S.

C ARDELEAN COMPANY NORD VEST SRL

OBIECTIVUL : MODERNIZARE STRAZI DE INTERES LOCAL IN CARTIER TUR, ORASUL NEGRESTI OAS

FISA DE ASTERNERE MIXTURA ASFALTICA - BAD 20

STRADA LOCALA I TUR ; Lung = 1820 M

Data de 07.11.2015

NR. CRT Numar Cantitate/ Timpul de asternere Temperatura mixturi


camion tona
Temp mixt la Inceput Sfarsit asternere Inceput Sfarsit
asterner asternere compactare compactare
1. B 98 XSS 30 163 10.05 10.20 141 112
2. MM 27 SUD 30 162 10.25 10.45 141 113
3. B 89 XSS 30 163 11.00 11.20 143 111
4. B 96 XSS 30 162 11.55 12.15 142 111
5. B 88 XSS 30 163 12.30 12.45 143 112
6. MM 09 YCJ 30 161 12.50 13.10 142 113
7. MM 06 SPK 30 162 13.20 13.35 142 114

Intocmit Verificat si aprobat


Sef Santier Responsabil Tehnic cu Executia

Ing. Bota Marius Ing. Man Aron

S.C ARDELEAN COMPANY NORD VEST SRL

OBIECTIVUL : MODERNIZARE STRAZI DE INTERES LOCAL IN CARTIER TUR, ORASUL NEGRESTI OAS

FISA DE ASTERNERE MIXTURA ASFALTICA - BAD 20

STRADA LOCALA I TUR ; Lung = 1820 M

Data de 09.11.2015

NR. CRT Numar Cantitate/ Timpul de asternere Temperatura mixturi


camion tona
Temp mixt la Inceput Sfarsit asternere Inceput Sfarsit
asterner asternere compactare compactare
1. B 98 XSS 30 163 10.05 10.20 141 112
2. MM 27 SUD 30 162 10.25 10.45 141 113
3. B 89 XSS 30 163 11.00 11.20 143 111
4. MM 30 SUD 30 163 11.30 11.45 144 112
5. B 96 XSS 30 162 11.55 12.15 142 111
6. B 88 XSS 30 163 12.30 12.45 143 112
7. MM 09 YCJ 30 161 12.50 13.10 142 113
8. MM 06 SPK 30 162 13.20 13.35 142 114
Intocmit Verificat si aprobat

Sef Santier Responsabil Tehnic cu Executia

Ing. Bota Marius Ing. Man Aron

S.C ARDELEAN COMPANY NORD VEST SRL

OBIECTIVUL : MODERNIZARE STRAZI DE INTERES LOCAL IN CARTIER TUR, ORASUL NEGRESTI OAS

FISA DE ASTERNERE MIXTURA ASFALTICA - BAD 20

STRADA LOCALA I TUR ; Lung = 1820 M

Data de 10.11.2015
NR. CRT Numar Cantitate/ Timpul de asternere Temperatura mixturi
camion tona
Temp mixt la Inceput Sfarsit asternere Inceput Sfarsit
asternere asternere compactar compactare
e
1. B 98 XSS 30 162 10.25 10.45 141 113
2. B 89 XSS 30 161 11.50 11.10 141 112
3. MM 27 SUD 30 162 11.25 11.45 142 114
4. B 96 XSS 30 162 12.00 12.15 143 113
5. MM 30 SUD 30 163 12.25 12.45 144 115
6. B 88 XSS 30 163 12.50 13.10 143 114
7. MM 06 SPK 30 162 13.30 13.55 142 114
8. MM 29 SUD 30 162 14.20 14.35 142 113
9. B 98 XSS 30 162 14.45 15.05 141 112
Intocmit Verificat si aprobat

Sef Santier Responsabil Tehnic cu Executia

Ing. Bota Marius Ing. Man Aron

S.C ARDELEAN COMPANY NORD VEST SRL

OBIECTIVUL : MODERNIZARE STRAZI DE INTERES LOCAL IN CARTIER TUR, ORASUL NEGRESTI OAS

FISA DE ASTERNERE MIXTURA ASFALTICA - BAD 20

STRADA LOCALA I TUR ; Lung = 1820 M


NR. CRT Numar Cantitate/ Timpul de asternere Temperatura mixturi Data de 11.11.2015
camion tona
Temp mixt la Inceput Sfarsit asternere Inceput Sfarsit
asternere asternere compactare compactare
1. B 88 XSS 30 161 10.25 10.45 142 112
2. B 89 XSS 30 162 10.55 11.15 142 111
3. MM 29 SUD 30 162 11.45 12.05 141 112
4. B 98 XSS 30 162 12.20 12.35 143 113
5. B 96 XSS 30 163 12.40 13.00 144 112
6. MM 27 SUD 30 162 13.10 13.25 143 114
7. MM 06 SPK 30 162 13.45 14.00 142 113
8. MM 09 YCJ 30 161 14.20 14.35 145 113
9. B 89 XSS 30 162 14.55 15.15 142 112
10. MM 30 SUD 30 161 15.30 15.50 142 112
Intocmit Verificat si aprobat

Sef Santier Responsabil Tehnic cu Executia

Ing. Bota Marius Ing. Man Aron

S.C ARDELEAN COMPANY NORD VEST SRL

OBIECTIVUL : MODERNIZARE STRAZI DE INTERES LOCAL IN CARTIER TUR, ORASUL NEGRESTI OAS

FISA DE ASTERNERE MIXTURA ASFALTICA - BAD 20

STRADA LOCALA I TUR ; Lung = 1820 M

Data de 12.11.2015

NR. CRT Numar Cantitate/ Timpul de asternere Temperatura mixturi


camion tona
Temp mixt la Inceput Sfarsit asternere Inceput Sfarsit
asternere asternere compactare compactare
1. MM27 SUD 30 162 10.10 10.25 140 111
2. MM30 SUD 30 163 10.45 11.00 142 112
3. B 88 XSS 30 163 11.10 11.30 141 113
4. B 89 XSS 30 162 11.55 12.10 142 114
5. B 96 XSS 30 161 12.40 12.45 142 114
6. MM 06 SPK 30 163 13.00 13.20 143 115
7. B 98 XSS 30 162 13.35 13.55 144 113
8. MM 29 SUD 30 162 14.15 14.35 142 114
9. MM 27 SUD 30 163 14.45 15.00 142 112
Intocmit Verificat si aprobat

Sef Santier Responsabil Tehnic cu Executia

Ing. Bota Marius Ing. Man Aron

S.C ARDELEAN COMPANY NORD VEST SRL

OBIECTIVUL : MODERNIZARE STRAZI DE INTERES LOCAL IN CARTIER TUR, ORASUL NEGRESTI OAS

FISA DE ASTERNERE MIXTURA ASFALTICA - BAD 20

NR. CRT Numar Cantitate/ Timpul de asternere Temperatura mixturi STRADA LOCALA I TUR ;
camion tona Lung = 1820 m
Temp mixt la Inceput Sfarsit asternere Inceput Sfarsit
asternere asternere compactare compactare STRADA LOCALA II TUR ;
1. MM 30 SUD 30 162 9.30 9.45 140 110 Lung= 870 m
2. B 96 XSS 30 163 10.00 10.15 142 112
Data de 13.11.2015
3. B 88 XSS 30 163 10.25 10.40 142 113
4. MM 27 SUD 30 164 10.50 11.05 144 112
5. B 89 XSS 30 163 11.20 11.35 143 114
TUR 2- BAD 20
6. MM 29 SUD 30 162 13.30 13.45 138 112
7. B 98 XSS 30 162 14.20 14.40 141 113
8. MM 06 SPK 30 163 15.00 15.15 142 113
Intocmit Verificat si aprobat

Sef Santier Responsabil Tehnic cu Executia

Ing. Bota Marius Ing. Man Aron

S.C ARDELEAN COMPANY NORD VEST SRL

OBIECTIVUL : MODERNIZARE STRAZI DE INTERES LOCAL IN CARTIER TUR, ORASUL NEGRESTI OAS

FISA DE ASTERNERE MIXTURA ASFALTICA - BAD 20

STRADA LOCALA 1 TUR ; Lung = 1820 M

Data de 08.04.2016

NR. CRT Numar Cantitate/ Timpul de asternere Temperatura mixturi


camion tona
Temp mixt la Inceput Sfarsit asternere Inceput Sfarsit
asternere asternere compactare compactare
1. B 98 XSS 30 163 9.20 9.35 142 115
2. MM 27 SUD 30 162 9.45 10.00 142 114
3. MM 30 SUD 30 162 10.15 10.30 140 115
Intocmit Verificat si aprobat

Sef Santier Responsabil Tehnic cu Executia

Ing. Bota Marius Ing. Man Aron

S.C ARDELEAN COMPANY NORD VEST SRL

OBIECTIVUL : MODERNIZARE STRAZI DE INTERES LOCAL IN CARTIER TUR, ORASUL NEGRESTI OAS

FISA DE ASTERNERE MIXTURA ASFALTICA – BAD 20

STRADA LOCALA 2 TUR ; Lung = 870 M

Data de 08.04.2016

NR. CRT Numar Cantitate/ Timpul de asternere Temperatura mixturi


camion tona
Temp mixt la Inceput Sfarsit asternere Inceput Sfarsit
asternere asternere compactare compactare
1. B 96 XSS 30 164 13.10 13.25 142 117
2. B 89 XSS 30 162 14.00 14.15 140 115
3. MM 06 SPK 30 162 15.00 15.20 145 116
4. MM 09 YCJ 30 161 15.30 15.45 144 115
Intocmit Verificat si aprobat

Sef Santier Responsabil Tehnic cu Executia

Ing. Bota Marius Ing. Man Aron

S.C ARDELEAN COMPANY NORD VEST SRL

OBIECTIVUL : MODERNIZARE STRAZI DE INTERES LOCAL IN CARTIER TUR, ORASUL NEGRESTI OAS

FISA DE ASTERNERE MIXTURA ASFALTICA – BA 16

STRADA LOCALA I TUR ; Lung = 1820 M

NR. CRT Numar Cantitate/ Timpul de asternere Temperatura mixturi Data de 12.04.2016
camion tona
Temp mixt la Inceput Sfarsit asternere Inceput Sfarsit
asternere asternere compactare compactare
1. MM 30 SUD 30 163 9.10 9.30 141 115
2. B 98 XSS 30 162 9.50 10.10 142 114
3. B 88 XSS 30 163 10.20 10.40 140 113
4. MM 27 SUD 30 161 11.10 11.30 143 114
5. B 89 XSS 30 162 12.30 12.50 142 115
6. B 96 XSS 30 163 13.20 13.40 140 115
7. MM 06 SPK 30 163 14.10 14.20 141 114
8. MM 09 YCJ 30 162 15.00 15.20 141 115
Intocmit Verificat si aprobat

Sef Santier Responsabil Tehnic cu Executia

Ing. Bota Marius Ing. Man Aron

S.C ARDELEAN COMPANY NORD VEST SRL

OBIECTIVUL : MODERNIZARE STRAZI DE INTERES LOCAL IN CARTIER TUR, ORASUL NEGRESTI OAS

FISA DE ASTERNERE MIXTURA ASFALTICA – BA 16

STRADA LOCALA I TUR ; Lung = 1820 M

Data de 13.04.2016
NR. CRT Numar Cantitate/ Timpul de asternere Temperatura mixturi
camion tona
Temp mixt la Inceput Sfarsit asternere Inceput Sfarsit
asternere asternere compactare compactare
1. B 89 XSS 30 162 8.40 8.55 145 113
2. B 98 XSS 30 162 9.10 9.25 143 114
3. B 96 XSS 30 161 9.50 10.10 142 113
4. B 88 XSS 30 163 10.15 10.30 142 116
5. MM 30 SUD 30 161 11.00 11.15 143 113
6. MM 27 SUD 30 162 12.10 12.25 142 113
7. MM 29 SUD 30 161 14.00 14.20 143 114
Intocmit Verificat si aprobat

Sef Santier Responsabil Tehnic cu Executia

Ing. Bota Marius Ing. Man Aron

S.C ARDELEAN COMPANY NORD VEST SRL

OBIECTIVUL : MODERNIZARE STRAZI DE INTERES LOCAL IN CARTIER TUR, ORASUL NEGRESTI OAS

FISA DE ASTERNERE MIXTURA ASFALTICA – BA 16

STRADA LOCALA I TUR ; Lung = 1820 M

Data de 14.04.2016
NR. CRT Numar Cantitate/ Timpul de asternere Temperatura mixturi
camion tona
Temp mixt la Inceput Sfarsit asternere Inceput Sfarsit
asternere asternere compactare compactare
1. MM 30 SUD 30 160 8.50 9.10 142 112
2. B 98 XSS 30 161 9.20 9.40 141 112
3. B 89 XSS 30 162 10.00 10.20 142 113
4. MM 27 SUD 30 162 10.50 11.10 141 113
5. MM 06 SPK 30 161 11.30 11.55 142 115
6. B 96 XSS 30 161 12.20 12.40 143 114
7. MM 09 YCJ 30 162 13.10 13.30 144 114
8. B 88 XSS 30 160 14.10 14.30 142 113
9. MM 30 SUD 30 160 15.10 15.25 141 112
Intocmit Verificat si aprobat

Sef Santier Responsabil Tehnic cu Executia

Ing. Bota Marius Ing. Man Aron

S.C ARDELEAN COMPANY NORD VEST SRL

OBIECTIVUL : MODERNIZARE STRAZI DE INTERES LOCAL IN CARTIER TUR, ORASUL NEGRESTI OAS

FISA DE ASTERNERE MIXTURA ASFALTICA – BA 16

STRADA LOCALA I TUR ; Lung = 1820 M

Data de 19.04.2016
NR. CRT Numar Cantitate/ Timpul de asternere Temperatura mixturi
camion tona
Temp mixt la Inceput Sfarsit asternere Inceput Sfarsit
asternere asternere compactare compactare
1. B 88 XSS 30 161 12.25 12.45 151 116
2. MM 30 SUD 30 161 13.00 13.25 152 117
3. MM 27 SUD 30 162 14.00 14.20 150 116
4. B 98 XSS 30 160 14.30 14.50 149 113
5. B 96 XSS 30 161 15.00 15.20 152 112
6. B 89 XSS 30 162 15.30 15.50 150 116
7. MM 09 YCJ 30 163 16.20 16.40 149 115
Intocmit Verificat si aprobat

Sef Santier Responsabil Tehnic cu Executia

Ing. Bota Marius Ing. Man Aron

S.C ARDELEAN COMPANY NORD VEST SRL

OBIECTIVUL : MODERNIZARE STRAZI DE INTERES LOCAL IN CARTIER TUR, ORASUL NEGRESTI OAS

FISA DE ASTERNERE MIXTURA ASFALTICA – BAD 20

STRADA LOCALA 2 TUR ; Lung = 870 M

Data de 21.04.2016

NR. CRT Numar Cantitate/ Timpul de asternere Temperatura mixturi


camion tona
Temp mixt la Inceput Sfarsit asternere Inceput Sfarsit
asternere asternere compactare compactare
1. MM 27 SUD 30 160 11.30 11.50 151 112
2. B 98 XSS 30 162 12.10 12.30 152 117
3. B 89 XSS 30 163 12.40 13.00 150 119
4. MM 30 SUD 30 164 13.30 13.50 153 121
5. MM 09 YCJ 30 163 14.10 14.30 150 122
6. B 88 XSS 30 162 15.00 15.20 152 115
Intocmit Verificat si aprobat

Sef Santier Responsabil Tehnic cu Executia

Ing. Bota Marius Ing. Man Aron

S.C ARDELEAN COMPANY NORD VEST SRL

OBIECTIVUL : MODERNIZARE STRAZI DE INTERES LOCAL IN CARTIER TUR, ORASUL NEGRESTI OAS

FISA DE ASTERNERE MIXTURA ASFALTICA – BAD 20

STRADA LOCALA 2 TUR ; Lung = 870 M

Data de 22.04.2016

NR. CRT Numar Cantitate/ Timpul de asternere Temperatura mixturi


camion tona
Temp mixt la Inceput Sfarsit asternere Inceput Sfarsit
asternere asternere compactare compactare
1. B 88 XSS 30 162 10.50 11.15 144 112
2. B 89 XSS 30 163 11.30 11.50 143 113
3. MM 30 SUD 30 162 12.20 12.40 140 114
4. MM 09 YCJ 30 160 13.30 13.50 142 113
5. MM 27 SUD 30 161 15.10 15.30 143 111
Intocmit Verificat si aprobat

Sef Santier Responsabil Tehnic cu Executia

Ing. Bota Marius Ing. Man Aron

S.C ARDELEAN COMPANY NORD VEST SRL

OBIECTIVUL : MODERNIZARE STRAZI DE INTERES LOCAL IN CARTIER TUR, ORASUL NEGRESTI OAS

FISA DE ASTERNERE MIXTURA ASFALTICA – BA 16

STRADA LOCALA 2 TUR ; Lung = 870 M

Data de.24.05.2016

NR. CRT Numar Cantitate/ Timpul de asternere Temperatura mixturi


camion tona
Temp mixt la Inceput Sfarsit asternere Inceput Sfarsit
asternere asternere compactare compactare
1. B 96 XSS 30 162 10.00 10.20 142 115
2. B 88 XSS 30 163 10.40 11.00 143 114
3. MM 30 SUD 30 163 11.20 11.40 142 116
4. MM 27 SUD 30 164 12.10 12.30 143 114
5. MM 09 YCJ 30 162 14.20 14.40 141 114
6. B 98 XSS 30 161 15.10 15.30 142 115
Intocmit Verificat si aprobat

Sef Santier Responsabil Tehnic cu Executia

Ing. Bota Marius Ing. Man Aron

S.C ARDELEAN COMPANY NORD VEST SRL

OBIECTIVUL : MODERNIZARE STRAZI DE INTERES LOCAL IN CARTIER TUR, ORASUL NEGRESTI OAS

FISA DE ASTERNERE MIXTURA ASFALTICA – BA16

STRADA LOCALA 2 TUR ; Lung = 870 M

Data de 25.05.2016

NR. CRT Numar Cantitate/ Timpul de asternere Temperatura mixturi


camion tona
Temp mixt la Inceput Sfarsit asternere Inceput Sfarsit
asternere asternere compactare compactare
1. MM 29 SUD 30 163 11.10 11.30 141 112
2. MM 30 SUD 30 161 11.50 12.10 142 113
3. B 88 XSS 30 164 12.20 12.40 144 114
4. B 89 XSS 30 163 13.10 13.30 143 112
5. B 96 XSS 30 164 13.50 14.10 141 114
Intocmit Verificat si aprobat

Sef Santier Responsabil Tehnic cu Executia

Ing. Bota Marius Ing. Man Aron