FUNDATIE RIGIDA STALP 1 FUNDATIE RIGIDA STALP 2

scara 1:50 scara 1:50


3
4
40
20 20

40

pardoseala
sapa de egalizare
placa de beton armat
pardoseala
termoizolatie polistiren extrudat
sapa de egalizare
strat separatie placa de beton armat
strat de pietris pentru strat separatie
rupere capilaritate
termoizolatie polistiren extrudat
strat de pietris

12 Mustati 4Ø16 L=1.85m


±0.00

11 Mustati 4Ø16 L=1.5m


15 5

3
Dop bitum

10 4Ø16 L=2.70m
-0.30 ±0.00
20 5 10

9 4 Ø16 L=2.20m
Trotuar

5 10
-0.20
3%
C25/30

2
50
100

Rigola
12 12 25 -0.70
25 Strat de pietris
Umplutura
20 20

125
-1.35
C25/30

80
100 100 30
25 25
200 Beton de egalizare
40 40 -1.25
Clasa de expunere XC2
25 25 30 Beton C25/30
Beton de egalizare Clasa structurala S4
2 10Ø16 L=3.40m 7 Ø8/10 L=1.10m S500 8 Ø8/10 L=1.50m S500 Otel Bst500C
cnom=50mm
70 70 13 4Ø12 L=2.40m Clasa de importanta: "III"
30
70 25 25
50

40 40
60 60 25 25
41

41

30

7 Ø8/10 L=1.10m S500 8 Ø8/10 L=1.50m S500


3 4Ø18 L=2.40m 25 25

11 Ø18/700 L=1.82m
14 4Ø12 L=1.42m
18 18
41

18 18
70
70 70
25 25

1 10Ø16 L=3.40m

60
1 4 14

85
15
70 20 70 18
18

25
18
15 4Ø12 L=1.62m

18
16 4Ø12 L=1.62m
100

40

40
13

5 16

35
7 18 18
18 18
5 10Ø18 L=2.9m

6 6Ø18 L=2.90m

4 10Ø18 L=2.9m

95
250
50

60
3

50 20 40 20 50
2

100

180
6

70 20 70
UNIVERSITATEA TEHNICĂ FUNDAȚII Nr. pl.
80 40 80 CLUJ-NAPOCA
FACULTATEA DE CONSTRUCȚII Anul IV Grupa 32301/B 2

200 Nume Semnat Scara:


Chînța 1:20 DETALII P
Desenat Darius Daniel
Data: S1 S2
Călin
Verificat DEC. 2022