCRARI
A.S. (MEGA ENGINEERING CONSULTING INC.) 2022 - LANSARE PROCEDURA PROIECT TEHNIC (P.T.): 3 LUNI
DE ATRIBUIRE CTR ASISTENȚĂ TEHNICĂ ACORDATĂ BENEFICIARULUI PENTRU PROCEDURA DE ATRIBUIRE A EXECUŢIEI LUCRĂRILOR: 2 LUNI
PROIECTARE SI EXECUTIE RAPORT FINANCIAR FINAL: 1 LUNĂ.
• ETAPA III: 36 LUNI
ASISTENȚĂ TEHNICĂ ACORDATĂ BENEFICIARULUI PE DURATA EXECUŢIEI LUCRĂRILOR, CU CONDIŢIA DEMARĂRII LUCRĂRILOR NU MAI TÂRZIU DE 3 ANI DE LA APROBAREA PROIECTULUI
TEHNIC.
TRASEUL ARE O LUNGIME DE 48.1 KM
IN DATA DE 15.09.2021 S-A DAT ORDINUL DE INCEPERE.
IN PERIADA 07-08.12.2021 A AVUT LOC VIZITA IN AMPLASAMENT PENTRU IDENTIFICAREA TERENULUI CAT SI A EVENTUALELOR CONSTRANGERI APARUTTE IN INTERVALUL 2008-2021.
PRESTATORUL LUCREAZA LA FINALIZAREA AMC 1-ANALIZA CONSTRAGERILOR.
IN DATA DE 28.05.2019 A FOST SEMNAT CONTRACTUL DE SERVICII 92/36788 AFERENT „COMPLETARE STUDIU DE FEZABILITATE PENTRU AUTOSTRADA TARGU MURES – TARGU NEAMT”.
TERMEN INITIAL DE FINALIZARE A REVIZUIRII STUDIULUI DE FEZABILITATE - 25.01.2021.
CONTRACT DE REVIZUIRE SF IN DERULARE
IN DATA DE 02.12.2021 A FOST SEMNAT ADITIONALUL NR. 3, PRIN CARE SE PRELUNGESTE TERMENUL DE FINALIZARE AL SERVICIILOR DE PROIECTARE PANA CU 118 ZILE.
TERMEN DE FINALIZARE CONFORM ACT ADITIONAL - 04.04.2022
IN DATA DE 05.11.2020 A FOST AVIZAT TRASEUL FINAL IN COMISIA CTE CNAIR.
IN DATA DE 27.01.2021 A FOST APROBAT STUDIU TOPOGRAFIC. MASURATORI TOPOGRAFICE CU TEHNOLOGIA LIDAR
- IN DATA DE 25.03.2021 A FOST APROBAT STUDIUL GEOTEHNIC AFERENT TRONSON: DITRAU - TARGU NEAMT, SECTOR 4 KM 95+600 – KM 118+800.
ANUL 2022 - FINALIZARE
- AU FOST FINALIZATE INVESTIGATIILE IN SITU PE JUD. MURES, JUD. HARGHITA SI JUD NEAMT SI AU FOST APROBATE STUDIILE ARHEOLOGICE ETAPA 2 JUD. MURES, JUD. HARGHITA SI JUD
04.04.2022 (CONFORM ACT PROIECTARE
AUTOSTRADA TARGU MURES - PROIECTANT: INGENIERIA ESPECIALIZADA OBRA CIVIL E NEAMT. DE ASEMENEA AU FOST OBTINUTE AVIZELE DIRECTIILOR JUDETENE DE CULTURA MURES, HARGHITA SI NEAMT. - STUDIU ARHEOLOGIC FINALIZAT
7 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA 0+000 211+000 TARGU MURES - TARGU NEAMT LOT 1 211 92% 11% 28.05.2019 ADITIONAL LA CTR DE 2026 - PERIOADA ESTIMATA 17.58 MIL. LEI FARA TVA
TARGU NEAMT INDUSTRIAL SA - AU FOST FINALIZATE FORAJELE GEOTEHNICE SI INVESTIGATII GEOFIZICE.
PRESTARI SERVICII) PENTRU DESCHIDEREA PRIMELOR
- IN DATA DE 10.11.2021 A FOST SOLICITATA DE CATRE CNAIR S.A. INCETAREA PROCEDURII DE OBTINERE A ACORDULUI DE MEDIU DEMARATA INITIAL.
SECTIUNI
- IN PERIOADA 08-11.11.2021 AU FOST INAINTATE NOTIFICARILE PRIVIND DEMARAREA PROCEDURII DE OBTINERE A ACORDULUI DE MEDIU, IN CONFORMITATE CU PROPUNEREA DE
FINANTARE DIN PNRR PENTRU AUTOSTRADA TARGU MURES – TARGU NEAMT, SECTIUNEA I TARGU MURES – MIERCUREA NIRAJULUI SI LEGATURA LA AUTOSTRADA A3 (2,400KM) SI
SECTIUNEA III LEGHIN – TARGU NEAMT.
- IN DATA DE 07.12.2021 A FOST INAINTATA DOCUMENTATIA STUDIU DE FEZABILITATE PENTRU AUTOSTRADA TARGU MURES - TARGU NEAMT_REV 3, PENTRU CARE AU FOST EMISE
OBSERVATII IN DATA DE 28.12.2021.
- IN DATA DE 27.12.2021 AU FOST INAINTATE DOCUMENTATIILE PENTRU INTOCMIREA PROTOCOLULUI CU ADMINISTRATIA NATIONALA APELE ROMANE PENTRU SECTIUNEA I TARGU MURES
– MIERCUREA NIRAJULUI SI LEGATURA LA AUTOSTRADA A3 (2,400KM) SI SECTIUNEA III LEGHIN – TARGU NEAMT.
FINANTAREA INVESTITIEI - SE VA FACE PENTRU SECTOARELE I SI III DIN PNRR, FIIND NECESARA CONCENTRAREA RESURSELOR PENTRU FINALIZAREA IN TERMENELE IMPUSE
A FOST AVIZAT IN CADRUL CTE CNAIR STUDIUL SI RAPORTUL ALTERNATIVELOR DE TRASEU (AMC 1 SI AMC 2)
A FOST AVIZAT IN CADRUL COMISIEI TEHNICE PENTRU SIGURANTA CIRCULATIEI NODURILE RUTIERE SI DOTARILE AUTOSTRAZII.
CONSITRANS - CONTRACT ELABORARE SF SI PT ORDIN DE INCEPERE A FOST INAINTAT IN DATA DE 21.09.2021 STUDIUL DE FEZABILITATE FINAL.
1270.62 MIL. LEI FARA
10 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA BUZAU - FOCSANI 0+000 82+440 (VALOARE CONTRACT PROIECTARE: 13.933.291,10 LEI, FARA BUZAU - FOCSANI 82,44 55,00% 12.11.2018 - ETAPA 2022 FINALIZARE 2022 PRESTATORUL A PREDAT IN DATA DE 17.09.2021 STUDIUL GEOTEHNIC FINAL
TVA
TVA) PROIECTARE A FOST INAINTAT PROIECTULUI TEHNIC IN DATA DE 18.10.2021.
A FOST AVIZAT STUDIUL DE FEZABILIATE IN CTE CNAIR, CTE MTI.
A FOST OBTINUT ACORDUL DE MEDIU.
VALORI ESTIMATE:
SECTIUNEA 6, CONEXIUNE DN 2.099 MIL. LEI FARA TVA
73C CU AUTOSTRADA SIBIU - - TIGVENI - CURTEA DE
ANUL 2023 - FINALIZARE
12 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA SIBIU - PITESTI 44+800 68+000 PITESTI (NOD TIGVENI) SI SECTIUNEA 6 23,2 0% 0% 2022 2023 ARGES
PROIECTARE
MODERNIZARE DN 73C (KM 3.926 MIL. LEI FARA TVA
44+800 – KM 68+000) - AUTOSTRADA SIBIU -
PITESTI
CONTRACT IN DERULARE.
S-AU EFECTUAT VIZITE IN TEREN CU REPREZENTANTI DIN PARTEA BENEFICIARULUI SI DIN PARTEA PRESTATORULUI PENTRU IDENTIFICAREA EVENTUALELOR CONSTRANGERI.
2021 - DEMARARE SERVICII DE 2023 - FINALIZARE SERVICII DE
PLOIESTI - BRASOV (FARA 1000.8 MIL. LEI FARA A FOST APROBAT DE CATRE BENEFICIAR RAPORTUL DE PROGRES NR. 5.
13 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA PLOIESTI - BRASOV SC CONSITRANS S.R.L. 97,3 0% 0% PROIECTARE FAZA S.F. + P.A.C. PROIECTARE FAZA S.F. + P.A.C.
SECTOR RASNOV - CRISTIAN) TVA AU FOST APROBATE TEME DE PROIECTARE PENTRU STUDIUL ARHEOLOGIC PRELIMINAR, STUDIUL TOPOGRAFIC SI PENTRU STUDIUL GEOTEHNIC PRELIMINAR.
+ P.T.E. + P.T.E.
AU FOST TRANSMISE OBSERVATII PRESTATORULUI LA STUDIUL GEOTEHNIC PRELIMINAR SI LA STUDIUL ARHEOLOGIC PRELIMINAR.
IN DATA DE 13.12.2021 A FOST PREDATA DOCUMENTATIA AMC 1, IAR IN DATA DE 31.12.2021 SI 04.01.2022 AU FOST FORMULATE OBSERVATII ASUPRA DOCUMENTATIEI.
2.1. DRUMURI DE MARE VITEZA IN FAZA PROIECTARE (SF, PT) - IANUARIE 2021
STADIUL FINANCIAR
Nr. crt. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) PANA LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII
ACTUAL
IN DATA DE 10.03.2021, CNAIR A SEMNAT CONTRACTUL PENTRU ELABORARE STUDIU DE FEZABILITATE DRUM DE MARE VITEZA VITEZA BAIA MARE - SUCEAVA, LOT 2 BISTRITA - VATRA
DORNEI CU OFERTANTUL SC EXPLAN SRL., CU O VALOARE DE 15.793.026,12 LEI FARA TVA.
DRUM DE MARE VITEZA BAIA MARE - 15.8 MIL LEI FARA TVA
IN DATA DE 08.11.2021 A FOST TRANSMISA ADRESA DE APROBARE A DOCUMENTATIEI ANALIZA MULTICRITERIALA 1 REVIZIA 1.
2 DRUMURI DE MARE VITEZA IN FAZA PROIECTARE (SF, PT) DRUM DE MARE VITEZA DEJ - BISTRITA - VATRA DORNEI - 145+000 228+000 SC EXPLAN SRL BISTRITA - VATRA DORNEI LOT 2 83 2021 2023 ANUL 2023 (VALOARE CONTRACT
IN DATA DE 26.11.2021 A FOST EMIS AVIZUL CTE CNAIR 5120 PRIN CARE A FOST AVIZATA DOCUMENTATIA ANALIZA MULTICRITERIALA ETAPA 1.
SUCEAVA ELABORARE S.F.)
IN DATA DE 03.12.2021 A FOST INAINTATA DOCUMENTATIA ANALIZA MULTICRITERIALA ETAPA 2. ACEASTA FIIND APROBATA IN DATA DE 22.12.2021.
IN DATA DE 05.01.2022 A FOST EMIS AVIZUL CTE CNAIR 5147 PRIN CARE A FOST AVIZATA DOCUMENTATIA ANALIZA MULTICRITERIALA ETAPA 2.
IN DATA DE 10.03.2021, CNAIR A SEMNAT CONTRACTUL PENTRU ELABORARE STUDIU DE FEZABILITATE DRUM DE MARE VITEZA BAIA MARE - SUCEAVA, LOT 3 VATRA DORNEI – SUCEAVA CU
DRUM DE MARE VITEZA BAIA MARE - 14.48 MIL LEI FARA TVA ASOCIEREA BEST CONSULTING & DESIGN SRL – INGENIERIA ESPECIALIZADA OBRA CIVIL E INDUSTRIAL, CU PRETUL DE 14.475.000,00 LEI FARA TVA.
ASOCIEREA BEST CONSULTING & DESIGN S.R.L. – INGENIERIA
3 DRUMURI DE MARE VITEZA IN FAZA PROIECTARE (SF, PT) DRUM DE MARE VITEZA DEJ - BISTRITA - VATRA DORNEI - 228+000 335+000 VATRA DORNEI-SUCEAVA LOT 3 107 2021 2023 ANUL 2023 (VALOARE CONTRACT IN DATA DE 01.11.2021 A FOST INAINTATA ANALIZA MULTICRITERIALA ETAPA 1, PENTRU ACEASTA FIIND EMISE OBSERVATII IN DATA DE 04.11.2021.
ESPECIALIZADA OBRA CIVIL E INDUSTRIAL S.A.
SUCEAVA ELABORARE S.F.) AU FOST SOLICITATE PUNCTELE DE VEDERE ALE AUTORITATILOR LOCALE PRIVIND VARIANTELE CLASATE PE PRIMELE 2 POZITII.
IN DATA DE 20.12.2021 A FOST INAINTATA ANALIZA MULTICRITERIALA ETAPA 1_REV 1, PENTRU ACEASTA FIIND EMISE OBSERVATII IN DATA DE 12.01.2022
3. DRUMURI EXPRES
STADIUL FINANCIAR
Nr. crt. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) PANA LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII
ACTUAL
IN DATA DE 15.04.2021, CNAIR A SEMNAT CONTRACTUL PENTRU "PROIECTAREA SI EXECUTIA DRUMULUI EXPRES BRAILA - GALATI” CU ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE
ORDIN DE INCEPERE
ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L.
01.07.2021 - ETAPA
VALOAREA CONTRACTULUI ESTE DE 371.416.131,09 LEI FARA TVA.
ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - PROIECTARE, 371.42 MIL. LEI FARA
1 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES DRUM EXPRES BRAILA - GALATI 0+000 10+770 BRAILA - GALATI LOT 1 10,77 0% 0% MAI 2024 ANUL 2024 SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE.
SPEDITION UMB - TEHNOSTRADE S.R.L. 10.01.2022 TVA
DURATA CONTRACTULUI ESTE DE 34 LUNI, DIN CARE 10 LUNI PERIOADA DE PROIECTARE SI 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR. PERIOADA DE GARANTIE ESTE DE 120 DE LUNI.
INCEPERE EXECUTIE LUCRARI
A FOST AVIZAT PTE IN CADRUL CTE CNAIR SA IN LUNA NOV. 2021
IN BAZA AC 76/24.12.2022
A FOST OBTINUTA AC NR. 76/24.12.2021 ETAPA I, KM 2+880-KM 9+640
SECTOR 1: 0+000 - 1+850
IN DATA DE 03.07.2020 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE.
INCEPAND CU DATA DE 13.07.2020 A FOST EMIS ORDINUL DE INCEPERE EXECUTIE LUCRARI
27.12.2018 - PROIECTARE;
16.09.2019 - EXECUTIE SECTOR
SECTOR 2: 1+850 - 10+000
TRONSON 1 - CRAIOVA - SECTOR 1: 0+000 - 1+800 3;
DRUM EXPRES CRAIOVA - PITESTI 358.18 MIL. LEI FARA IN DATA DE 22.02.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE.
2 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES 0+000 17+700 TIRRENA SCAVI S.P.A. (ITALIA) ROBANESTI SECTOR 2: 1+800 - 10+000 17,7 42,77% 37,47% 13.07.2020 - EXECUTIE SECTOR TRIM IV 2022 ANUL 2022
TVA INCEPAND CU DATA DE 01.03.2021 A FOST EMIS ORDINUL DE INCEPERE EXECUTIE LUCRARI
(KM 0+000 - KM 17+700) SECTOR 3: 10+000 - 17+700 1;
01.03.2021 - EXECUTIE SECTOR
SECTOR 3: 10+000 - 17+700 – IN EXECUTIE
2 - km 5+245 - km 10+000
IN DATA DE 22.05.2019 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE PENTRU SUPRAFETELE AFERENTE DOMENIUL PUBLIC. IN DATA DE 05.07.2019 A FOST OBTINUTA AUTORIZATIA DE
CONSTRUIRE.
INCEPAND CU DATA DE 16.09.2019 A FOST EMIS ORDINUL DE INCEPERE EXECUTIE LUCRARI.
21.12.2018 - ACTIVITATEA DE
TRONSON 2 - ROBANESTI -
PROIECTARE, 24.09.2019 -
DRUM EXPRES CRAIOVA - PITESTI ASOCIEREA SA & PE CONSTRUCT SRL - SC SPEDITION UMB SRL PIATRA OLT (KM 17+700 - KM LOT 1: KM 17+700 - KM 661.45 MIL. LEI FARA
3 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES 17+700 36+200 18,5 92,55% 79,95% EXECUTIE (ETAPELE I, II SI III), TRIM II 2022 ANUL 2022
- SC TEHNOSTRADE SRL - SC CONSITRANS SRL 57+550) 36+200 TVA
21.11.2019 - EXECUTIE (ETAPA
Lot 1 km 17+700 - km 36+200
IV)
21.12.2018 - ACTIVITATEA DE
TRONSON 2 - PIATRA OLT -
PROIECTARE, 24.09.2019 -
DRUM EXPRES CRAIOVA - PITESTI ASOCIEREA SA & PE CONSTRUCT SRL - SC SPEDITION UMB SRL VALEA MARE (KM 17+700 - LOT 2: KM 36+200 - KM 792.18 MIL. LEI FARA
4 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES 36+000 57+500 21,35 93,72% 78,05% EXECUTIE (ETAPELE I, II SI III), TRIM II 2022 ANUL 2022
- SC TEHNOSTRADE SRL - SC CONSITRANS SRL 57+550) 57+550 TVA
21.11.2019 - EXECUTIE (ETAPA
Lot 2 - km 36+200 - km 57+550
IV)
ANTREPRENORUL A CONSTITUIT GARANTIA DE BUNA EXECUTIE, IN CONFORMITATE CU PREVEDRILE CONTRACTUALE, ACEASTA FIIND APROBATA DE CATRE C.N.A.I.R. S.A. IN DATA DE
02.09.2021.
ASOCIEREA SA & PE CONSTRUCT SRL - SC SPEDITION UMB SRL TRONSON 4 617.08 MIL. LEI FARA DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE:
5 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES DRUM EXPRES CRAIOVA - PITESTI 89+300 121+115 TRONSON 4 31,82 0% 0% 15.11.2021 2024 ANUL 2024
- SC TEHNOSTRADE SRL COLONESTI - OARJA - PITESTI TVA • 12 LUNI PERIOADA DE PROIECTARE,
• 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,
• 120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.
INCEPAND CU DATA DE 15.11.2021 A FOST EMIS ORDIN DE INCEPERE.
ANTREPRENORUL A CONSTITUIT GARANTIA DE BUNA EXECUTIE, IN CONFORMITATE CU PREVEDRILE CONTRACTUALE, ACEASTA FIIND APROBATA DE CATRE C.N.A.I.R. S.A. IN DATA DE
10.11.2020.
3.2. DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) - IANUARIE 2022
STADIUL FINANCIAR
Nr. crt. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) PANA LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII
ACTUAL
IN CURS DE ANALIZA AMC ETAPA 1 (TRANSMIS IN DATA DE 15.03.2021 SI RETRANSMIS IN DATA DE 11.05.2021) DE CATRE REPREZENTANTII JASPERS.
INGINERIA ESPECIALIZADA OBRA CIVIL E INDUSTRIAL SA - SE ASTEAPTA RASPUNS DIN PARTEA MTI CA ADRESA CNAIR SA TRANSMISA IN DATA DE 07.05.2021 REFERITOARE LA OPORTUNITATEA / NECESITATEA REALIZARII IN CADRUL PROIECTULUI A
CONTRACT PROIECTARE (ELABORARE STUDIU DE UNOR DRUMURI DE LEGATURA CU PTF ISACCEA.
28.02.2022 (TERMEN INITIAL) FEBRUARIE 2023- TERMEN
DRUM EXPRES BRAILA - TULCEA FEZABILITATE SI PROIECT TEHNIC) SEMNAT IN LUNA MAI IUNIE 2020 - ETAPA 1674.75 MIL. LEI FARA IN DATA DE 9.06.2021 A FOST ANALIZATA DOC AMC ETAPA 1 IN SEDINTA CU CONSULTANTII JASPERS. AU FOST FORMULATE OBSERVATII CARE AU FOST TRANSMISE PRESTATORULUI IN DATA
2 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES 0+000 59+700 BRAILA - TULCEA LOT 1 59,7 0% 0% 23.02.2023 (CF AA. NR.3 - FINALIZARE PROIECTARE
(JIJILA - CATALOI) 2020. PROIECTARE TVA DE 16.06.2021.
92/74452/10.09.2021) (CONFORM AA NR. 3)
(VALOARE CONTRACT PROIECTARE: 14.159.206,13 LEI, FARA S-A PROGRAMAT SEDINTA CU EXPERTII JASPERS, REPREZENTANTI DIN PARTEA MTI SI CESTRIN IN DATA DE 26.07.2021 IN VEDEREA CORELARII MODELULUI NATIONAL DE TRANSPORT PENTRU
TVA) OBIECTIVELE DIN ZONA DOBROGEI.
IN VEDEREA DEFINITIVARII DOCUMENTATIE AMC ETAPA 1 TREBUIE DEFINITIVATA LA NIVELUL MTI STRATEGIA REFERITOARE LA OBIECTIVELE DIN ZONA DOBROGEI.
IN DATA DE 19.03.2021 CNAIR A SEMNAT CU OFERTANTUL DECLARAT CASTIGATOR - ASOCIEREA EGIS ROMANIA S.A. – SEARCH CORPORATION S.R.L.
VALOAREA CONTRACTULUI ESTE DE 20.247.133,77 LEI FARA TVA,
SURSA DE FINANTARE: 85% CONTRIBUTIA UNIUNII EUROPENE DIN FONDUL EUROPEAN DE DEZVOLTARE REGIONALA SI 15% CONTRIBUTIE PROPRIRE.
IN DATA DE 16.04.2021 A FOST SEDINTA DE INCEPUT (ORDINUL DE INCEPERE)
TERMENUL DE PREDARE AMC 1 (16.07.2021) A FOST DEPASIT DIN CAUZA UNOR OBIECTIVE SEVESO DEPISTATE IN ZONA DE INTERES A DRUMULUI EXPRES.
IN DATA DE 03.09.2021 PRESTATORUL A TRANSMIS AMC 1.
ORDIN DE INCEPERE IN DATA DE 21.09.2021 AU FOST TRANSMISE PRESTATORULUI OBSERVATII LA AMC 1.
ASOCIEREA EGIS ROMANIA S.A. – SEARCH CORPORATION
4 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES CRAIOVA - TARGU JIU CRAIOVA - TARGU JIU 108 0% 0% 16.04.2021 - ETAPA APRILIE 2023 20.25 MIL LEI FARA TVA IN DATA DE 28.09.2021 A PRESTATORUL A TRANSMIS AMC 1 REVIZUIT.
S.R.L
PROIECTARE IN DATA DE 22.10.2021 A FOST AVIZAT IN CADRUL CTE CNAIR SA-AMC1 VARIANTELE DE TRASEU 3 SI 5 .
IN DATA DE 03.12.2021 PRESTATORUL A TRANSMIS AMC2 .
IN DATA DE 20.12.2021 AU FOST TRANSMISE PRESTATORULUI OBSERVATII LA AMC 2.
IN DATA DE 06.01.2022 PRESTATORUL A TRANSMIS AMC2 REVIZUIT.
IN DATA DE 12.01.2022 UNITATEA DE IMPLEMENTARE A TRANMIS SOLICITAREA CATRE CTE CNAIR S.A. IN VEDEREA PROGRAMARII SEDINTEI PT AVIZARE AMC2.
PRECIZARI SUPLIMENTARE - IN LUNA DECEMBRIE 2021, A FOST APROBATA FINANTAREA ETAPEI DE PREGATIRE (ELABORAREA STUDIULUI DE FEZABILITATE SI A PROIECTULUI TEHNIC) ,
EXECUTIA LUCRARILOR URMAND A INTRA IN SPATIUL FINANCIAR ALOCAT IN CADRUL POT 2021-2027
CONTRACT IN DERULARE.
SEARCH CORPORATION & – MEGA MUHENDISLIK
PRESTATORUL A TRANSMIS DOCUMENTATIA ANALIZA MULTICRITERIALA DE TRASEU.
MUSAVIRLIK A.S. (MEGA ENGINEERING CONSULTING INC.) -
09.10.2022 (TERMEN INITIAL) AU FOST EMISE OBSERVATII DIN PARTEA BENEFICIARULUI SI PRESTATORUL A TRANSMIS DOCUMENTATIA REVIZUITA.
CONTRACT PROIECTARE ELABORARE STUDIU DE AUGUST 2020 – DEMARARE OCTOMBRIE 2022 - TERMEN 1671.37 MIL. LEI FARA
8 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES PLOIESTI - GAESTI 0+000 76+000 PLOIESTI - GAESTI 76 0% 0% 09.01.2023 (CF AA. NR.2 - IN DATA DE 09.04.2021 ANALIZA MULTICRITERIALA ETAPA 1 A FOST AVIZATA IN CADRUL C.T.E. CNAIR.
FEZABILITATE SI PROIECT TEHNIC DE EXECUTIE SEMNAT IN ETAPA DE PROIECTARE FINALIZARE PROIECTARE TVA
92/78399/24.09.2021 ) A FOST SUSPENDAT CONTRACTUL PENTRU O PERIOADA DE 3 LUNI INCEPAND CU DATA DE 18.05.2021.
DATA DE 25.08.2020 (VAL CTR PROIECTARE: 15.86 MIL LEI
IN DATA DE 18.08.2021 A FOST RELUATA ACTIVITATEA DE PROIECTARE.
FARA TVA)
IN PREZENT SE ASTEAPTA DEFINITIVAREA AMC PENTRU OBIECTIVUL PLOIESTI-BRASOV, IN VEDEREA DEFINITIVARII MODULUI DE CONECTARE A CELOR DOUA OBIECTIVE DE INVESTITII.
CONTRACT IN DERULARE.
DOCUMENTATIA ANALIZA MULTICRITERIALA DE TRASEU ESTE REVIZUITA CONFORM OBSERVATIILOR BENEFICIARULUI.
SEARCH CORPORATION SRL - EGIS ROMANIA S.A - EGIS IN DATA DE 14.04.2021 A FOST AVIZATA IN CADRUL CTE-CNAIR SA DOCUMENTATIA AMC ETAPA 1. IN CURS DE ELABORARE DOCUMENTATIA AMC ETAPA 2. IN DATA DE 16.06.2021
INTERNATIONAL SAS. PRESTATORUL A INTAINTAT DOCUMENTATIA AMC ETAPA 2. DOCUMENTATIA AMC ETAPA 2 ESTE IN ANALIZA LA BENEFICIAR.
9 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES SUCEAVA - SIRET 0+000 40+000 CONTRACT PROIECTARE ELABORARE SF SI PROIECT TEHNIC SUCEAVA- SIRET 56,17 0% 0% OCTOMBRIE 2020 OCTOMBRIE 2022 882.9 MIL. LEI FARA TVA DOCUMENTATIA AMC 2 A FOST AVIZATA IN CTE - CNAIR S.A. IN DATA DE 23.07.2021.
SEMNAT IN DATA DE 07.09.2020 (VALOARE CONTRACT DE A FOST OBTINUT CERTIFICATUL DE URBANISM (SV)
PROIECTARE: 10,092,839.13 LEI FARA TVA) IN PREZENT SE REALIZEAZA STUDII GEOTEHNICE.
INVESTIGATIILE GEOTEHNICE AU FOST DEMARATE, IN DATA DE 24.08.2021.
BENEFICIARUL A EMIS ORDINUL DE MOBILIZARE AL UTILAJELOR PREZENTATE IN PT, INCLUSIV UTILAJELE SOLICITATE SPRE APROBARE “SUPLIMENTAR”.
CONTRACTUL IN DERULARE
A FOST TRANSMIS AMC ETAPA 1 SE AFLA IN CURS DE REVIZUIRE CONFORM OBSEVATIILOR BENEFICIARULUI.
SEARCH CORPORATION & EGIS ROMANIA- CONTRACT
PRESTATORUL ANALIZEAZA ETAPIZAREA SI FAZAREA OBIECTIVULUI DE INVESTITII CONFORM CERINTELOR CNAIR SI MTI. IN DATA DE 09.06.2021 PRESTATORUL A INTAINTAT DOCUMENTATIA
PROIECTARE ELABORARE STUDIU DE FEZABILITATE SEMNAT
AUGUST 2020 DEMARARE OCTOMBRIE 2022 - FINALIZARE OCTOMBRIE 2022 - TERMEN 3563.3 MIL. LEI FARA AMC ETAPA 1. DOCUMENTATIA AMC ETAPA 1 ESTE IN ANALIZA LA BENEFICIAR.
10 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES TISITA - ALBITA 0+000 160+000 IN DATA DE 09.07. 2020 TISITA - ALBITA 160 0% 0%
ETAPA DE PROIECTARE ETAPA DE PROIECTARE FINALIZARE ETAPA DE PROIECTARE TVA DOCUMENTATIA AMC 1 REV 3 ETAPIZARE/FAZARE ESTE IN CURS DE REVIZUIRE IN CONFORMITATE CU OBSERVATIILE BENEFICIARULUI / MTI.
(VALOARE CONTRACT PROIECTARE: 11.057.073,07 LEI FARA
PRESTATORUL A PREDAT AMC 1 REVIZUIT CONFORM OBSERVATIILOR BENEFICIARULUI.
TVA)
IN DATA DE 09.11.2021 MTI A MENTIONAT FAPTUL CA ANALIZELE EFECTUATE NU JUSTIFICA REALIZAREA UNUI DRUM EXPRES INTRE TISITA SI ALBITA.
SE ASTEAPTA DE LA DIRECTIILE SUPORT DIN CADRUL CNAIR SA (DAP) PUNCTUL DE VEDERE REFERITOR LA MODIFICAREA OBIECTULUI CONTRACTULUI.
CONTRACT IN DERULARE.
DOCUMENTATIA REVIZUITA AMC 1 A PRIMIT AVIZUL C.T.E. IN DATA DE 01.04.2021.
DOCUMENTATIA AMC ETAPA 2 A FOST AVIZATA IN CADRUL CTE-CNAIR S.A. IN DATA DE 24.06.2021.
09.06.2022 (TERMEN
PRESTATORUL A INAINTAT DOCUMENTATIA IN VEDEREA OBTINERII CERTIFICATULUI DE URBANISM. NU A FOST OBTINUT CERIFICATUL DE URBANISM (OPBSERVATII PRIMARIA MARACINENI SI
FINALIZARE INITIAL)
INSTITUTUL POMICOL MARACINENI)
09.12.2020 19.07.2022 (CF AA. NR.2 - 222.71 MIL. LEI FARA
12 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES A1 (PITESTI) - MIOVENI 0+000 10+300 SEARCH CORPORATION S.R.L. A1 (PITESTI) - MIOVENI 10,3 0% 0% PRIMARIA UAT MARACINENI A EMIS AVIZ NEFAVORABIL, IA INSTITUTUL POMICOL MARACINENI NU ESTE DE ACORD CU VARIANTA AVIZATA IN CADRUL AMC ETAPA 2, ASTFEL CU A FOST
92/78398/24.09.2021) TVA
RESPINS.
18.10.2022 (CF AA. NR.3 -
IN PREZENT, PRESTATORUL REVIZUIESTE VARIANTA DE TRASEU ASTFEL INCAT AUTORITATILE LOCALE SA FIE DE ACORD CU VARIANTA FINALA.
92/88329/29.10.2021
IN DATA DE 16.11.2021 A FOST REAVIZATA IN CADRUL CTE-CNAIR SA DOCUMENTATIA AMC 2.
IN DATA DE 13.12.2021 A FOST OBTINUT CU EMIS DE CATRE CJ ARGES.
PRESTATORUL A TRANSMIS TEMELE DE PROIECTARE PENTRU DEMARAREA STUDIILOR DE TEREN.
IN DATA DE 02.11.2020, CNAIR A SEMNAT CONTRACTUL NR. 20/5001 PENTRU ELABORARE STUDIU DE FEZABILITATE CU OFERTANTUL SC EXPLAN SRL., CU O VALOARE DE 2.707.123,03 LEI
FARA TVA. STADIUL PROIECTULUI:
15.04.2022 + 55 luni de la
2.707.123,03 LEI FARA - In data de 15.12.2020 s-a aprobat varianta optima de traseu de catre Beneficiar prin aviz CTE DRDP Cluj nr. 62762/15.12.2020 , respectiv in data de 22.12.2020 s-a aprobat prin aviz CTE
Ordin de incepere executie
2020 (ordin de incepere TVA (VALOARE CNAIR SA nr. 5011/22.12.2020.
13 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM DE LEGATURA DRUM DE LEGATURA A3-TURENI 0+000 4+957 SC EXPLAN SRL A3-TURENI 4.957 39,70% 39,70% lucrari pentru Asistenta
nr.57052/09.11.2020) CONTRACT ELABORARE - In data de 01.02.2021 Consiliul Judetean Cluj a emis Certificatul de urbanism nr. 103/01.02.2021, pentru obiectivul de investitie “Drum Expres pentru realizarea conexiunii dintre Autostrada
tehnica (conform AA nr.1
S.F.+PT+DTAC) A3 (zona Turda) si Drum National DN1 (zona Tureni)".
/09.08.2021)
- In data de 13.04.2021 s-au aprobat Studiile de specialitate si investigatii de teren prin adresa DRDP Cluj nr. 17730/13.04.2021.
- In data de 17.06.2021 s-a aprobat Studiul de fezabilitate de catre Beneficiar prin aviz CTE DRDP Cluj nr.29313/17.06.2021.In curs de avizare CTE CNAIR
Drum Expres Bucuresti- S.C. TPF INGINERIE S.R.L. 11.515.926,40 (lei fara
14 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES 0+000 0+060 Bucuresti-Targoviste 60 27.12.2021 27.12.2024 Anul 2021 - ETAPA DE PROIECTARE CONTRACTUL A FOST SEMNAT IN DATA DE 25.11.2021. DURATA CONTRACTULUI ESTE DE 25 DE LUNI DE LA DATA DE INCEPERE. SE ASTEAPTA SEMNAREA GARANTIEI DE BUNA EXECUTIE.
Targoviste TVA)
4. DRUMURI NAȚIONALE
STADIUL FINANCIAR
Nr. crt. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) PANA LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII
ACTUAL
PROBLEME:
DN79 ARAD - ORADEA, KM 4+150 – 266.31 MIL. LEI FARA CONTRACTUL A FOST REZILIAT DE CATRE BENEFICIAR IN DATA DE 02.10.2020 DATORITA INTARZIERILOR SI NEEXECUTARII LUCRARILOR RAMASE DE EXECUTAT DE CATRE ANTREPRENOR.
1 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL 4+150 107+745 ASTALDI S.P.A. 103,55 98% 98% 03.02.2009 REZILIAT IN FOLOSINTA
KM 107+745 TVA 1. NEEXECUTAREA LUCRARILOR PENTRU PODUL DE LA KM 41+635
2. INTARZIEREA FINALIZARII EXECUTIEI LUCRARILOR
MODERNIZARE DN 5,
ASOCIEREA EUROCOGEN - FILIALA ANINOASA SRL & DRUM MODERNIZAT -
BUCURESTI – ADUNATII
5 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN5 7+573 19+220 ALEANDRI SPA & BEOZZO COSTRUZIONI SRL & SMART LUCRARI FINALIZATE IN ANUL 11,647 99,50% 94,60% 23.04.2015 ESTIMAT FEBRUARIE 2022 76.13 MIL. LEI FARA TVA EXECUTIE LUCRARI
COPACENI KM 7+573 - KM
BUILDING PROJET SRL 2020
19+220
RECEPTIE LA TERMINAREA
7 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN76 55+425 69+350 ASOCIEREA SC SYLC CON TRANS SRL/HIDROSTROY AD IONESTI - VARFURILE LOT 3 13,93 99,21% 95,71% 15.03.2019 LUCRARILOR - ESTIMAT 55.95 MIL. LEI FARA TVA RECEPTIE LA TERMINAREA LUCRARILOR - ESTIMAT MARTIE 2022
MARTIE 2022
8 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN56 47+000 84+020 MOCHLOS S.A. GALICEA MARE - CALAFAT LOT 2 33,83 100% 91,43% 03.09.2012 16.06.2021 81.94 MIL. LEI FARA TVA PROCESUL VERBAL DE RECEPTIE LA TERMINAREA LUCRARILOR A FOST APROBAT DE DIRECTORUL GENERAL AL CNAIR IN DATA DE 16.06.2021.
IN DATA DE 29.06.2020 A FOST DEPUSA APLICATIA DE FINANTARE PENTRU ANGAJAREA CHELTUIELILOR AFERENTE ACESTUI PROIECT, DIN FONDURI NERAMBURSABILE, ALOCALTE IN CADRUL
MODERNIZARE DN29D POIM 2014 - 2020
22.06.2020 - EMITERE ORDIN
ASOCIEREA SC AUTOTEHNOROM SRL - SC OPR ASFALT SRL - BOTOSANI - STEFANESTI KM 208.44 MIL LEI FARA CONTRACT PROIECTARE SI EXECUTIE IN DERULARE
12 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN29D 2+800 48+146 45,046 20% 15,00% DE INCEPERE PENTRU ETAPA MARTIE 2023
OBRAS PUBLICAS-Y REGADIOS SA - SC EVALCONS TECH SRL 2+800 – KM 18+500 SI KM TVA IN DATA DE 08.01.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUCTIE
PROIECTARE
18+800 – KM 48+146 TERMEN DE PREDARE A PROIECTULUI TEHNIC DE EXECUTIE: 28.02.2021
PT - AVIZAT CNAIR SA NR. 5035/26.03.2021
CONTRACT SEMNAT IN DATA DE 01.02.2021, CU O PERIOADA CONTRACTUALA DE 2 ANI (6 LUNI PROIECTAREA ȘI 18 LUNI EXECUTIE ) SI ARE O GARANTIE DE 84 DE LUNI. IN DATA DE
DRUM DE LEGATURA INTRE PT - AVIZAT; 99% 189.57 MIL. LEI FARA
18 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN69 0+000 10+000 TODINI COSTRUZIONI GENERALI S.P.A. 9,9 2% 01.03.2021 01.04.2023 ANUL 2023 02.07.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE NR. 35 (NR MTI 26799 DIN 02.07.2021) - ETAPA I. AVIZ CTE CNAIR PAC NR. 5075 DIN 30.06.2021.
DN69 SI AUTOSTRADA A1 PROIECTARE TVA
AVIZ CTE CNAIR - FAZA PTE - NR. 5115 DIN 16.11.2021 .
CONTRACT SERVICII DE
PROIECTARE DERULAT
DRUM TRANSREGIO GILAU - STUDIU DE FEZABILITATE IN ELABORARE
20 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL 0+000 38+800 GILAU - APAHIDA 38,8 IN BAZA UNUI 2345.52 MIL. FARA TVA
APAHIDA FINALIZARE SF - 2022/ INTARZIERI IN GESTIONAREA CTR DE PROIECTARE GESTIONAT DE CATRE PRIMARIA CLUJ NAPOCA
PROTOCOL DE CATRE
UAT CLUJ NAPOCA
S.C. SEARCH CORPORATION S.R.L. - ELABORARE SF / S.C. BEST 109.69 MIL. LEI FARA SF REVIZUIT IN ANUL 2016 / HG NR. 460/28.06.2018 PENTRU APROBAREA INDICATORILOR TEHNICO-ECONOMICI
21 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN24C 106+650 142+250 MANOLEASA - RADAUTI PRUT 35,6 33,63% 0%
CONSULTING & DESIGN S.R.L. BUCURESTI - REVIZUIRE S.F. TVA LIPSA FINANTARE LUCRARI
5. VARIANTE OCOLITOARE
STADIUL FINANCIAR
Nr. crt. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) PANA LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII
ACTUAL
15.01.2019 - PENTRU
LUCRARILE AUTORIZATE PRIN
AC 140/ 20.12.2018 CONTRACTUL DE PROIECTARE SI EXECUTIE PASAJ DOMNESTI A FOST SEMNAT IN DATA DE 10.05.2017 CU NR. DE INREGISTRARE: 92/33009/10.05.2017)
PASAJ SUPRATERAN PE DJ 602 16.09.2019 PENTRU 24 LUNI DE LA EMITEREA AUTORIZATII DE CONSTRUIRE: NR. 140/ 20.12.2018, NR. 69/ 28.08.2019 SI NR. 54/ 23.09.2020
STRACO GRUP SRL - SC COMNORD SRL - SPECIALIST
1 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE CENTURA BUCURESTI CENTURA BUCURESTI DOMNESTI - DJ 602 0,536 57,09% 49,01% LUCRARILE AUTORIZATE PRIN AUTORIZATIEI DE CONSTRUIRE ANUL 2022 91.55 MIL. LEI FARA TVA LUCRARI IN EXECUTIE: RAMPE DIN PAMANT ARMAT, MONTARE TABLIER METALIC GIRATIE SUSPENDATA, MONTARE PREDALE SI LISE MARGINALE PREFABRICATE, ARMARE SI BETONARE
CONSULTING SRL
DOMNESTI AC 69/28.08.2019 (ESTIMAT LUNA 09.2022) SUPRASTRUCTURA OBIECT ST2, INFRASTRUCTURA SI SUPRASTRUCTURA BRETELE DE INTOARCERE PRELUNGIREA GHENCEA, INFRASTRUCTURA BRETELE DE INTOARCERE DOMNESTI, BORDURI
23.09.2020 - PENTRU SI TROTUARE BRETELE DE INTOARCERE PRELUNGIREA GHENCEA, LUCRARI DE CANALIZARE PLUVIALA SI RELOCARI/PROTEJARI RETELE DE UTILITATI.
LUCRARILE AUTORIZATE PRIN
AC 54/23.09.2020
05.12.2018 CONTRACTUL A FOST SEMNAT IN DATA DE 24.10.2018. ORDINUL DE INCEPERE PENTRU PROIECTAREA LUCRARILOR A FOST EMIS.
(DATA DE INCEPERE A A FOST AVIZAT PROIECTUL TEHNIC IN SEDINTA CTE DIN DATA DE 19.06.2020
ASOCIEREA SC TEHNIC ASIST SRL – SC TASS INFRA LOGISTIC 132.051 MIL. LEI FARA
2 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE BARLAD 0+000 11+281 BARLAD 1 11,281 32,00% 22,70% ACTIVITATII DE PROIECTARE) 2022/ INTARZIERI AUTORIZATIE DE CONSTRUIRE A FOST EMISA.
SRL TVA
06.08.2020 - DATA DE ORDINUL DE INCEPERE A LUCRARILOR A FOST EMIS IN DATA DE 06.08.2020
INCEPERE A LUCARILOR) AMPLASAMENTUL LUCRARILOR A FOST PREDAT CATRE ANTREPRENOR IN DATA DE 06.08.2020.
PRETUL PE KM ESTE DE CCA. 20.990.555 LEI FĂRĂ TVA, REPREZENTAND CCA. 4,327,949 EURO FARA TVA.
DURATA CONTRACTULUI ESTE DE 174 DE LUNI, DIN CARE:
ASOCIEREA S.C. SA&PE CONSTRUCT S.R.L. – S.C. SPEDITION 705.28 MIL. LEI FARA
3 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE GALATI 0+000 33+600 GALATI 1 33,6 0% 0% FEBRUARIE 2022 26.aug ANUL 2026 • 12 LUNI PERIOADA DE PROIECTARE,
UMB S.R.L. – S.C. TEHNOSTRADE S.R.L. TVA
• 42 LUNI PERIOADA DE EXECUTIE A LUCRĂRILOR,
• 64 DE LUNI PERIOADĂ DE GARANȚIE A LUCRĂRILOR.
DECEMBRIE 2021 -
30.06.2017 (SERVICII DE CONTRACTUL DE PROIECTARE SI EXECUTIA VARIANTEI DE OCOLIRE SATU MARE A FOST SEMNAT IN DATA DE16.11.2015
DESCHIDERE TRAFIC 4 KM,
ASOCIEREA ITINERA SPA COLLINI LAVORI SPA - VIA DESIGN PROIECTARE) 304.791 MIL. LEI FARA DATA DE INCEPERE A PERIOADEI DE PROIECTARE ESTE 30.06.2017.
4 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE SATU MARE 0+000 19+540 SATU MARE 1 19,54 86,40% 73,04% RESTUL VARIANTEI URMAND A 2022
SRL 28.06.2018 TVA DATA DE INCEPERE EXECUTIE LUCRARi ESTE 28.06.2019-ETAPA I.
FI DESCHISA TRAFICULUI IN
(EXECUTIE LUCRARI) DATA DE INCEPERE EXECUTIE LUCRARI ETAPA II ESTE 02.12.2020
ANUL 2022
VINERI, 16.04.2021, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL PENTRU "CONSTRUCTIA VARIANTEI DE OCOLIRE TECUCI - REST DE EXECUTAT”, CU ASOCIEREA S.C. MAVGO HOLDING S.R.L. – S.C.
ANTREPRIZA DE CONSTRUCTII DRUMURI SI AUTOSTRAZI S.R.L. (FOSTA S.C. AQUA PARC S.R.L.) – S.C. BDU MAXI CONSTRUCT S.R.L. – HYDROSTROY AD.
29.63% - PROGRES 29.63% - PROGRES VALOAREA CONTRACTULUI ESTE DE 41.735.534,38 LEI FARA TVA.
58% - PROGRES FIZIC 58% - PROGRES FIZIC
ASOCIEREA S.C. MAVGO HOLDING S.R.L. – S.C. ANTREPRIZA INREGISTRAT IN INREGISTRAT IN CADRUL SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE.
INREGISTRAT LA DATA INREGISTRAT LA DATA
DE CONSTRUCȚII DRUMURI ȘI AUTOSTRĂZI S.R.L. (FOSTA S.C. CADRUL CONTRACTULUI CONTRACTULUI DE LUCRARI VARIANTA DE OCOLIRE TECUCI ARE O LUNGIME DE 6.945 KM.
7 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE TECUCI 0+000 6+945 TECUCI (RELICITARE) RELICITARE 6,945 REZILIERII REZILIERII 41.74 MIL. LEI FARA TVA
AQUA PARC S.R.L.) – S.C. BDU MAXI CONSTRUCT S.R.L. – DE LUCRARI REZILIAT REZILIAT
28% IN CADRUL NOULUI 24% IN CADRUL NOULUI
HYDROSTROY AD 29.40% IN CADRUL 18.56% IN CADRUL NOULUI VARIANTA SE DESPRINDE DIN DN24, TRAVERSEAZA CU UN PASAJ SUPERIOR DN24 SI LINIA CF MARASESTI - TECUCI LA KM 0+385,95, CONTINUA IN ALINIAMENT PANA LA INTERSECTIA LA NIVEL
CONTRACT CONTRACT
NOULUI CTR CONTRACT CU DJ252H LA KM 2+490, TRAVERSEAZA CU PASAJ SUPERIOR LINIA CF FAUREI - TECUCI LA KM 6+416,29 SI SE FINALIZEAZA LA KM 6+945 (ECHIVALENT CU KM 6+801,29), LA INTERSECȚIA CU
DN25.
PERIOADA CONTRACTUALA DE EXECUTIE A LUCRARILOR ESTE DE 12 DE LUNI, IAR PERIOADA DE GARANTIE ESTE DE 60 DE LUNI.
29.01.2019 - DATA DE
INCEPERE PERIOADA DE PROIECT TEHNIC FINALIZAT
VARIANTA OCOLITOARE TIMISOARA 272.43 MIL. LEI FARA
8 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE 0+000 25+690 TIRRENA SCAVI S.P.A TIMISOARA - SECTOR SUD 25,69 45,00% 46,18% PROIECTARE ESTIMAT 2022 ANUL 2022 AUTORIZATIE DE CONSTRUIRE EMISA IN LUNA MARTIE 2020.
SUD TVA
25.03.2020 - ORDIN - EXECUTIE LUCRARI IN DERULARE.
INCEPERE EXECUTIE LUCRARI
ORDINUL DE INCEPERE A CONTRACTULUI A FOST COMUNICAT CA FIIND 25.09.2020 (PROIECTARE+EXECUTIE). PERIOADA DE PROIECTARE ESTE DE 6 LUNI (FINALIZARE 24.03.2021) SI 24 LUNI
5.535 KM (5 VIADUCTE, EXECUTIE LUCRARI (FINALIZARE 23.03.2023).
VARIANTA OCOLITOARE ZALAU ASOCIEREA SINOHYDRO CORPORATION LIMITED – SC GOOD ETAPA 2 - 7 KM INTRE DN 1F KM 2 PODURI, 2 185.54 MIL. LEI FARA DECIZIA DE EXPROPRIERE NR. 1848 DIN 10.11.2020.
9 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE 0+000 5+535 1 20,00% 17,30% 2020 2023 ANUL 2023
VO DN 1V PROOD S.R.L. 79+625 - DJ 191C INTERSECTII TIP TVA A FOST ACORDATA ANTREPRENORULUI POSESIA SANTIERULUI.
GIRATIE) A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE NR. 17/26.03.2021.
A FOST EMISA HOTARAREA DE GUVERN NR.622 DIN 03.06.2021 PRIVIND SCOATEREA DEFINITIVA DIN FONDUL FORESTIER NATIONAL.
STADIUL FINANCIAR
Nr. crt. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) PANA LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII
ACTUAL
CONTRACTUL DE EXECUTIE LUCRARI A FOST SEMNAT IN DATA DE 20.06.2019/ AUTORIZATIE DE CONSTRUIRE VALABILA.
LUCRARI IN EXECUTIE:
DRUM - LUCRARI DE EXCAVATIE DN4 SI CB, LUCRARI DE UMPLUTURI, EXECUTIE STRAT DE FORMA, EXECUTIE FUNDATIE DIN BALAST,ASTERNERE STRAT DE BALSAT STABILIZAT.
PASAJ - TURNARE BETON EGALIZARE: 31 DE FUNDATII; TURNARE RADIERE: 31 BUC; EXECUTIE ELEVATII PILE: 27 BUC; EXECUTIE ELEVATII CULEE: 4 BUC; EXECUTIE RIGLE: 9 BUC, ARMARE SI
COFRARE 2 BUC, CUZINETI SI ORPITORI SEISMICI SP1A, SP1B SI P2B, P4B, P1B, COFRARE SI ARMARE RIGLE: P2B1, P3, P5B1, APROVIZIONARE APARATE DE REAZEM.
CONSOLIDARI - RAMPA A1: BETON DE EGALIZARE RAMPA A1; RADIERE BETONATE ZID TIP L – 7 BUC; ELEVATII BETONATE ZID TIP L – 6 BUC, EXCAVATIE SEGMENT 2 ZID TIP U, RADIER
LARGIRE LA 4 BENZI A CENTURII
31.07.2019 - DATA DE BETONAT SEGMENT 1 TIP U, ELEVATII BETONATE SEGMENT 1 TIP U; RAMPA A: EXCAVATIE PRIMUL ZID TIP L, BETON DE EGALIZARE ZID TIP L – 7 BUC, RADIERE ZID TIP L, 7 SEGMENTE; ELEVATII
RUTIERE A MUNICIPIULUI AMENAJARE NOD RUTIER LOT
1 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI 29+500 33+190 ITINERA SPA 3,69 40,00% 49,33% INCEPERE PERIOADA DE ESTIMAT 2022 2022 169.5 MIL. LEI FARA TVA ZID TIP L – 4 BUC.
BUCURESTI SUD INTRE A2 KM 1: OLTENITA - DN 4
PROIECTARE RAMPA B: EXECUTATA IN PROPORTIE DE 90 %; MONTARE GEODREN, BETON DE PANTA PE ZIDUL TIP L; RAMPA B1: EXECUTATA IN PROPORTIE DE 75 %; RAMPA BUCURESTI: EXCAVATIE ZID DE
23+600 SI A1 KM 55+520
SPRIJIN TIP L; BETON DE EGALIZARE; RADIERE BETONATE; ELEVATII BETONATE; RAMPA OLTENITA: RADIERE BETONATE ZID DE SPRIJIN TIP L; BETON DE EGALIZARE; RADIERE BETONATE;
ELEVATII BETONATE
RETELE DE UTILITATI - RETEA DE DISTRIBUTIE GAZE NATURALE – INTREGIRE CONDUCTA NOUA DN CB SI BRANSAMENTE NOI, S-A DEVIAT RETEAUA PE NOUL TRASEU PE DN4, KM 1+140 LA KM
1+580, SE PREGATESTE O NOUA CUPLARE PE DN4; RETEA DE TELECOMUNICATII – FINALIZATA, TREBUIE INTOCMIT PV LA TERMINAREA LUCRARILOR; RETEA E-DISTRIBUTIE – S-AU DEVIAT
TRASEELE JT ANTENA VODAFONE SI REMAT SI TRASEU MT 20 kV – PORCINE 1, SE MONTEAZA CABLURILE PE DN 4, PE TRASEELE DE MEDIE TENSIUNE.
RETEA DE CANALIZARE PLUVIALA - RETEA DN 4, REALIZAT APROXIMATIV 2600 M, 83,00%; RETEA CB, REALIZAT APROXIMATIV 1260 M, 32,12 %.
MODERNIZAREA CENTURII
1. CONTRACTUL DE EXECUTIE LUCRARI A FOST SEMNAT IN DATA DE 02.03.2020/ AUTORIZATIE DE CONSTRUIRE VALABILA.
RUTIERE A MUNICIPIULUI 235.75 MIL. LEI FARA
2 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI 12+300 23+750 TIRRENA SCAVI S.P.A SECTIUNEA DN 2 - A2 11,524 12,89% 19,22% 04.05.2020 2022 2022 LUCRARI IN EXECUTIE: RELOCARE RETELE TELECOMUNICATII, RELOCARE RETELE APA-CANAL, DEMOLARE CONSTRUCTII EXPROPRIATE, 1500 MC STRAT DE FORMA DIN BALAST, 1000 MC STRAT
BUCURESTI INTRE A1 - DN7 SI TVA
DE FUNDATIE DIN PIATRA SPARTA, 50 MC DEMOLARE CAP PILOTI FORATI, 100 M REALIZARE RIGOLE, ACTIVITATI GENERALE.
DN2 - A2
STADIUL FINANCIAR
Nr. crt. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) PANA LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII
ACTUAL
14.06.2021 - DATA PUBLICARII ANUNTULUI, 31.08.2021 - DATA DE DEPUNERE A OFERTELOR, 23.11.2021 - DATA FINALIZARE PROCEDURA DE EVALUARE/ IN PREZENT PROCEDURA SE AFLA IN
ETAPA DE EVALUARE A OFERTELOR TEHNICE
de Incepere:
VARIANTE OCOLITOARE IN PREGATIRE FAZA EXECUTIE VARIANTA OCOLITOARE PROCEDURA DE LICITATIE ATRIBUIRE CONTRACT PROIECTARE 293.084 MIL LEI FARA
1 VARIANTA OCOLITOARE 0+000 13+057 SIGHISOARA 13,057 0,00% 0,00% 2022 2022 2024
LUCRARI SIGHISOARA SI EXECUTIE IN DERULARE TVA
Auditului de Siguranta Rutiera – ASR) - 6 luni de la Predare la Supervizor si Beneficiar a Proiectului Tehnic de Execuție si a Detaliilor de Executie;
STADIUL FINANCIAR
Nr. crt. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) PANA LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII
ACTUAL
PENTRU BUNA IMPLEMENTARE A OBIECTIVULUI, A FOST INCHEIAT UN PARTENERIAT ADMINISTRATIV CU PRIMARIA BISTRITA, IN VEDEREA SUSTINERII MODULUI DE CONECTARE IN ZONA
2.33 MIL LEI FARA TVA
MUN. BISTRITA.
1 VARIANTE OCOLITOARE IN PREGATIRE FAZA PROIECTARE VARIANTA OCOLITOARE VARIANTA OCOLITOARE BISTRITA 0+000 15+000 BISTRITA 1 15 (VALOARE ESTIMATA
OBIECTIVUL FACE PARTE DIN ,,AUTOSTRADA NORDULUI” – FIIND SPECIFICAT IN STUDIUL DE FEZABILITATE CA DRUMUL DE MARE VITEZA BAIA MARE-SUCEAVA: LOT 1 BAIA MARE-BISTRITA SI
CONTRACT S.F.)
LOT 2 BISTRITA-VATRA DORNEI, VA INDEPLINI SI FUNCTIA DE VARIANTA DE OCOLIRE PENTRU LOCALITATILE INTERSECTATE DE ACESTA.
CNAIR SA A TRANSMIS CATRE MINISTERUL TRANSPORTURILOR SI INFRASTRUCTURII CEREREA DE FINANTARE PENTRU PROIECTUL: ""ELABORARE STUDIU DE FEZABILITATE, PROIECT TEHNIC DE
EXECUTIE INCLUSIV PAC, DETALII DE EXECUTIE, ASIGURAREA ASISTENTEI TEHNICE PE PARCURSUL EXECUTIEI DE LUCRARI SI IN PERIOADA DE GARANTIE A LUCRARILOR EXECUTATE PENTRU
OBIECTIVUL DE INVESTITIE: DRUM DE LEGATURA PENTRU SPORIREA CAPACITATII DE TRAFIC INTRE DN6 (ZONA UZINEI FORD) SI DRUMUL EXPRES CRAIOVA – PITESTI (TRONSONUL 1)"".
DRUM DE LEGATURA DN6 - DRUM
IN DESFASURARE PROCEDURA DE ACHIZITIE ATRIBUIRE
2 VARIANTE OCOLITOARE IN PREGATIRE FAZA PROIECTARE VARIANTA OCOLITOARE EXPRES CRAIOVA-PITESTI 10
CONTRACT DE PRESTARI SERVICII DE PROIECTARE PROCEDURA DE ACHIZITIE IN DERULARE CU O VALOARE ESTIMATA A CONTRACTULUI DE 1.500.000 LEI INCLUSIV TVA. TERMEN LIMITA DE DEPUNERE A OFERTELOR: 08.09.2021. CELE 2
(TRONSONUL 1)
OFERTE DEPUSE SUNT IN ANALIZA.
DURATA ESTIMATA A PRESTARII SERVICIILOR ESTE DE 89 LUNI (3 LUNI – ELABORARE SF INCLUSIV DOCUMENTATII PENTRU OBTINERE AVIZE/ACORDURI; 2 LUNI – ELABORARE PT INCLUSIV
DTAC SI DE; 24 LUNI – ASISTENTA TEHNICA PE PARCURSUL EXECUTIEI LUCRARILOR; 60 LUNI – ASISTENTA TEHNICA IN PERIOADA DE GARANTIE A LUCRARILOR).
5.5. VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC - IANUARIE 2022
STADIUL FINANCIAR
Nr. crt. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) PANA LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII
ACTUAL
CONTRACT DE SERVICII DE PROIECTARE ACTUALIZARE A STUDIULUI INITIAL INCLUSIV DOCUMENTATII PENTRU AVIZE,OBTINERE AVIZE SI ACORDURI, ELABORARE PROIECT TEHNIC INCLUSIV
DTAC, DETALII DE EXECUTIE SI ASISTENTA TEHNICA PENTRU OBIECTIVUL VARIANTA DE OCOLIRE RM. VALCEA NR. 148 /04.10.2019, CU ORDIN DE INCEPERE ACTIVITATI EMIS IN DATA DE
16.12.2019, IN DERULARE. PRESTATOR SC SEARCH CORPORATION SRL.
VALOAREA CONTRACT PROIECTARE: 3,832,075.75 LEI FARA TVA.
DOCUMENT DE AVIZARE CTE-CNAIR NR. 4915/09.04.2020 - ACTUALIZARE SF - ALTERNATIVE DE TRASEU.
CERTIFICATUL DE URBANISM NR. 12/10054/06.08.2020 EMIS DE C.J. VALCEA ""NU POATE FI UTILIZAT IN SCOPUL DECLARAT"" URMARE A AVIZULUI NEFAVORABIL AL PRIMARIEI ORASULUI
2022 - ETAPA DE PROIECTARE
CALIMANESTI.
VARIANTA OCOLITOARE RAMNICU 2022- DEMARARE PROCEDURA 276.36 MIL. LEI FARA
2 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE 0+000 21+837 SC SEARCH CORPORATION SRL RAMNICU VALCEA PROIECTARE 21,84 30% 0% 16.12.2019 2024 DOCUMENT DE AVIZARE CTE-CNAIR NR. 4992/19.10.2020 - ACTUALIZARE SF - ALTERNATIVE DE TRASEU (AMC ETAPA 4) - VARIANTE PENTRU RACORDAREA LA CENTURA CALIMANESTI.
VALCEA ATRIBUIRE CTR PROIECTARE SI TVA
C.J. VALCEA A EMIS UN NOU CERTIFICAT DE URBANISM, NR. 70/16141/23.11.2020, CARE SPECIFICA FAPTUL CA ""NU POATE FI UTILIZAT IN SCOPUL DECLARAT"" URMARE A AVIZULUI
EXECUTIE
NEFAVORABIL AL PRIMARULUI COMUNEI DAESTI.
DOCUMENT DE AVIZARE CTE-DRDP CRAIOVA NR. 3/20.01.2021 - STUDIUL ALTERNATIVELOR DE TRASEU IN ZONA LOCALITATII FEDELESOIU, COMUNA DAESTI - ETAPA 5. DOCUMENTATIA
TEHNICA A FOST INAINTATA LA CJ VALCEA CARE A EMIS CERTIFICATUL DE URBANISM NR. 05/19899/26.01.2021 CARE ""NU POATE FI UTILIZAT IN SCOPUL DECLARAT"" URMARE A AVIZULUI
NEFAVORABIL AL PRIMARULUI COMUNEI DAESTI. S-A EMIS ORDIN DE SISTARE DIN DATA
DE 29.01.2021. URMARE A DEMERSURILOR DRDP CRAIOVA, LA TRIBUNALUL VALCEA E DESCHIS DOSARUL NR. 2416/90/2021 AVAND CA OBIECT ANULARE ACT ADMINISTRATIV, RECLAMANT:
CNAIR SA PRIN DRDP CRAIOVA, PARAT: PRIMARIA COM. DAESTI PRIN PRIMAR.
STADIU:
7 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE HUSI CONTRACT REVIZUIRE SF IN DERULARE 14,4
CONTRACT IN DERULARE.
IN DATA DE 26.04.2021 PRESTATORUL A TRANSMIS STUDIUL DE PREFEZABILITATE CONFORM GRAFICULUI ACTIVITATILOR. AU FOST FORMULATE OBSERVATII ASUPRA DOCUMENTATIE
STUDIUL DE PREFEZABILITATE. PRESTATORUL A TRANSMIS SPF-UL REVIZUIT.
VARIANTA OCOLITOARE PITESTI VALOARE SPF + SF 2.732
8 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE 0+000 20+000 TPF INGINERIE SRL PITESTI VEST 20 0% 0% A FOST PREDAT STUDIUL DE TRAFIC REVIZUIT. SPF A FOST ANALIZAT IN CADRUL CTE-CNAIR S.A. AU FOST FORMULATE OBSERVATII DE CATRE CTE-CNAIR.
VEST MIL LEI FARA TVA
PRESTATORUL REVIZUIESTE STUDIUL DE PREFEZABILITATE FUNCTIE DE OBSERVATIILE EMISE IN CADRUL SEDINTEI CTE - CNAIR DIN DATA DE 01.09.2021 SI IN CADRUL SEDINTEI DIN 10.11.2021
CU AUTORITATILE LOCALE.
PRESTATORUL A TRANSMIS DOCUMENTATIA REVIZUITA SI SE ASTEAPTA NOTA DE PREZENTARE.
9 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE DOROHOI 0+000 13+900 SC NV CONSTRUCT SRL DOROHOI 13,9 0% 0% 429.22 MII LEI IN CURS DE FINALIZARE STUDIUL DE FEZABILITATE, DUPA APROBARE PUZ DOROHOI
CONTRACT IN DERULARE.
VARIANTA OCOLITOARE TIMISOARA IN DATA DE 20.05.2021 FOST AVIZAT IN CTE CNAIR SA - ANALIZA MULTICRITERIALA ETAPA 1.
10 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE 0+000 13+600 SEARCH CORPORATION SRL TIMISOARA 13,6 18.01.2021 18.04.2022 3.66 MIL. LEI FARA TVA
VEST IN DATA DE 16.11.2021 A FOST AVIZATA IN CADRUL CTE-CNAIR SA DOCUMENTATIA AMC 2.
PRESTATORUL A TRANSMIS TEMELE DE PROIECTARE PENTRU STUDIILE ARHEOLOGIC, TOPOGRAFIC SI STUDIUL GEOTEHNIC.
5.6. VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU AUTORITATILE LOCALE - IANUARIE 2022
STADIUL FINANCIAR
Nr. crt. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) PANA LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII
ACTUAL
OBIECTIVUL A FOST TRANSFERAT CATRE CJ BIHOR IN VEDEREA REVIZUIRII DOCUMENTATIEI TEHNICE SI IMPLEMENTARII ACESTUIA IN BAZA OUG 101/2020.
DECEMBRIE 2020 - A FOST SEMNAT UN PARTENERIAT INTRE CNAIR SI CJ BIHOR IN ACEST SENS
FEB. 2022 - SEMNARE
VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU IN DATA DE 20.05.2021 A FOST AVIZAT IN CADRUL CTE CNAIR SA STUDIUL DE FEZABILITATE.
1 VARIANTA OCOLITOARE VARIANTA OCOLITOARE ALESD 0+000 16+840 CONTRACT PRESTARI SERVICII PROIECTARE - FINALIZAT ALESD 16,84 CONTRACT PROIECTARE SI 2022 2024
AUTORITATILE LOCALE IN DATA DE 21.05.2021 A FOST AVIZAT IN CADRUL CTE MTI STUDIUL DE FEZABILITATE
EXECUTIE
DEC 2021- OBIECTIV AVIZAT IN CADRUL CTE IM; PROMOVAREA HG DE APROBARE A INDICATORILOR TEHNICO ECONOMICI - IN CURS DE APROBARE
LICITATIE DE ATRIBUIRE A UNUI CONTRACT DE PROIECTARE SI EXECUTIE IN DERULARE - ESTIMARE SEMNARE CTR PROIECTARE SI EXECUTIE - FEB 2022, IN IPOTEZA FARA CONTESTATII.
ETAPA I – VARIANTA SUD 126.88 MIL. LEI FARA PENTRU IMPLEMENTAREA ACESTUI OBIECTIV PRIMARIA MUNICIPIULUI IASI A INAINTAT O PROPUNERE DE SCHIMBARE A TRASEULUI, CA URMARE A IMPOSIBILITATII PASTRARII TRASEULUI PE
VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU 19+690 26+460
2 VARIANTA OCOLITOARE VARIANTA OCOLITOARE IASI OBIECT 3 – VARIANTA TRAFIC 6,77 TVA (VALOARE BULEVARDUL POITIERS SI STRADA TREI FANTANI (KM 19+690 - KM 26+460).
AUTORITATILE LOCALE (SELGROS) (DN28)
GREU ESTIMATA) PROPUNEREA A FOST ACCEPTATA DE CNAIR, URMAND A SE IDENTIFICA SURSA DE FINANTARE.
PENTRU IMPLEMENTAREA ACESTUI OBIECTIV A FOST SEMNAT UN PARTENERIAT DE IMPLEMENTARE INTRE CNAIR SA SI PRIMARIA MEDIAS IN BAZA PREVEDERILOR OUG 101/2020.
OBIECTIVUL SE IMPLEMENTEAZA DE CATRE UAT MEDIAS.
VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU
3 VARIANTA OCOLITOARE VARIANTA OCOLITOARE MEDIAS 0+000 8+500 MEDIAS 1 8,5 2022 2024 A FOST SEMNAT CONTRACTUL DE REVIZUIRE A STUDIULUI DE FEZABILITATE DE CATRE PRIMARIA MEDIAS IN LUNA IUNIE 2021.
AUTORITATILE LOCALE
A FOST EMIS ORDINUL DE INCEPERE IN DATA DE 10.06.2021 -
IN PREZENT ESTE IN DERULARE ETAPA DE REALIZARE A ANALIZEI MULTICRITERIALE 1 - REVIZIA 3 A FOST TRANSMISA CATRE CNAIR IN VEDEREA AVIZARII IN CTE CNAIR IN DATA DE 11.01.2022.
OBIECTIVUL A FOST TRANSFERAT CATRE CJ BIHOR IN VEDEREA REVIZUIRII DOCUMENTATIEI TEHNICE SI IMPLEMENTARII ACESTUIA IN BAZA OUG 101/2020.
A FOST SEMNAT IN LUNA DECEMBRIE 2020, PARTENERIATUL INTRE CNAIR SI CJ BIHOR IN ACEST SENS.
COPISA CONSTRUCTORA PIRENAICA SA - CONTRACT REZILIAT CONTRACT REVIZUIRE STUDIU DE FEZABILITATE FINALIZAT - STUDIUL DE FEZABILITATE A FOST AVIZAT IN CADRUL CTE CNAIR, CTE MTI , CTE IM, IN PREZENT AFLANDU-SE PE CIRCUITUL DE
VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU CONTRACT REZILIAT DE CATRE CONTRACT REZILIAT DE CATRE CONTRACT REZILIAT DE CATRE 257.413 MIL. LEI FARA
4 VARIANTA OCOLITOARE VARIANTA OCOLITOARE STEI 0+000 27+230 LICITATIE ATRIBUIRE CONTRACT REST LUCRARI RAMASE DE STEI 1 27,23 0% 0% AVIZARE PROIECTUL DE HG DE ACTUALIZARE A INDICATORILOR TEHNICO - ECONOMICI.
AUTORITATILE LOCALE ANTREPRENOR ANTREPRENOR ANTREPRENOR TVA
EXECUTAT, CU TERMEN DEPUNERE OFERTE : 22.06.2020 PROCEDURA DE ATRIBUIRE A UNUI CONTRACT DE EXECUTIE LUCRARI IN DERULARE - ETAPA DE EVALUARE OFERTE TEHNICE, ESTIMAT ATRIBUIRE CTR - FEB. 2022, SEMNARE IN IPOTEZA FARA
CONTESTATII - MARTIE 2022
DOCUMENTATIA DE ATRIBUIRE A CONTRACTULUI DE EXECUTIE SE AFLA IN ELABORARE LA NIVELUL CONSILIULUI JUDETEAN BIHOR.
STADIUL FINANCIAR
Nr. crt. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) PANA LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII
ACTUAL
23.01.2019 - DATA DE
INCEPERE PERIOADA DE
PROIECTARE
DESCHIDERE TRAFIC
08.03.2019 - DATA DE
OBIECT 1: 0+000 -20+299, 03.09.2020 - OBIECT 3;
INCEPERE A LUCRARILOR IN 668.33 MIL. LEI FARA
1 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE VARIANTA OCOLITOARE BACAU 0+000 30+842 SPEDITION UMB SRL – TEHNOSTRADE SRL BACAU OBIECT 2: 0+000 - 3+177 30,842 100,00% 99,78% IANUARIE 2022 ANUL 2020, 2021 02.12.2020 - OBIECT 1
BAZA AC TVA
OBIECT 3: 0+000 -7+366 10.08.2021 RTL OBIECT 1, OBIECT 2, OBIECT 3
040/15.07.201503.07.2019 -
LANSARE PROCEDURA DE ATRIBUIRE MASURI DE MEDIU SUPLIMENTARE DERIVATE DIN REVIZUIREA ACORDULUI DE MEDIU - DRDP IASI - RESPONSABIL
DATA DE INCEPERE A
LUCRARILOR IN BAZA AC
051/28.06.2019
LUCRARILE AU FOST FINALIZATE SI VARIANTA DE OCOLIRE SACUENI ESTE IN DATA IN CIRCULATIE INCEPAND CU 09.12.2020.
MOMENTAN SE AFLA IN PROCEDURA DE RECEPTIE LA TERMINAREA LUCRARILOR, LA DATA DE 15.09.2021 FIIND EMISA DECIZIA DIRECTORULUI GENERAL AL C.N.A.I.R.S.A. NR.1413/15.09.2021
PRIN CARE ESTE NUMITA COMISIA PENTRU EFECTUAREA R.T.L. IN PERIOADA 29.09.2021 - 08.10.2021 COMISIA SI-A DESFASURAT ACTIVITATEA, FIIND INTOCMIT PROCESUL VERBAL DE
4 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE VARIANTA OCOLITOARE SACUENI 0+000 7+620 SC ANTREPRIZA DE REPARATII SI LUCRARI ARL CLUJ SA SACUENI 7,62 10.09.2019 12.08.2020 DECEMBRIE 2020 42.83 MIL. LEI FARA TVA
SUSPENDARE A RECEPTIEI LA TERMINAREA LUCRARILOR NR.49178/08.10.2021, CARE SUSPENDA RECEPTIA PANA LA MAXIM 90 ZILE CA URMARE A DEPASIRII INDICATORILOR TEHNIC-
ECONOMICI. IN DATA DE 26.11.2021 A FOST EMIS DOCUMENTUL DE AVIZARE PRIVIND ACTUALIZAREA INDICATORILOR TEHNICO-ECONOMICI,.
A FOST EMIS AVIZUL MTI nr.87/95/29.12.2021. PENTRU OBTINEREA APROBARII INDICATORILOR PRIN H.G..