Part I: MEMORIU TEHNIC GENERAL

DEPOZITUL VECHI CALARAI


JUDEUL CLRAI

ASISTEN TEHNIC PENTRU PREGTIREA A 5 PROIECTE


N SECTORUL DE MEDIU. EUROPEAID/123052/D/SER/RO

EuropeAid/123052/D/SER/RO
stage: October 2010-10-22
/var/www/apps/conversion/tmp/scratch_7/333984583.doc

page 1 of 17

Technical Assistance for Preparation of 5 projects


in the Environment Sector.
EuropeAid/123052/D/SER/RO
Consortium C&E Consulting and Engineering GmbH
Louis Berger SAS Poyry Environment GmbH

CONINUT

NR PAGIN

Partea I

MEMORIU TEHNIC GENERAL...................................................................1

Localizare i topografie.............................................................................5

Clim............................................................................................................5

Geologie......................................................................................................6

Prezentarea lucrrilor................................................................................6

4.1

Principiile de baza ale lucrarilor...................................................................6

4.2

Scopul general al lucrrilor...........................................................................7

4.2.1

Generaliti...................................................................................................7

Part II: MEMORIU TEHNIC PENTRU LUCRRI DE CONSTRUC IE .......................8


Concept privind progresul construciilor i echipamente tehnice necesare .......8
5

nchiderea temporar (faza 1)...................................................................8

5.1

Defriarea amplasamentului........................................................................8

5.2

Indeprtarea deeurilor i a pmntului......................................................8

5.3

Nivelarea corpului depozitului - conturul depozitului...................................9

5.4

Drumuri de acces.........................................................................................9

5.5

Sistemul de colectare a levigatului...............................................................9

5.6

Acoperirea temporar a suprafeei..............................................................9

5.7

Colectarea i devierea temporar a apelor de suprafa ..........................10

5.8

Bazinul de retenie a apelor pluviale..........................................................11

5.9

Instalaia pentru gazele din depozit i sistemul de colectare a gazelor .....11

5.10

Marcaje de amplasare temporare..............................................................11

5.11

Amenajarea terenului.................................................................................12

5.12

mprejmuire................................................................................................12

EuropeAid/123052/D/SER/RO
stage: October 2010-10-22
/var/www/apps/conversion/tmp/scratch_7/333984583.doc

page 2 of 17

Technical Assistance for Preparation of 5 projects


in the Environment Sector.
EuropeAid/123052/D/SER/RO
Consortium C&E Consulting and Engineering GmbH
Louis Berger SAS Poyry Environment GmbH

Realizarea sistemului final de impermeabilizare (faza 2).....................13

6.1

Defriarea amplasamentului......................................................................13

6.2

Excavarea i mutarea stratului de acoperire temporar............................13

6.3

Mutarea materialului (argil, silt) de pe drumul de acces..........................13

6.4

Demolarea instalaiilor de colectare a gazului din depozit .........................14

6.5

Demolarea marcajelor temporare de amplasare.......................................14

6.6

Modificarea i extinderea sondei verticale de gaze...................................14

6.7

Realizarea ferestrei de migraie a gazului.................................................14

6.8

Teren de incercri.......................................................................................15

6.9

Nivelarea i compactarea corpului profilat al depozitului ...........................15

6.10

Construirea stratului de drenare a gazului din depozit..............................15

6.11

Realizarea stratului mineral de impermeabilizare......................................15

6.12

Amplasarea geotextilului de separare........................................................16

6.13

Realizarea stratului de drenare..................................................................16

6.14

Amplasarea geotextilului permeabil sub prisma de drenaj........................16

6.15

Realizarea stratului de cultur i a stratului vegetal ..................................16

6.16

Montarea conductelor de colectare a gazului de depozit..........................17

6.17

Prisma de drenaj........................................................................................17

6.18

Drumuri de acces.......................................................................................17

6.19

Sistemul final de colectare i deversare a apelor de suprafa .................17

6.20

Marcaje de amplasament...........................................................................18

6.21

Amenajarea terenului.................................................................................18

EuropeAid/123052/D/SER/RO
stage: October 2010-10-22
/var/www/apps/conversion/tmp/scratch_7/333984583.doc

page 3 of 17

Technical Assistance for Preparation of 5 projects


in the Environment Sector.
EuropeAid/123052/D/SER/RO
Consortium C&E Consulting and Engineering GmbH
Louis Berger SAS Poyry Environment GmbH

1 Localizare i topografie
Forma predominant de relief este cmpia, reprezentat prin cele patru mari uniti:
Cmpia Mostitei (Brganul de sud), Cmpia Vlsiei, Cmpia Burnas i Lunca
Dunrii, a se vedea figura 11. Principalele forme de relief sunt cmpiile, luncile i
iazurile. Altitudinea medie este de 46 m. Cel mai nalt punct din jude are 83 m, iar
cel mai jos 8 m. n partea sudic, judeul este mrginit de Dunre i lunca sa.
Nivelul solului n Lunca Dunrii este mic, zona s-a format prin sedimente aluvionare
ale fluviului. n Lunca Dunrii exist numeroase insule i canale.
.

Relieful n Judeul Clrai

2 Clim
Judeul Clrai are un climat continental, cu veri calde i uscate i ierni reci. De-a lungul
Dunrii, iernile sunt mai blnde dect n zona de terase de deasupra Clraiului. Cantitile
medii anuale de precipitaii variaz de la 400-600 mm. Valoarea medie a precipitaiilor n luna
iunie variaz ntre 75,9 mm n Oltenia i 72,2 mm n Clrai. Luna cu precipitaile cele mai
sczute este februarie, cu 30,1 mm n Clrai. Precipitaiile cad cel mai mult n lunile de
var, cu numeroase furtuni. Precipitaii sub form de ninsoare cad din decembre pn n
februarie, media lunii ianuarie fiind de 90-100 mm. Cantitile pierdute prin evapo-transpiraie
EuropeAid/123052/D/SER/RO
stage: October 2010-10-22
/var/www/apps/conversion/tmp/scratch_7/333984583.doc

page 4 of 17

Technical Assistance for Preparation of 5 projects


in the Environment Sector.
EuropeAid/123052/D/SER/RO
Consortium C&E Consulting and Engineering GmbH
Louis Berger SAS Poyry Environment GmbH

n perioada iunie-august duc la un necesar de ap pentru agricultur, care depete bilanul


local de ap. Acest deficit de ap este acoperit n principal din apa de suprafa. Parametrii
privind condiiile climatice pentru acest jude sunt prezentai n tabelul de mai jos.

3 Geologie
Judeul Clrai este situat n Cmpia Valahiei sau Cmpia Romn, n partea de sud a rii,
mrginit de Dunre la est, sud i vest i de Platoul Getic n nord. Din punct de vedere
tectonic, Cmpia Romn este situat pe platforma moesic i parial pe bazinul moesic
mezozoic-cenozoic. Clrai e plasat n zona joas de es a Bucuretiului. Suprafaa este
acoperit de loess. Sub stratul de loess se gsesc formaiuni sedimentare din Cuaternar i
Paleozoic, dispuse dup cum urmeaz:
Sedimentele din formaiunile Mostitea i Dunrii: depozite de nisip i pietri, cu o
grosime de 10-25 m, sub stratul de loess. n zona Dunrii se ntlnesc depozite terasate.
Pleistocenul mediu: secvena Mostitea este urmat de sedimente lutoase. Acestea pot
atinge o grosime de este 50 m.
Formaiunea Frteti: alctuit din nisip, pietri, bolovani, pe alocuri cimentate cu cuarit,
gresie, roci eruptive, cu o grosime de 15-25 m la sud de Clrai i 120-170 m nspre
nord. Depozitele Frteti sunt foarte importante deoarece structura lor conine principalul
strat al pnzei freatice.

4 Prezentarea lucrrilor
4.1 Principii de baz ale lucrarilor
Lucrarile inchiderii vechiului deposit sunt bazate pe urmtoarele:

Conditiile si situatia locala fara a lua in considerare limitele de proprietate,


Suprafata acoperita de deseuri,
Conditiile legale ale proprietatilor,
Stabilirea modului de colectare a apelor de suprafata si a sistemului de evacuare,
Stabilirea bazinului de retentie,
Stabilirea sistemului de colectare prin levigare,
Stabilirea drumurilor de acces,
Infrastuctura si legatura cu drumurile publice,
Stabilirea sistemului de extractie a gazului din depozit,

EuropeAid/123052/D/SER/RO
stage: October 2010-10-22
/var/www/apps/conversion/tmp/scratch_7/333984583.doc

page 5 of 17

Technical Assistance for Preparation of 5 projects


in the Environment Sector.
EuropeAid/123052/D/SER/RO
Consortium C&E Consulting and Engineering GmbH
Louis Berger SAS Poyry Environment GmbH

Cladiri si instalatii care urmeaza a fi construite (ex. Instalatie de extractie de gaz


arzator de gaze in exces la temperature inalte),
Amplasarea de imprejmuiri,
Amenajarea terenului,
Amplasarea sistemului de acoperire temporar si mai tarziu a sistemului final de
suprafata,
Excavarea deseurilor si solului existent, transportul deseurilor si solului si depozitarea
lor compacta in zona depozitului.
Modelarea de penti stabile
Estimarea cantitatii de deseuri aditionale de la depozite mai mici sau de la livrarile
regulate.

Cadrul general al lucrrilor


1.8.1 Generaliti
nchiderea depozitului Calarasi se va realiza n dou etape:
-

Etapa 1: acoperirea temporar cu noul depozit de deeuri, mutarea deeurilor inclusiv


redepozitarea pe acelai amplasament i realizarea unei acoperiri temporare, inclusiv
montarea componentelor pentru extracia gazului de depozit, sistemele de colectare i
evacuare a apei de suprafa i de colectare a levigatului.
Etapa a 2-a: nchiderea final, cu un sistem de etanare a suprafeei i instalarea
sistemului final de extracie a gazului de depozit, i a celui de colectare a apei de
suprafa

EuropeAid/123052/D/SER/RO
stage: October 2010-10-22
/var/www/apps/conversion/tmp/scratch_7/333984583.doc

page 6 of 17

Technical Assistance for Preparation of 5 projects


in the Environment Sector.
EuropeAid/123052/D/SER/RO
Consortium C&E Consulting and Engineering GmbH
Louis Berger SAS Poyry Environment GmbH

Part II: MEMORIU TEHNIC PENTRU


LUCRRI DE CONSTRUCIE
Concept privind progresul construciilor i
echipamentele tehnice necesare
Preambul:
Urmtoarele puncte descriu procesul de lucrri planificat. Variaiile din partea Contractorului
sunt posibile, n cazul n care Clientul i inginerul coordonator le accept.

5 nchiderea temporar (faza 1)


8.1 Defriarea amplasamentului
ndeprtarea i eliminarea vegetaiei i a arborilor, inclusiv a rdcinilor din zona
depozitului de deeuri.
Stratul de pmnt cu rdcini cu o grosime de aproximativ 20 de cm trebuie s fie
ndeprtat i depozitat n zona central a rampei de deeuri pe o arie mare i n strat
subire
Suprafa: 95.000 m
Echipamente utilizate: Buldozer, Excavator echipamente grele ca. 95% of 95.000 m 2 (90.250
m2)
Excavator echipament mic ca. 5% of 95.000 m2 (4.750 m2)

5.1 ndeprtarea deeurilor i a pmntului


ndeprtarea deeurilor din zonele marginale i nivelarea pantelor la o nclinare de max.
1 : 2,5 precum i depozitarea nivelat a deeurilor n ramp.
Volum: 190.000 m
Echipament utilizat: Buldozer, Excavator echipamente grele ca. 95% of 190.000 m
(180.500 m)
Excavator echipament mic ca. 5% of 190.000 m (9.500 m)
Poziie necesar: Excavarea solului existent (BK2) din zonele de delimintare, conform
solicitrilor Inginerului
Volum: acceptare preliminar: aprox. 7.500 m

Echipament utilizat: Buldozer, Excavator echipamente grele cca. 100% din 7.500 m
(7.500 m)

EuropeAid/123052/D/SER/RO
stage: October 2010-10-22
/var/www/apps/conversion/tmp/scratch_7/333984583.doc

page 7 of 17

Technical Assistance for Preparation of 5 projects


in the Environment Sector.
EuropeAid/123052/D/SER/RO
Consortium C&E Consulting and Engineering GmbH
Louis Berger SAS Poyry Environment GmbH

5.2 Nivelarea corpului depozitului conturul depozitului


Nivelare - excavare, compactare, conform suprafeei proiectate a depozitului, pant cu
nclinare de max. 1:2,5.
Suprafa: 80.000 m
Echipamente utilizate: Buldozer, Excavator echipamente grele cca 95% din 80.000 m2
(76.000 m2)
Excavator echipament mic cca. 5% din 80.000 m2 (4.000 m2)
Compactor picior de oaie, compactor cu cilindru cca. 100% (80.000 m2)

5.3 Drumuri de acces


Construcia drumurilor de acces temporar n depozit.
Lungime total: 1950 m derivaii n depozit, inclusiv drum privat, berma si rampa
Echipamente utilizate: Buldozer, Excavator echipamente grele cca. 90%
Excavator echipament mic cca. 10%
Compactor picior de oaie, compactor cu cilindru cca. 100%

5.4 Sistemul de colectare a levigatului


Construirea sistemului de colectare a levigatului, care const n conducte de drenare a
levigatului, conducte gravitaionale i cmin de vizitare
Lungimea conductelor de drenare levigat: approx. 400 m
Numrul cminelor de vizitare:
2 buc.
Echipamente utilizate: Macara mobil, Excavator echipament mic cca. 80%
Lucru manual cca 20 %
Compactor cu cilindru, mai compactor cca. 100%

5.5 Acoperirea temporar a suprafeei


Acoperirea temporar a suprafeei, constnd ntr-un strat provizoriu de acoperire
Volum: 33.000 m3
Echipamente utilizate: Buldozer, Excavator echipamente grele cca 95% din 33.000 m
(31.350 m2)
Excavator echipament mic, cca. 5% din 33.000 m (1.650m)
Compactor picior de oaie, compactor cu cilindru cca 100% (33.000 m)

EuropeAid/123052/D/SER/RO
stage: October 2010-10-22
/var/www/apps/conversion/tmp/scratch_7/333984583.doc

page 8 of 17

Technical Assistance for Preparation of 5 projects


in the Environment Sector.
EuropeAid/123052/D/SER/RO
Consortium C&E Consulting and Engineering GmbH
Louis Berger SAS Poyry Environment GmbH

5.6 Colectarea i devierea temporar a apelor de suprafa


Realizarea temporar a sistemului de colectare a apelor de suprafa i a canalelor de
deversare i realizarea parial a sistemului final de colectare a apelor de suprafa i a
rigolelor de deversare:
Realizarea profilului canalului temporar de deversare a apelor de suprafa avndu-se n
vedere finalizarea anurilor cu piatr spart de 0,2 m
Lungime:
1.750 m
Realizarea profilului anului pentru deversarea temporar a apelor de suprafa
avndu-se n vedere finalizarea acestuia cu dale din piatr
Lungime:
165 m
Realizarea profilului anului de deversare temporar a apelor de suprafa avndu-se
n vedere finalizarea anului cu elemente din beton (cascad)
Lungime:
185 m
Aprivizionarea si amplasarea conductei de beton DN 500
Lungime:
37 m
Aprovizionarea si amplasarea conductei de beton DN 300
Lungime:
16 m
Aprovizionarea si amplasarea elementelor in cascad
Lungime:
5 buc.
Echipamente utilizate: Buldozer, Excavator echipamente grele cca. 40%
Buldozer, Excavator echipamente mici cca. 40%
Lucru manual cca. 20 %
Compactor cu cilindru, mai compactor cca. 100%
Furnizarea i amplasarea stratului mineral de impermeabilizare (argil, silt,

lehm/argil nisipoas), grosime 0,5 m inclusiv mbinarea acestuia cu terenul


existent (rambleu) sub piatra concasat 16/63
Volum: 1800 m3
Echipamente utilizate: Buldozer, Excavator echipamente grele cca. 40%
Buldozer, Excavator echipamente mici cca. 40%
Lucru manual cca. 20 %
Compactor cu cilindru, mai compactor cca. 100%
Amplasarea geotextilului sub anurile de scurgere
Suprafa: 5.500 m
Echipamente utilizate: Excavator echipament mic cca 50%
Lucru manual cca. 50 %

EuropeAid/123052/D/SER/RO
stage: October 2010-10-22
/var/www/apps/conversion/tmp/scratch_7/333984583.doc

page 9 of 17

Technical Assistance for Preparation of 5 projects


in the Environment Sector.
EuropeAid/123052/D/SER/RO
Consortium C&E Consulting and Engineering GmbH
Louis Berger SAS Poyry Environment GmbH

5.7 Bazinul de retenie a apelor pluviale


Realizarea unui bazin de retenie a apei pluviale, inclusiv lucrri de terasamente,
inclusiv totalitatea echipamentelor i instalaiilor tehnice, conducte, cmine de vizitare i
amenajri ale terenului
Volum de retenie: 730 m3
Echipamente utilizate: Buldozer, Excavator echipamente grele cca. 60%
Buldozer, Excavator echipamente mici cca. 20%
Lucru manual cca 20 %
Compactor picior de oaie, compactor cu cilindru cca 100%

5.8 Instalaia pentru gazele din depozit i sistemul de colectare a


gazelor din depozit
Construirea puurilor verticale pentru gazele din depozit
Numr: 16
Furnizarea i instalarea conductelor de admisie
Lungime: approx. 2.590 m
Staie de colectare a gazelor, staie de comprimare, canal pentru condens i instalaie de
ardere a gazului
Echipamente utilizate: Macara mobil, Excavator echipamente grele cca. 60%
Macara mobil, Excavator echipamente mici ca. 30%
Lucru manual cca. 10 %
Compactor cu cilindru, mai compactor cca. 100%

5.9 Marcaje de amplasare temporare


Livrarea i montarea marcajelor de amplasare temporare
Cantitate: 10 buci
Echipamente utilizate: Excavator echipament mic cca. 50%
Lucru manual cca 50 %

EuropeAid/123052/D/SER/RO
stage: October 2010-10-22
/var/www/apps/conversion/tmp/scratch_7/333984583.doc

page 10 of 17

Technical Assistance for Preparation of 5 projects


in the Environment Sector.
EuropeAid/123052/D/SER/RO
Consortium C&E Consulting and Engineering GmbH
Louis Berger SAS Poyry Environment GmbH

5.10 Amenajarea terenului


Hidronsmnare cu specii locale
Suprafa: 63.000 m
Echipamente utilizate: Instalaie adecvat pentru nsmnare cca. 90%
Lucru manual cca. 10 %
Livrarea i aezarea unui covor de protecie mpotriva eroziunii din iut sau fibre din
nuc de cocos,, greutate unitar > 350 g/m, inclusiv dispozitive de prindere, inclinarea
pantei 1:2,5
Suprafa: 31.000 m
Echipamente utilizate: Excavator echipamente grele i echipamente speciale ale
Contractorului pentru amplasarea covorului anti-eroziune sau buldozer cu
grind de distribuie, inclusiv lucru manual 100 %

5.11 mprejmuire
Montarea unui gard din baghete de oel mpletite, cu nlimea de min 1,80m i protecie
mpotriva crrii.
Montarea porilor de intrare, cu lime total de: 4 m, respectiv 2 m
Porile vor fi realizate din baghete mpletite. Gardul i porile trebuie s fie galvanizate la
cald.
Lungimea total a gardului: approx. 1.360 m
Numr pori:
2 buc.

EuropeAid/123052/D/SER/RO
stage: October 2010-10-22
/var/www/apps/conversion/tmp/scratch_7/333984583.doc

page 11 of 17

Technical Assistance for Preparation of 5 projects


in the Environment Sector.
EuropeAid/123052/D/SER/RO
Consortium C&E Consulting and Engineering GmbH
Louis Berger SAS Poyry Environment GmbH

6 Realizarea sistemului final de impermeabilizare (faza 2)


9.1 Defriarea amplasamentului
ndeprtarea i eliminarea vegetaiei i a arborilor, inclusiv a rdcinilor din zona
depozitului de deeuri.
ndeprtarea covorului de iarb, a celui de protecie mpotriva coroziunii i a stratului de
iarb din ntreaga zon a depozitului. Materialul rezultat constituie proprietatea
Contractorului i trebuie ndeprtat corespunztor .
Suprafa 59.300 m
Used equipment: Dozer, Excavator Buldozer, excavator echipamente grele cca. 95% of
59.300 m2
(56.335 m2)
Excavator echipament mic, cca. 5% din 59.300m2 (2.965 m2)

9.2 Excavarea i mutarea stratului de acoperire temporar


Excavarea stratului de sol inert pentru acoperire temporar cu grosimea de 0,3 m din
zona depozitului, inclusiv transportarea n zona de depozitare intermediar a
Contractorului. De asemenea, mutarea i transportarea stratului de acoperire
temporar din zona de depozitare temporar a Contractorului i nivelarea excavarea,
umplerea, mprtierea, compactarea, avndu-se n vedere viitoarea suprafa a
depozitului
Volum: 17.800 m3
Echipamente utilizate: Buldozer, Excavator - echipamente grele cca. 80% din 17.800 m3
(14.240 m3)
Buldozer, Excavator echipamente mici, cca 10% din 17.800 m3
(1.780 m3)
Lucru manual cca. 10 % din 17.800m3 (1.780 m3)

9.3 Mutarea materialului (argil, silt) de pe drumul de acces


Mutarea materialului (argil, silt) de pe drumul de acces pe berme sau rampe, inclusiv
transportarea acestuia n zona de depozitare intermediar a Contractorului. De
asemenea, mutarea materialului (argil, silt) din zona de depozitare temporar a
Contractorului i i nivelarea excavarea, umplerea, mprtierea, compactarea,
avndu-se n vedere viitoarea suprafa a depozitului.
Volum: 2.500 m3
Echipamente utilizate: Buldozer, Excavator - echipamente grele cca. 80% din 2.500 m3
(2.000 m3)
Buldozer, Excavator echipamente mici, cca. 10% din 2.500 m3
(250 m3)
Lucru manual cca. 10 % din 2.500 m3 (250 m3)
EuropeAid/123052/D/SER/RO
stage: October 2010-10-22
/var/www/apps/conversion/tmp/scratch_7/333984583.doc

page 12 of 17

Technical Assistance for Preparation of 5 projects


in the Environment Sector.
EuropeAid/123052/D/SER/RO
Consortium C&E Consulting and Engineering GmbH
Louis Berger SAS Poyry Environment GmbH

9.4 Demontarea instalaiilor de colectare a gazului din depozit


Demontarea i mutarea evilor de gaz aprobate pentru instalaiile de gaz, inclusiv
racordurile i coturile sudate pentru aproximativ 10 m in jurul puurilor de gaz .
Materialele reutilizabile trebuie s fie curate, depozitate corespunztor n zona de
depozitare temporar a Contractorului i pstrate pentru reutilizare. Materialele care nu
pot fi reutilizate constituie proprietatea Contractorului i trebuie eliminate n mod
corespunztor.
Lungime: aprox . 190 m
Echipamente utilizate:
Excavator echipament uor cca 50%
Lucru manual cca. 50 %

9.5 Demontarea marcajelor temporare de amplasare


Demontarea marcajelor de amplasare existente pe materialul de acoperire temporar.
Toate materialele constituie proprietatea Contractorului i trebuie depozitate n mod
corespunztor.
Cantitate: 10 buci
Echipamente utilizate: Excavator echipament mic cca. 50%
Lucru manual cca. 50 %

9.6 Modificarea i extinderea sondei verticale de gaze


Mutarea liniei de conducte flexibile din oel inoxidabil i a tuturor celorlalte instalaii
pentru modificarea sondelor verticale de gaze extinderea acestora.
Cantitate: 16 buci
Echipamente utilizate: Excavator echipament mic cca. 50%
Lucru manual cca. 50 %

9.7 Realizarea ferestrelor de migraie a gazului


Construirea ferestrelor de migraie a gazului de 5 * 5 m, oferind o legtur direct ntre
corpul depozitului (grmada de deeuri) cu stratul de 0.3 m grosime pentru scurgerea
gazului (pietri 8/32). Stratul intermediar de acoperire trebuie ndeprtat complet de pe
aceste segmente.
Numr: 20 buci
Echipamente utilizate: Excavator echipament greu cca. 80%
Lucru manual cca. 20 %

EuropeAid/123052/D/SER/RO
stage: October 2010-10-22
/var/www/apps/conversion/tmp/scratch_7/333984583.doc

page 13 of 17

Technical Assistance for Preparation of 5 projects


in the Environment Sector.
EuropeAid/123052/D/SER/RO
Consortium C&E Consulting and Engineering GmbH
Louis Berger SAS Poyry Environment GmbH

9.8 Teren de ncercri


Construirea unui teren de ncercri, inclusiv dezafectarea sa complet n urma finalizrii
ncercrilor
Cantitate: 1
Echipamente utilizate: Buldozer, Excavator echipamente grele cca. 80%
Buldozer, Excavator echipamente mici cca. 10%
Lucru manual cca. 10 %
Compactor picior de oaie, Compactor cu cilindru, mai compactor cca100%

9.9 Nivelarea i compactarea corpului profilat al depozitului


Nivelarea - excavarea, umplerea, mprtierea, compactarea, avndu-se n vedere
viitoarea form a depozitului i nclinaiile prevzute ale pantelor i pregtirea fundaiei
pentru sistemul final de impermeabilizare
Suprafa: 64.600 m
Echipamente utilizate: Buldozer, Excavator echipamente grele cca. 60%
Buldozer, Excavator echipamente mici cca. 20%
Lucru manual cca. 20%
Compactor picior de oaie, Compactor cu cilindru, mai compactor cca.
100%

6.1 Construirea stratului de drenare a gazului de depozit


Furnizarea i amplasarea stratului de drenare a gazului de depozit, cu grosimea de 0.3 m
pe pante i platou.
Volum: 19.400 m
Echipamente utilizate: Buldozer, Excavator echipamente grele cca. 60% din 19.400 m
(11.640 m)
Buldozer, Excavator echipament mic cca. 30% din 19.400 m (5.820
m)
Lucru manual cca.10 % din 19.400 m (1.940 m)

6.2 Realizarea stratului mineral de impermeabilizare


Furnizarea i amplasarea stratului mineral de impermeabilizare (argil, silt, lehm), cu
grosime de 0,5 m, inclusiv compactarea i mbinarea acestuia cu terenul existent
Volum: 32.300m
chipamente utilizate: Buldozer, Excavator echipamente grele cca. 60% din 32.300 m

EuropeAid/123052/D/SER/RO
stage: October 2010-10-22
/var/www/apps/conversion/tmp/scratch_7/333984583.doc

page 14 of 17

Technical Assistance for Preparation of 5 projects


in the Environment Sector.
EuropeAid/123052/D/SER/RO
Consortium C&E Consulting and Engineering GmbH
Louis Berger SAS Poyry Environment GmbH

(19.380 m)
Bulozer, Excavator echipamente mici cca. 30% din 32.300 m (9.690 m)
Lucru manual cca. 10 % din 32.300 m (3.230 m)
Compactarea cu compactorul picior de oaie (primul strat) 16.150 m3
Compactarea cu compactorul cu cilindru (cel de-al doilea strat) 16.150 m3

6.3 Amplasarea geotextilului de separare


Furmizarea i amplasarea unui geotextil de separare ntre stratul mineral de
impermeabilizare i stratul de drenare, incluzndu-se i suprapunerile.
Suprafa: 10.000 m
Echipamente utilizate: Excavator echipament greu i echipamente speciale ale
Contractorului pentru aplasarea geotextilului, sau buldozer cu grind
de distribuie, inclusiv lucru manual 100 %

6.4 Realizarea stratului de drenare


Furnizarea i amplasarea stratului de drenare pentru apa de suprafa necontaminat,
stratul de drenare geosintetic (incluzandu-se si suprapunerile) pe pante i platou.
Volum: 54.500 m
Echipamente utilizate: Echipament special al Contraqctorului pentru amplasarea stratului de
drenare a geosinteticului sau buldozer cu grind de distribuie, inclusiv lucru manual 100%.

6.5 Amplasarea geotextilului permeabil sub prisma de drenaj


Furnizarea i amplasarea unui geotextil permeabil i de separare sub prisma de drenaj,
intre stratul de recultivare si prisma de drenare fiind incluse i suprapunerile.
Suprafa: 14.500 m i 4.000 m
Echipamente utilizate: echipamente speciale ale Contractorului pentru aplasarea geotextilului
inclusiv lucru manual 100 %

6.6 Realizarea stratului de cultur i a stratului vegetal


Furnizarea i aezarea nisipului/pietriului cu argil, grosime 0,85 m ca strat de
recultivare. Pmntul de cultur trebuie s fie stratificat, fr compactare. Pentru
transportarea intern a pmntului ctre locul de construcie, Contractorul trebuie s
defineasc pistele de transport, care trebuie re-afnate dup finalizarea ntregului proces
de transport.

EuropeAid/123052/D/SER/RO
stage: October 2010-10-22
/var/www/apps/conversion/tmp/scratch_7/333984583.doc

page 15 of 17

Technical Assistance for Preparation of 5 projects


in the Environment Sector.
EuropeAid/123052/D/SER/RO
Consortium C&E Consulting and Engineering GmbH
Louis Berger SAS Poyry Environment GmbH

Volum: 50.450 m
Echipamente utlizate: Buldozer, Excavator echipament mic cca. 80% din 50.450 m
(40.360 m)
Lucru manual cca 20 % din 50.450 m (10.090 m)
Fr compactare
Furnizarea i amplasarea solului vegetal (humus), grosime 0,15 m, ca strat de
recultivare. Stratul de cultur trebuie s fie stratificat, fr compactare. Pentru
transportarea intern a pmntului ctre locul de construcie, Contractorul trebuie s
defineasc pistele de transport, care trebuie re-afnate dup finalizarea ntregului proces
de transport..
Volum: 8.900 m
Echipamente utlizate: Buldozer, Excavator echipament mic cca. 80% din 8.900 m (6.670
m)
Lucru manual cca 20 % din 8.900 m (2.230 m)
Fr compactare

6.7 Montarea conductelor de colectare a gazului de depozit


Furnizarea i instalarea conductelor de suciune
Lungime: aprox. 2.600 m
Echipamente utilizate: Excavator echipamente mici cca. 70%
Lucru manual cca. 30 %

6.8 Prisma de drenaj


Furnizarea i umplerea cu piatr zdrobit sub form de prism de drenaj. Aceasta trebuie
amplasat pe geotextilul de filtrare dup fixarea geotextilului de protecie. Furnizarea i
amplasarea unui geotextil permeabil ntre prisma de drenaj i stratul de cultur.
Volum: 3.600 m
Echipamente utilizate: Buldozer, Excavator echipamente mici cca. 50% din 3.600 m
(1.800 m)
Lucru manual cca. 50 % din 3.600 m (1.800 m)

6.9 Drumuri de acces


Constrirea drumurilor finale de acces pe berme sau rampe sau n zona marginal.
Volum: 625 m
Echipamente utilizate: Excavator echipament mic cca. 100%
Compactor picior de oaie,compactor cu cilindru cca. 100%

6.10 Sistemul final de colectare i deversare a apelor de suprafa

EuropeAid/123052/D/SER/RO
stage: October 2010-10-22
/var/www/apps/conversion/tmp/scratch_7/333984583.doc

page 16 of 17

Technical Assistance for Preparation of 5 projects


in the Environment Sector.
EuropeAid/123052/D/SER/RO
Consortium C&E Consulting and Engineering GmbH
Louis Berger SAS Poyry Environment GmbH

Construirea canalelor finale de colectare i deversare a apelor de suprafa:


In acest proiect exist berme i cascade.
Profilele canalelor i conductele din zona marginal a depozitului i bazinul de retenie au
fost realizate o dat cu rigolele de colectare i deversare temporar a apelor de
suprafa.
La acel moment se realizeaz toate reparaiile, ntreinerea i modificrile necesare.

6.11 Marcajele de amplasament


Livrarea i fixarea marcajelor finale de amplasament.
Cantitate: 22 buci
Echipamente utilizate: Excavator echipament mic cca. 50%
Lucru manual cca. 50 %

6.12 Amenajarea terenului


Hidronsmnare cu specii locale
Suprafa: 59.300 m
Echipamente utilizate: Dispozitiv adecvat pentru nsmnare cu iarb cca. 90%
Lucru manual cca. 10 %
Livrarea i aezarea unui covor de protecie mpotriva eroziunii din iut sau fibre din
nuc de cocos,, greutate unitar > 350 g/m, inclusiv dispozitive de prindere, inclinarea
pantei 1:2,5
Suprafa: 27.250 m
Echipamente utilizate: Excavator echipamente mici i echipamente speciale ale
Contractorului pentru amplasarea covorului anti-eroziune
sau buldozer cu grind de distribuie, inclusiv lucru manual
100 %