Potkrovlje I

Kp=620.76 m2 MB30

Dp=16 cm (ugradnja betona po m3 gotovog elementa)

GN 400-606 4.1

Materijal:

Beton MB30 1.0 * (m3 svb./m3 GE) * 5958.67 din/m3 svb = 5958.67 din/m3 GE

∑M= 5958.67 din/m3 GE

Rad:

BV 1.0 Nc/m3 GE * 300 din/Nc = 300 din/m3 GE

BIII 1.0 Nc/m3 Ge * 200 din/Nc = 200 din/m3 GE

RII 0.15 Nc/m3 GE * 150 din/Nc = 22.5 din/m3 GE

∑R= 522.5 din/m3 GE

C= M + R * (K+1)= 5958.67 din/m3 GE + 522.5 din/m3 GE * (4 + 1) = 8571.17 din/m3 GE

Spravljanje betona [m3 svb.]

GN 400-201d

Materijal:

Cement 380 kg/m3 svb * 11.2 din/kg = 4256 din/m3 svb

Sljunak 1.25 m3 sljunka/m3 svb * 1300 din/m3 sljunka = 1625 din/m3 svb

Voda 0.16 m3 vode/m3 svb * 87 din/m3 vode = 13.92 din/m3 svb

∑M= 5894.92 din/m3 svb

Rad:

RII 0.085 Nc/m3 svb * 150 din/Nc = 12.75 din/m3 svb

∑R= 12.75 din/m3 svb

CB= M + R * (K + 1) = 5894.92 din/m3 svb + 12.75 din/m3 svb * (4 + 1) = 5958.67 din/m3 svb
Radna brigada

kp = 620.76 m2 * 0.16 m = 99.32 m3

BV = 1.0 , BIII = 1.0, RII = 0.15 → Nc/m3 GE

RII = 0.085 Nc/m3 svb * 1.015 m3svb/m3 GE = 0.0863 Nc/m3 GE → radnik koji spravlja beton

∑RII= 0.236 Nc/m3 GE

Nc/m3
kp [m3 GE] radnici Nc RD R D
GE
BV 1 99.32 12.42 13

99.32 BIII 1 99.32 12.42 13 1

RII 0.236 23.44 2.93 3


Jedna smena, radni dan je 8h.

Potkrovlje II

kp=393.04 m2 MB30

Dp=16 cm (ugradnja betona po m3 gotovog elementa)

GN 400-606 4.1

Materijal:

Beton MB30 1.0 * (m3 svb./m3 GE) * 5958.67 din/m3 svb = 5958.67 din/m3 GE

∑M= 5958.67 din/m3 GE

Rad:

BV 1.0 Nc/m3 GE * 300 din/Nc = 300 din/m3 GE

BIII 1.0 Nc/m3 Ge * 200 din/Nc = 200 din/m3 GE

RII 0.15 Nc/m3 GE * 150 din/Nc = 22.5 din/m3 GE

∑R= 522.5 din/m3 GE


C= M + R * (K+1)= 5958.67 din/m3 GE + 522.5 din/m3 GE * (4 + 1) = 8571.17 din/m3 GE

Spravljanje betona [m3 svb.]

GN 400-201d

Materijal:

Cement 380 kg/m3 svb * 11.2 din/kg = 4256 din/m3 svb

Sljunak 1.25 m3 sljunka/m3 svb * 1300 din/m3 sljunka = 1625 din/m3 svb

Voda 0.16 m3 vode/m3 svb * 87 din/m3 vode = 13.92 din/m3 svb

∑M= 5894.92 din/m3 svb

Rad:

RII 0.085 Nc/m3 svb * 150 din/Nc = 12.75 din/m3 svb

∑R= 12.75 din/m3 svb

CB= M + R * (K + 1) = 5894.92 din/m3 svb + 12.75 din/m3 svb * (4 + 1) = 5958.67 din/m3 svb

Radna brigada

kp = 393.04 m2 * 0.16 m = 62.89 m3

BV = 1.0 , BIII = 1.0, RII = 0.15 → Nc/m3 GE

RII = 0.085 Nc/m3 svb * 1.015 m3svb/m3 GE = 0.0863 Nc/m3 GE → radnik koji spravlja beton

∑RII= 0.236 Nc/m3 GE

Nc/m3
kp [m3 GE] radnici Nc RD R D
GE
BV 1 62.89 7.86 8

62.89 BIII 1 62.89 7.86 8 1

RII 0.236 14.84 1.86 2


Jedna smena, radni dan je 8h.