NOIEMBRIE 2020 - AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI

Stadiu fizic actual Stadiul financiar


Nr.crt. Indicativ Categorie Rang Sector Lot Lungime (km) De la Până la Antreprenor Valoare proiect Data începerii Data finalizării An deschidere (în folosință) Observatii
(procent) actual (procent)

CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 11.08. 2020.


A FOST TRANSMISA CATRE ANTREPRENOR ADRESA CU ORDINUL DE INCEPERE PENTRU DATA DE 14.09.2020. A FOST ACORDAT DREPTUL DE ACCES IN SANTIER ANTREPRENORULUI.
ANUL 2022 6 LUNI - ETAPA DE PROIECTARE; 18
ASOCIEREA TRAMECO SA – VAHOSTAV -SK A.S. – DRUMURI BIHOR SA – DRUM ASFALT SRL – 14 SEPTEMBRIE 2020 - EMITERE ORDIN DE INCEPERE PENTRU ETAPA DE DURATA CONTRACTULUI ESTE DE 144 DE LUNI DIN CARE:
1 AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ORADEA AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA SECTIUNEA 3C SUBSECTIUNEA 3C2: CHIRIBIS - BIHARIA 28.55 30+550 59+100 326.51 MIL. LEI FARA TVA MARTIE 2022 0,5% 0% LUNI - ETAPA DE EXECUTIE LUCRARI; 120 LUNI -
EAST WATER DRILLINGS SRL PROIECTARE (PROIECT TEHNIC) 6 LUNI - ETAPA DE PROIECTARE; FINALIZARE PUNCT DE REFERINTA NR. 1 IN 09.11.2020.
PERIOADA DE GARANTIE
18 LUNI - ETAPA DE EXECUTIE LUCRARI
120 LUNI - PERIOADA DE GARANTIE

SEMNARE CONTRACT PROIECTARE SI EXECUTIE IN DATA DE 22.09.2020


PREȚUL PE KM DE AUTOSTRADĂ ESTE DE CCA. 46.353.817 LEI FĂRĂ TVA, REPREZENTÂND CCA. 9.557.488 EURO FĂRĂ TVA.
SUBSECTIUNEA 3A2 NADASELU - MIHAIESTI KM
DURATA CONTRACTULUI ESTE DE 96 DE LUNI, DIN CARE:
2 AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ORADEA AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA SECTIUNEA 3A SI SECTIUNEA 3B 8+700 - 25+500+ 3B1, MIHAIESTI – ZIMBOR KM 0+000 30.06 8+700 38-760 ASOCIEREA S.C. SPEDITION UMB S.R.L. – S.C. TEHNOSTRADE S.R.L. – S.C. ELECTROMONTAJ S.A 1.390,614 MIL. LEI FARA TVA SEMNARE CONTRACT - 22.09.2020 2023 0% 0% 2023
• 12 LUNI PERIOADA DE PROIECTARE,
- 13+260
• 24 LUNI PERIOADA DE EXECUȚIE A LUCRĂRILOR,
• 60 DE LUNI PERIOADĂ DE GARANȚIE A LUCRĂRILOR.

CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN 30.09.2020


SUBSECTIUNEA 3B5: NUSFALAU - SUPLACU DE 6 LUNI PERIOADA DE PROIECTARE
3 AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ORADEA AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA SECTIUNEA 3B: MIHAIESTI - SUPLACU DE BARCAU 13.55 66+500 80+054 NUROL INSAAT VE TICARET S.A 384.14 MIL. LEI FARA TVA 01 FEBRUARIE 2021 FEBRUARIE 2023 0% 0% FEBRUARIE 2023
BARCAU 18 LUNI PERIOADA DE EXECUTIE
120 LUNI PERIOADA DE GARANTIE

CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 01.07.2020;


DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE:
8 DECEMBRIE 2020 - ORDIN DE INCEPERE PENTRU ETAPA DE PROIECTARE 12 LUNI PERIOADA DE PROIECTARE,
4 AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ORADEA AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA SECTIUNEA 3B: MIHAIESTI - SUPLACU DE BARCAU SUBSECTIUNEA 3B2: ZIMBOR - POARTA SALAJULUI 12.24 13+260 25+500 ASOCIEREA SC SA&PE CONSTRUCT SRL - SC SPEDITION UMB SRL - SC TEHNOSTRADE SRL 680.40 MIL. LEI FARA TVA 2023 0% 0% 2023
(PROIECT TEHNIC) 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,
120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR
A FOST CONSTITUITA GARANTIA DE BUNA EXECUTIE A LUCRARILOR, ORDINUL DE INCEPERE A LUCRARILOR EMIS IN DATA DE 10.08.2020 A FOST DECALAT CU MAXIM 120 DE ZILE

1. CONTRACT DE EXECUTIE SEMNAT IN DATA DE 29.05.2020.


2. AUTORIZATIE DE CONSTRUIRE VALABILA PENTRU ACEST SECTOR.
3. DURATA DE REALIZARE A ACESTUI CONTRACT ESTE URMATOAREA:
LOT 1 - TARGU MURES - UNGHENI (4.5 KM) + DRUM 18 LUNI - PERIOADA DE EXECUTIE A LUCRARILOR;
5 AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ORADEA AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA SECTOR 1C: TG. MURES - OGRA 9.2 0+000 4+500 S.C. STRABAG S.R.L. 192.06 MIL. LEI FARA TVA EMITERE ORDIN DE INCEPERE PENTRU EXECUTIE - 22 IULIE 2020 2022 22.10% 15% ANUL 2022
DE LEGATURA (4.7 KM) 108 LUNI (9 ANI) - PERIOADA DE GARANTIE A LUCRARILOR;
LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 3 PODURI SI PASAJE PE DRUMURI DE LEGATURA, 6 PODURI SI PASAJE PE AUTOSTRADA, PRECUM SI
DOUA NODURI RUTIERE PENTRU CONECTAREA AUTOSTRAZII LA RETEAUA DE DRUMURI EXISTENTA.

TRONSON OGRA - CAMPIA TURZII 18 SEPTEMBRIE 2020 - NOD CHETANI (1.3 KM) - DESCHIDEREA TRAFICULUI SLABA MOBILIZARE A ANTREPRENORULUI CAUZATA DE FAPTUL CA ACESTA SE AFLA IN INSOLVENTA DIN DATA DE 24.08.2015, LA APROXIMATIV 6 LUNI DE ZILE DE LA DATA SEMNARII
6 AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ORADEA AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA LOT 3 15.691 21+500 37+191 ASOCIEREA SC STRACO GRUP SRL & SPECIALIST CONSULTING SRL & SC TOTAL ROAD SRL 279.74 MIL. LEI FARA TVA 04.05.2016 37.45% 41.97% ANUL 2021
(2A3 CHETANI - CAMPIA TURZII) 2021 - INTARZIERI MAJORE ALE CONTRACTULUI DE PROIECTARE SI EXECUTIE CONTRACTULUI DE LUCRARI

DECEMBRIE 2020 (CONFORM DETERMINAR


PROIECT TEHNIC FINALIZAT IN DATA DE 11.03.2019
INGINER SI CONF. ESTIMARE VERBALA
TRONSON COMARNIC - BRASOV, LOT 2: SECTOR RASNOV - LOT 2: SECTOR PREDEAL - CRISTIAN, KM 162+300 - 6.3 KM AUTOSTRADA + 3.56 KM ESTIMAT DECEMBRIE 2020 (CONFORM ASUMARE ANTREPRENOR) AUTORIZATII DE CONSTRUIRE EMISE: ETAPA 1 - 11.04.2019 SI ETAPA A 2-A : 05.12.2019
7 AUTOSTRADA BUCURESTI - BRASOV AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 162+300 168+600 ASOCIEREA SC ALPENSIDE SRL - SC SPECIALIST CONSULTING SRL (IN INSOLVENTA) 118.02 MIL. LEI FARA TVA 11.04.2018 79.89% 62.60% ANTREPRENOR)
CRISTIAN, KM 162+300 - KM 168+600 SI DRUM DE LEGATURA KM 168+600 SI DRUM DE LEGATURA DRUM DE LEGATURA AUGUST 2021 (CONFORM PROGRAM DE EXECUTIE) EXECUTIE LUCRARI IN DERULARE, ANTREPRENOR MOBILIZAT.
AUGUST 2021 (CONF. PROGRAM DE EXECUTIE
PLATILE EFECTUATE INCLUD SI PLATA AVANSULUI.
EMIS DE ANTREPRENOR)

2023
ASOCIEREA S.C. SA&PE CONSTRUCT S.R.L. - S.C. SPEDITION UMB S.R.L. - S.C. TEHNOSTRADE DURATA CONTRACTULUI ESTE DE 90 LUNI SI CUPRINDE 12 LUNI PERIOADA DE CONTRACT SEMNAT IN DATA DE 31.08.2020.
8 AUTOSTRADA DE CENTURA A MUNICIPIULUI BUCURESTI (A0) AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA SECTOR NORD LOT 4 4.47 47+600 52+070 312.63 MIL. LEI FARA TVA 31.08.2020 0% 0% ESTIMAT 2023
S.R.L. PROIECTARE, 18 LUNI PERIOADA DE EXECUTIE A LUCRARILOR SI 60 DE LUNI ESTIMAT EMITERE ORDIN DE INCEPERE A ETAPEI DE PROIECTARE (ELABORARE PROIECT TEHNIC) - FEBRUARIE 2021
PERIOADA DE GARANTIE A LUCRARILOR.

ORDIN DE INCEPERE A LUCRARILOR 18.08.2020 ETAPA 1: KM 69+000 - KM 70+700


10.04.2019 - ORDIN DE INCEPERE A ACTIVITATII DE PROIECTARE 10% - PROGRES FIZIC ETAPA 1 DECIZIA PENTRU EXPROPRIERI AFERENTA HG 675/2020 A FOST EMISA IN DATA DE 15.10.2020
9 AUTOSTRADA DE CENTURA A MUNICIPIULUI BUCURESTI (A0) AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA SECTOR SUD LOT 2: VIDRA - BRAGADIRU 16.3 69+000 85+300 ALSIM ALARKO SANAYI TESISLERI VE TICARET A.S. 750.85 MIL. LEI FARA TVA FEBRUARIE 2023 19,07% - PROGRES FINANCIAR FEBRUARIE 2023
18.08.2020 - ORDIN INCEPERE LUCRARI KM 69+000 - KM 70+700 - 3% - PROGRES GENERAL A FOST ACORDAT AVANSUL PENTRU EXECUTIE LUCRARI (15% DIN VALOAREA LUCRARILOR)
ORDINUL DE INCEPERE PENTRU ETAPA 2, CONSTAND IN INTREG ALINIAMENTUL LOTULUI 2, A FOST EMIS IN DATA DE 29.10.2020 (14,6 KM)

DERULARE ETAPA DE PROIECTARE (ELABORARE PAC SI PTE). PROIECTUL TEHNIC IN FORMA FINALA, REVIZUITA CONFORM OBSERVATIILOR CONSULTANTULUI, VA FI DEPUS LA CNAIR SA IN
SECTOR NORD - KM 52+070 – KM 52+770; SECTOR SUD - KM
10 AUTOSTRADA DE CENTURA A MUNICIPIULUI BUCURESTI (A0) AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA LOT 1: GLINA - VIDRA 16.93 52+070 69+000 ALSIM ALARKO SANAYI TESISLERI VE TICARET A.S. 830.68 MIL. LEI FARA TVA 03.10.2019 - DATA DE INCEPERE A ACTIVITATII DE PROIECTARE IUNIE 2023 0.00% 2.46% ANUL 2023 SAPTAMANA 2-4 DECEMBRIE 2020.
52+770 – KM 69+000
ESTIMARE EMITERE ORDIN DE INCEPERE PENTRU EXECUTIE - DECEMBRIE 2020

IN PREZENT ANTREPRENORUL A REUSIT SA FINALIZEZE DECLARATIA DE PROIECTARE (INREGISTRAND INTARZIERI MAJORE IN ACTIVITATEA DE PROIECTARE), FIIND PENALIZAT CONFORM
SECTOR SUD - KM 85+300 - KM 100+765; SECTOR NORD - KM 85+300 - 100+765 ASOCIEREA AKTOR TECHNICAL SOCIETE ANONYME (AKTOR S.A.) - S.C. EURO CONSTRUCT CONTRACTULUI PENTRU NEINDEPLINIREA PUCTULUI DE REFERINTA NR 1 (FINALIZAREA DECLARATIEI DE PROIECTARE).
11 AUTOSTRADA DE CENTURA A MUNICIPIULUI BUCURESTI (A0) AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA LOT 3: BRAGADIRU - JOITA 17.965 0+000 - 2+500 NORD 853.42 MIL. LEI FARA TVA 23.05.2019 - DATA DE INCEPERE A ACTIVITATII DE PROIECTARE DECEMBRIE 2022 0.00% 0.29% DECEMBRIE 2022
0+000 + KM 2+500 SUD TRADING 98 S.R.L. IANUARIE 2021- ANTREPRENORUL VA PROCEDA LA ELABORAREA PAC SI PT.
TERMEN DE APROBARE DECLARATIE DE PROIECTARE: 23.11.2020 -27. 11.2020.

CONTRACT PROIECTARE SI EXECUTIE CU INTARZIERI MAJORE INREGISTRATE ; A


ASOCIEREA AKTOR TECHNICAL SOCIETE ANONYME (AKTOR S.A.) - S.C. EURO CONSTRUCT FOST ACORDATA DE CATRE INGINER O EXTENSIE DE TIMP PANA LA DATA DE
12 AUTOSTRADA SEBES - TURDA AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA SANTIMBRU - AIUD LOT 2 24.25 17+000 41+250 549.33 MIL. LEI FARA TVA 02.12.2014 78.10% 68.08% FINALIZARE LUCRARI - IUNIE 2021
TRADING 98 S.R.L. 03.12.2020
IUNIE 2021 - CONFORM GRAFIC DE LUCRARI

DESCHIDERE TRAFIC (15, 6 KM) - 03.12.2020


DESCHIDERE TRAFIC - 03.12.2020 80,93% (DIN VALOAREA DE
13 AUTOSTRADA SEBES - TURDA AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA LANCRAM - SANTIMBRU LOT 1 17 0+000 17+000 ASOCIEREA IMPRESA PIZZAROTTI & C SPA POMPONIO CONSTRUCTII SRL 541.73 MIL. LEI FARA TVA 02.12.2014 92.60% DESCHIDERE INTEGRALA A TRAFICULUI - IUNIE
FINALIZARE CONTRACT: APRILIE 2021 CONTRACT ACCEPTATA)
2021 (SIMULTAN CU FINALIZAREA LOTULUI 2)

2025 IN CF CU PREVEDERILE CTR DURATA DE REALIZARE A ACESTUI CTR ESTE DE 60 22.06.2020 – ORDIN DE INCEPERE FAZA PROIECTARE (12 LUNI)
DE LUNI, RESPECTIV: 12 LUNI PERIODA DE PROIECTARE SI 48 DE LUNI PENTRU CONTRACT DE SERVICII NR.92/58937/11.09.2020: „SUPERVIZARE AUTOSTRADA SIBIU – PITESTI, SECTIUNEA 5 – CURTEA DE ARGES – PITESTI KM 92+600-KM 122+950" SEMNAT CU ASOCIAREA EGIS
14 AUTOSTRADA SIBIU - PITESTI AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA CURTEA DE ARGES - PITESTI SECTIUNEA 5 30.35 91+761 122+110 ASTALDI SPA (ITALIA) 1710 MIL. LEI FARA TVA IUNIE 2020 - EMITERE ORDIN ETAPA DE PROIECTARE 0% 0% ANUL 2025
EXECUTIA LUCRARILOR. PERIOADA DE GARANTIE A LUCRARILOR OFERTATA DE INTERNATIONAL S.A.S – SEARCH CORPORATION S.R.L.- ITALROM INGINERIE INTERNATIONALA S.R.L.- METROUL S.A, A INLOCUIT SUPERVIZORUL DRDP BUCURESTI INCEPAND CU DATA DE
ASTALDI SPA ESTE DE 120 DE LUNI 01.10.2020

PROIECTUL TEHNIC A FOST FINALIZAT SI APROBAT DE CATRE CNAIR SA IN DATA DE 01.04.2020.

SECTIUNEA 1: SIBIU - BOITA (KM 0+000 - KM 14+150), 29.05.2019 - EMITERE ORDIN DE INCEPERE ETAPA DE PROIECTARE, 30.03.2020 - AUTORIZATIA DE CONSTRUIRE A FOST EMISA IN DATA DE 09.03.2020.
15 AUTOSTRADA SIBIU - PITESTI AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA LOT 1: KM 0+000 - KM 13+170 13.17 0+000 13+170 PORR CONSTRUCT SRL 612.65 MIL. LEI FARA TVA 28.05.2023 26,70% 19.09% 2023
LOT 1 EMITERE ORDIN DE INCEPERE ETAPA EXECUTIE LUCRARI
CONTRACT DE SERVICII NR. 92/61673/22.09.2020: „SUPERVIZARE AUTOSTRADA SIBIU – PITESTI, SECTIUNEA 1 –SIBIU – BOITA KM 00+000-KM 14+150""ASOCIEREA TPF INGINERIE S.R.L. -
SEPTEMBRIE CONSULTING S.R.L."" A INLOCUIT SUPERVIZORUL DRDP BUCURESTI INCEPAND CU DATA DE 19.10.2020

DRUM BRAILA-JIJILA - 19,095 KM; ORDINUL DE INCEPERE S-A EMIS DOAR PENTRU SECTIUNEA 2 (DIN CELE 5)- POD SUSPENDAT
24% - progres exclusiv pentru
16 POD BRAILA AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI DRUM NATIONAL POD SUSPENDAT PESTE DUNARE IN ZONA BRAILA 1 DRUM DE LEGATURA CU DN22 ASOCIEREA ASTALDI S.P. A - IHI INFRASTRUCTURE SYSTEM CO., LTD. 1.996 MLD. LEI FARA TVA 21.12.2018 DECEMBRIE 2021 34.40% DECEMBRIE 2021 03.09.2020 S-A APROBAT PROIECTUL DE HG PENTRU EXPROPRIERI SUPLIMENTARE
sectiunea de pod
SMARDAN-MACIN - 4,328 KM S-AU APROBAT PROIECTELE TEHNICE DE EXECUTIE AFERENTE RELOCARILOR LINIILOR ELECTRICE SI TELECOMUNICATIILOR