GRAFIC EXECUTIE
Legenda
Gri inchis Responsabilitate toti participantii
Verde Responsabilitate Bau-Mark
Gri deschis Responsabilitate AG Steel Building&Cladding
Albastru Responsabilitate Etnis
Rosu Responsabilitate Electricall
Luna IV
tamana 1 saptamana 2 saptamana 3 saptamana 4
GRAFIC EXECUTIE PROIECT ANKO
Instalatii electrice
Montare priza pamant 1 zi
Instalatii electrice exterioare 10 zile
Instalatii electrice interioare 18 zile
Receptii probe 5 zile
Luna IV
tamana 1 saptamana 2 saptamana 3 saptamana 4
GRAFIC EXECUTIE PROIECT ANKO
Inchideri si compartimentari
Instalatii electrice
Montare priza pamant 1 zi
Instalatii electrice exterioare 10 zile
Instalatii electrice interioare 18 zile
Receptii probe 5 zile
Luna IV
saptamana 1 saptamana 2 saptamana 3 saptamana 4
Beneficiar: SC TERMOTOTAL PROD SRL
Obiectiv: Construire hala metalica
Loc., jud.: Gherla, jud. Cluj
Executant suprastructura: AG STEEL BUILDING&CLADDING
Lansare Sosire in
PU material
Nr. crt. Denumire material Furnizor comanda santier Punere in opera (zz/ll/aa) U.M. Cant. material
(eur/U.M.)
(zz/ll/aa) (zz/ll/aa)
1 Piese ancorare BAUROM 10/22/2015 10/29/2015 10/30/2015
2 Structura metalica si organe asamblare BAUROM 10/29/2011 11/20/2015 21.11-05.12.2015
3 Panouri sdw acoperis si tabla plana Megaprofil/Isopan 11/2/2015 12/4/2015 05-10.12.2015
4 Panouri sdw perete Megaprofil/Isopan 11/2/2015 12/7/2015 11-19.12.2015
5 Suruburi, profil etansare, silicon, spuma Mirad Tehnic 11/27/2015 12/4/2015 05-19.12.2015
6 Suruburi, profil etansare, silicon, spuma Mirad Tehnic 12/18/2015 1/8/2016 12-20.01.2016
7 J&B Coilprofil 12/14/2015 12/18/2015 21-22.01.2016
Pagina 12
A.G. Steel Building & Cladding
Bulevardul Poitiers Nr. 5A
Iasi - 700671 Romnia
+40 (332) 411 807 (T)
+40 (332) 815 811 (F)
+40 (732) 505 930 (M)
office@aktun.ro
www.aktun.ro
Pagina 13
Beneficiar: SC TERMOTOTAL PROD SRL
Obiectiv: Construire hala metalica
Loc., jud.: Gherla, jud. Cluj
Executant suprastructura: AG STEEL BUILDING&CLADDING
EVIDENTA UTILAJE
Lansare Sosire in
PU utilaj Cost total utilaj
Nr. crt. Denumire utilaj comanda santier Perioada folosire (zz/ll/aa) U.M. Cant.
(lei/U.M.) (lei)
(zz/ll/aa) (zz/ll/aa)
1 Macara structura metalica 11/16/2015 11/20/2015 20-27.11.2015 ora 56 100.00 5,600.00
2 Macara panouri sdw acoperis si perete 11/27/2015 12/4/2015 04-07.12.2015 ora 24 100.00 2,400.00
3 Nacela 11/16/2015 11/20/2015 20.11-19.12.2015 zile 26 198.90 5,304.00
4 Nacela 11/16/2015 11/20/2015 20.11-19.12.2015 zile 26 198.90 5,304.00
5 Nacela 12/17/2015 1/11/2016 11-22.01.2016 zile 11 198.90 2,187.90
TOTAL (lei): 20,795.90
TOTAL (lei): 26,14
Pagina 14
A.G. Steel Building & Cladding
Bulevardul Poitiers Nr. 5A
Iasi - 700671 Romnia
+40 (332) 411 807 (T)
+40 (332) 815 811 (F)
+40 (732) 505 930 (M)
office@aktun.ro
www.aktun.ro
1,540.00 200.00
660.00 200.00
600.00 450.00
600.00 450.00
200.00 450.00
3,600.00 1,750.00
26,145.90
fara TVA
Pagina 15
Beneficiar: SC TERMOTOTAL PROD SRL
Obiectiv: Construire hala metalica
Loc., jud.: Gherla, jud. Cluj
Executant suprastructura: AG STEEL BUILDING&CLADDING
EVIDENTA FURNIZORI
Pagina 16
A.G. Steel Building & Cladding
Bulevardul Poitiers Nr. 5A
Iasi - 700671 Romnia
+40 (332) 411 807 (T)
+40 (332) 815 811 (F)
+40 (732) 505 930 (M)
office@aktun.ro
www.aktun.ro
Pagina 17